CITY OF SANTA CLARITA
a
AGENDA REPORT
CONSENT CALENDAR
CITY MANAGER APPROVAL:
DATE: April 27, 2021
SUBJECT: SANTA CLARITA SPORTS CENTER GYMNASIUM ROOF
REPLACEMENT, PROJECT P3031 - AWARD CONSTRUCTION
CONTRACT
DEPARTMENT: Public Works
PRESENTER: Damon Letz
RECOMMENDED ACTION
City Council:
1. Award a construction contract to Rite -Way Roof Corporation for the replacement of the
Santa Clarita Sports Center Gymnasium roof through Sourcewell Contract 062117-DAC in
the amount of $446,259 and authorize a contingency in the amount of $66,939, for a total
contract amount not to exceed $513,198.
2. Authorize the City Manager or designee to execute all contracts and associated documents,
subject to City Attorney approval.
BACKGROUND
The Santa Clarita Sports Center Gymnasium Roof Replacement Project, Project P3031, will
remove and replace the roofing material on the Santa Clarita Sports Center Gymnasium. The
roof replacement is part of the City of Santa Clarita's (City) comprehensive maintenance plan for
sustaining facilities Citywide and supports the Santa Clarita 2025 theme of Sustaining Public
Infrastructure.
The roof material is deteriorating at an accelerated rate, due to its age, and multiple leaks are
occurring throughout the building. Staff has attempted to patch and repair the roof, however,
several leaks recur each year due to roof membrane slippage. Based on the condition of the roof,
patch work is no longer an effective repair method and replacement is now needed. This project
will install a new roofing membrane on the entire building and provide a 20-year warranty on the
material. Completing this roofing replacement will prevent further water -related damage and will
ensure recreation programs are not adversely impacted.
Page 1
Packet Pg. 134
On July 11, 1995, the City Council approved the use of "piggyback" purchasing. This process
permits the City to place orders against a competitively -awarded, existing public agency
contract. The Sourcewell Contract 062117-DAC was competitively solicited and awarded on
August 17, 2017, and is valid through 2021.
Staff recommends awarding the contract to Rite -Way Roof Corporation, which is contracted
with the Sourcewell Cooperative purchasing agreement, in the amount of $446,259 and authorize
a contingency in the amount of $66,939, for a total contract amount not to exceed $513,198. The
requested contingency will cover hidden conditions, such as the replacement of plywood and
framing members damaged by years of water leaks.
ALTERNATIVE ACTION
Other action as determined by the City Council.
FISCAL IMPACT
Adequate funds are available in expenditure account P3031601-5161.001 (General Fund -
Capital) to support the recommended construction contract and construction support costs.
ATTACHMENTS
Location Map
Bid Proposal for Rite -Way Roofing Corporation (available in the City Clerk's Reading File)
Page 2
Packet Pg. 135
(13VNI N
(IOVNINOO NouonNISN03 allVMV IN3W33V-ld321 -ROOM wAE) OSOS) deW uoqeoo-j:juewtj3euv
P!OONI p
to
CY)
CL <
F-
Z
CL
ez-
�c
0
Work Order Signature Document
EZIQC Contract No.: CA08-SCI-R01-080719-RWR
FINew Work Order F—I Modify an Existing Work Order
Work Order Number.: 089947.00 Date: 03/23/2021
Work Order Title: Santa Clarita Sports Complex gymnasium roof replacement
Owner Name: City of Santa Clarita Contractor Name: Rite -Way Roofing Corporation
Contact: Mareia Wasef Contact: Bill LaMontagne
Phone: 661-670-0311 Phone: 909-350-8490
Work to be Performed
Work to be performed as per the Final Detailed Scope of Work Attached and as per the terms and conditions of
Sourcewell EZIQC Contract No CA08-SCI-R01-080719-RWR.
Brief Work Order Description:
Roof replacement of gymnasium building. Contractor to develop full scope of work for Owner review and approval.
