HomeMy WebLinkAbout1994-06-28 - AGENDA REPORTS - SANTA CLARA RIVER TRAIL PHASE I CONTRw AGENDA REPORT City Manager Approval Item to be CONSENT CALENDAR DATE: June 28, 1994 Rick SUBJECT: Award Contract for Construction of Santa Clara River Trail - Phase I DEPARTMENT: Parks, Recreation, and Community Services BACKGROUND The Parks, Recreation, and Community Services Department is preparing to construct the first phase of the Santa Clara River Trail system. The design has been completed and necessary permits are being obtained. The bid opening for this project was held on June 9, 1994. Phase I of the Santa Clara River Trail is located in the Canyon Country community on the north side of the Santa Clara River from the Soledad bridge to Sierra Highway. The trail will use the existing Los Angeles County Flood Control maintenance road. Where the maintenance road has not been improved, the City will install a new asphalt road. The road will be striped and signed for bicycle and pedestrian traffic. In addition, awooden split -rail fence will be installed on the river side for safety. There will be two undercrossings: at Whites Canyon bridge and under Sierra Highway. The undercrossings will be constructed of concrete with a pipe rail fence. There will be access gates throughout the length of the trail, with access ramps located at the Whites Canyon bridge and at Sierra Highway. The engineer's estimate for this project was $800,000.00. Twenty-eight bid packages were purchased and six contractors submitted bids on this project. There was a base bid and an add/deduct alternate #1. The base bid included all trail improvements previously described. Alternate #1 was for the installation of 250 lineal feet of channel protection between two areas of existing concrete linings. The bids received were as follows: CONTRACTOR LOCATION BASE BID Granite Construction Company Lancaster $ 689,213.00 C.A. Rasmussen, Inc. Simi Valley $ 697,431.25 Padilla Paving Company, Inc. Santa Clarita $ 706,598.25 Terra -Cal Construction, Inc. Baldwin Park $ 734,330.50 Nye & Nelson, Inc. Ventura $ 755,364.60 Union Engineering Company, Inc. Ventura $ 926,273.60 App��o BC D a r t� ��em. Santa Clara River Trail - Phase I June 28, 1994 Page 2 In an effort to save funding which can then be applied to future phases of the trail system, the Department is recommending to award on the base bid only. This project can be constructed without including bid alternate #1 at this time. Bids received for alternate #1 were approximately $90,000.00. Staff has completed the review of all bids, background references, and bonding companies, and has found that Granite Construction Company has the lowest responsible base bid and has the understanding and experience to install the trail per the plans and specifications. Funding for this project has been budgeted for fiscal