Time of Performance Estimated Start Date: IWO () weeks .ru brri ttrll tiurne. Mat:=Hal lead time cuin�known, 16 eir 1 rernc;o (rinainufecrtuirer) once
executed contract is received,
Estimated Completion Date: 60 c alleiradaair days firorn start date
Liquidated Damages Will apply: N Will not a I : I...Ds shalll Ibe 1..,,000/'peir day
Work Order Firm Fixed Price: $446,259.47
Owner Purchase Order Number:
Approvals
City of Santa Clarita
Date Contractor Date
Work Order Signature Document Page 1 of 1
3/23/2021
t-�c el l Ilium,
Detailed Scope of Work
c _V�
,i m �'K: MKI
To: Bill LaMontagne From: Mareia Wasef
Rite -Way Roofing Corporation City of Santa Clarita
15426 Arrow Route 25663 Avenue Stanford
Fontana, CA 92335 Santa Clarita, CA 91355
909-350-8490 661-670-0311
Date Printed: March 23, 2021
Work Order Number: 089947.00
Work Order Title: Santa Clarita Sports Complex gymnasium roof replacement
Brief Scope: Roof replacement of gymnasium building. Contractor to develop full scope of work for
Owner review and approval.
Preliminary Revised �X Final
The following items detail the scope of work as discussed at the site. All requirements necessary to accomplish the items
set forth below shall be considered part of this scope of work.
See attached.
Subject to the terms and conditions of ezlQC Contract CA08-SCI-R01-080719-RWR.
Contractor
City of Santa Clarita
uaie
MIKtca
Scope of Work Page 1 of 1
3/23/2021
Contractor will supply all necessary labor, materials, and equipment to complete the following installation of a white 60 mil
thick Tremco TPA single -ply roof membrane to the building noted herein, per manufacturer's specifications (SEE
ATTACHED) and as follows:
1. Remove existing one layer of Built -Up Cap sheet roofing material, including wall flashings, down to wood deck and
haul away all debris. Existing coping metal to be removed and hauled away as trash. Demolition subcontractor to fill
out City -required CDMMP form.
2. Plywood deck replacement as necessary, not to exceed 10% allowance of total roof square footage, approximately
2200 SF. More than 2200 SF will result in supplemental work order for additional. Any portion of the allowance not
used during construction will result in credit to City, quantities to be confirmed by City Project Manager or Inspector.
3. Install one (1) layer of 1.8" Polyisocyanurate insulation over wood deck per manufactures specifications. Install 1/2"
sloped tapered polyisocyanurate insulation behind equipment curbs per manufactures specifications.
4. Mechanically attach one (1) layer of 1/4" Securock Glass Mat roof cover -board over insulation per manufactures
specifications.
5. Mechanically attach one (1) layer of White 60-mil. Tremco TPA single -ply roof membrane per manufacturer's
specifications to the field of the roof.
6. Fully -adhere one (1) layer of White 60-mil TPA single -ply membrane at all vertical walls and curb flashings with low
VOC bonding adhesive.
7. Flash, two (2) roof hatches, (7) HVAC equipment curbs, (15) exhaust fans, drains, and pipe penetrations per
manufacturer's specifications. Seal and caulk all terminations. Including ten (10) adjustable flashings, thirty-nine (39)
split pipe boots, ten (10) through wall clad metal scupper drains or over -flows, and four (4) cast iron roof drains and
overflows.
8. Approximately 550 LF of aluminum termination bar installed and sealed.
9. Install approximately 475 LF of new 24-ga. galvanized metal counter flashing.
10. Install approximately 850 LF of new 20" stretch out - 24-ga. Kynar finished coping metal and 22-ga. galvanized metal
cleat on parapet walls. Approximately eighty-five (85) cover plates at joints on coping included. Standard colors only.
11. Up to 300 lineal feet of walk -pads are included in bid to be install at roof access hatch and around serviceable HVAC
units.
12. Install approximately fifty (50) Dura-block pipe support hangers.
13. Supply a 20-year manufacturer's NDL warranty and a 2-year contractor workmanship warranty.
Clarifications:
• Roof removal and installation shall be per the above written scope of work details; the manufacturer's
specification as a recommendation only. All installations will adhere to manufacturer's recommendations to allow for
warranty issuance.
• Discount offered to the City of Santa Clarita, due to the CTC overage on the Tremco roof system and City's budget. See
proposal for details.
• Permits will be pulled by contractor, but at no -fee cost or reimbursable to contractor since costs were not
incorporated to this scope/proposal. Contractor will manage all inspections during construction.
• Payment schedule for this project shall include monthly invoicing with 5% retention until issuance of Notice of
Completion.
Fxrlucinnc-
Abatement and or testing of any kind, Light weight insulating concrete of any kind, Reglets, Lead sheets or Lead
flashings, Copper or Stainless Steel flashings, Gutters, Leader heads, Down spouts, Splash pans or blocks, Skylights,
Deck replacement over 10% allowance, Wood Nailers, Wood Blocking, Raising of any equipment curb or platform,
Tapered insulation other than behind units (done by framing), Roof hatch replacement, Roof accessories, Vapor
barrier, Expansion joints, Crickets, Any wood work Not called out above, Waterproofing, Deck Wall or Traffic Coatings,
Any mechanical work including disconnect and reconnect, Duct repair or sealing, Drain supply or installation, Interior
Damages, Interior protection, Temporary Roofing of any kind, Water testing, Scaffolding, Over time Wages, Shop
Drawings.
Contractor's Price Proposal - Summary
Date: March 23, 2021
Re: IQC Master Contract #: CA08-SCI-R01-080719-RWR
Work Order #: 089947.00
Owner PO #:
Title: Santa Clarita Sports Complex gymnasium roof replacement
Contractor: Rite -Way Roofing Corporation
Proposal Value: $446,259.47
Bond Fees $9,606.30
Discount-$60,000.00
New Tremco Roof System $392,331.85
Roof Deck Replacement Allowance $14,058.02
Roof Demolition $90,263.30
Proposal Total $446,259.47
Thisl total represents the correct total for the proposal. Any discrepancy between line totals,
sub -totals and the proposal total is due to rounding.
The Percentage of NPP on this Proposal: %
Contractor's Price Proposal - Summary Page 1 of 1
3/23/2021
Contractor's Price Proposal - Detail
Date: March 23, 2021
Re: IQC Master Contract #:
CA08-SCI-R01-080719-RWR
Work Order #:
089947.00
Owner PO #:
Title:
Santa Clarita Sports Complex gymnasium roof replacement
Contractor:
Rite -Way Roofing Corporation
Proposal Value:
$446,259.47
Sect. Item Mod.
uOM Description
Line Total
Labor Equip. Material (Excludes)
Bond Fees
1 01 22 16 00 0002
EA Reimbursable FeesReimbursable Fees will be paid to the contractor for eligible
$9,606.30
costs. Insert the appropriate quantity to adjust the base cost to the actual
Reimbursable Fee. If there are multiple Reimbursable Fees, list each one
separately and add a comment in the "note" block to identify the Reimbursable
Fee (e.g. sidewalk closure, road cut, various permits, extended warranty,
expedited shipping costs, etc.). A copy of each receipt shall be submitted
with the Price Proposal.
Quantity Unit Price Factor
Total
Installation 8,733.00 x 1.00 x 1.1000 -
9,606.30
Bond fees, 2% of $436,653.17
Subtotal for Bond Fees
$9,606.30
Discount
2 01 22 16 00 0002
EA Reimbursable FeesReimbursable Fees will be paid to the contractor for eligible
-$60,000.00
costs. Insert the appropriate quantity to adjust the base cost to the actual
Reimbursable Fee. If there are multiple Reimbursable Fees, list each one
separately and add a comment in the "note" block to identify the Reimbursable
Fee (e.g. sidewalk closure, road cut, various permits, extended warranty,
expedited shipping costs, etc.). A copy of each receipt shall be submitted
with the Price Proposal.
Quantity Unit Price Factor
Total
Installation-60,000.00 x 1.00 x 1.0000 -
-60,000.00
Project discount
Subtotal for Discount
-$60,000.00
New Tremco Roof System
3 07 22 16 00 0048
SF 2" Thick, R11.4, Polyisocyanurate, Roof Board Insulation
$73,062.53
Quantity Unit Price Factor
Total
Installation 22,000.00 x 2.24 x 1.4826
73,062.53
New 1.8" polyiso board installed over wood deck
4 07 22 16 00 0048 0125
MOD For Mechanically Fastened To Wood Or Steel, Deduct
-$4,566.41
Quantity Unit Price Factor
Total
Installation 22,000.00 x -0.14 x 1.4826
-4,566.41
5 07 22 16 00 0061
SF 1/4" Thick, R0.36, Glass -Mat, Roof Board Insulation (USG Securock
$63,277.37
Glass -Mat)
Quantity Unit Price Factor
Total
Installation 22,000.00 x 1.94 x 1.4826 -
63,277.37
Roof cover board installed over insulation per Manufacturer
6 07 22 16 00 0101
SF 3.5" Average Thickness (20.0 Average R-Value), 1 /2" Slope, Tapered
$2,988.92
Polyisocyanurate Board
Quantity Unit Price Factor
Total
Installation 400.00 x 5.04 x 1.4826
2,988.92
Tapered iso board installed behind equipment curbs
Contractor's Price Proposal - Detail
Page 1 of 3
3/23/2021
Contractor's Price Proposal - Detail Continues..
Work Order Number: 089947.00
Work Order Title: Santa Clarita Sports Complex gymnasium roof replacement
New Tremco Roof Svstem
7 07 51 13 00 0130
LF TremSEAL D General Purpose Sealant
$0.00
Quantity Unit Price Factor
Total
Installation 0.00 x 4.77 x 1.4826
0.00
Per Manufacturer's specification
8 07 51 13 00 0163
SQ 60 Mil Tri-Polymer Alloy (TPA) White Membrane
$183,284.94
Quantity Unit Price Factor
Total
Installation 255.00 x 484.80 x 1.4826 -
183,284.94
New TPA single ply membrane installation, 220 SQ mechanically attached in field area and 35 SQ fully
adhered in flashing/wall areas
9 07 51 13 00 0170
EA >1" To 4" Pipe Diameter, Prefabricated Tri-Polymer Alloy (TPA) Pipe Cone/Boot
$4,273.00
(Tremco)
Quantity Unit Price Factor
Total
Installation 39.00 x 73.90 x 1.4826
4,273.00
Approx 39 TPA pipe boots throughout roof area
10 07 51 13 00 0172
LF 36" Wide, Thermoplastic Tri-Polymer Alloy (TPA) Walkway Protection Pad
$6,204.68
(Tremco)
Quantity Unit Price Factor
Total
Installation 300.00 x 13.95 x 1.4826 -
6,204.68
New walkpads installed at roof access hatch and around serviceable HVAC units
11 07 51 13 00 0173
SQ Factory Coated Steel Fasteners And Steel Or Plastic Membrane Plates
$0.00
(Tremco)
Quantity Unit Price Factor
Total
Installation 0.00 x 50.20 x 1.4826 -
0.00
12 07 51 13 00 0185
SQ Low VOC, TPA Bonding Adhesive (Tremco)
$5,205.19
Quantity Unit Price Factor
Total
Installation 35.00 x 100.31 x 1.4826
5,205.19
Adhesive used for fully adhered portion of roof installation
13 07 51 13 00 0193
SF >10,000 SF 20 Year Roofing System Warranty
$7,561.26
Quantity Unit Price Factor
Total
Installation 25,500.00 x 0.20 x 1.4826
7,561.26
Tremco roof warranty
14 07 59 00 00 0002
LF Membrane Roofing Termination Barincludes fasteners and caulking.
$2,837.70
Quantity Unit Price Factor
Total
Installation 550.00 x 3.48 x 1.4826
2,837.70
New membrane term bar installed and sealed
15 07 71 13 00 0005
LF >16" To 22" Wide (Stretch -out), 24 Gauge, KYNAR 5009 Finish, Galvanized
$32,815.87
Steel Coping System With Galvanized Steel Cleats
Quantity Unit Price Factor
Total
Installation 850.00 x 23.83 x 1.4826 -
30,030.80
Demolition 850.00 x 2.21 x 1.4826 =
2,785.06
Remove existing and replace with new Kynar coping approx 20" stretch out
16 07 71 26 00 0006
LF 24 Gauge, Up To 12" Wide, Galvanized Steel Counter Flashing With Reglet
$8,655.05
Quantity Unit Price Factor
Total
Installation 475.00 x 12.29 x 1.4826
8,655.05
Installation of new counterflashing
17 23 05 29 00 0597
EA 5" x 6" x 20.2" Rooftop Support Base With 14 Gauge Galvanized Channel
$6,731.75
(Cooper B-Line Dura-Blok DB20)
Quantity Unit Price Factor
Total
Installation 50.00 x 90.81 x 1.4826 -
6,731.75
Pipe support hangers installed throughout
Contractor's Price Proposal - Detail
Page 2 of 3
3/23/2021
Contractor's Price Proposal - Detail Continues..
Work Order Number: 089947.00
Work Order Title: Santa Clarita Sports Complex gymnasium roof replacement
Subtotal for New Tremco Roof System
$392,331.85
Roof Deck Replacement Allowance
18 06 16 33 00 0005 SF 5/8" Thick CDX Plywood Roof DeckingApplied to wood rafters.
$8,186.92
Quantity Unit Price Factor
Total
Installation 2,200.00 x 1.99 x 1.4826 -
6,490.82
Demolition 2,200.00 x 0.52 x 1.4826 =
1,696.09
10% allowance of roof square footage total for plywood deck replacement
19 06 16 33 00 0005 0011 MOD For Selective Replacement <400 (Includes Removal Of Damaged Plywood And
$5,871.10
Fitting New Plywood To Size), Add
Quantity Unit Price Factor
Total
Installation 2,200.00 x 1.80 x 1.4826
5,871.10
Subtotal for Roof Deck Replacement Allowance
$14,058.02
Roof Demolition
20 01 74 19 00 0016 EA 40 CY Dumpster (5 Ton) "Construction Debris"Includes delivery of dumpster,
$3,973.19
rental cost, pick-up cost, hauling, and disposal fee. Non -hazardous material.
Quantity Unit Price Factor
Total
Installation 4.00 x 669.97 x 1.4826
3,973.19
Disposal of roof system demolition and general construction debris, approx 123 CY total for
existing roof
system demo
21 07 51 13 00 0068 SQ Demolish Cap Sheet Surfaced, Built Up Roofing Systemincludes protective
$86,290.11
surfacing.
Quantity Unit Price Factor
Total
Installation 251.00 x 231.88 x 1.4826 -
86,290.11
Demo one (1) layer of existing cap sheet roof system
Subtotal for Roof Demolition
$90,263.30
Proposal Total
This total represents the correct total for the proposal. Any discrepancy between line totals,
sub -totals and the proposal total is due to rounding.
The Percentage of NPP on this Proposal: %
$446,259.47
Contractor's Price Proposal - Detail Page 3 of 3
3/23/2021
so
111�1AN&I MIL,
Subcontractor Listing
Date: March 23, 2021
Re: IQC Master Contract #: CA08-SCI-R01-080719-RWR
Work Order #: 089947.00
Owner PO #:
Title: Santa Clarita Sports Complex gymnasium roof replacement
Contractor: Rite -Way Roofing Corporation
Proposal Value: $446,259.47
Name of Contractor
Duties
Amount
%
Klondike Construction Services
Roof demolition and disposal.
$60,000.00
13.45
Subcontractor Listing Page 1 of 1
3/23/2021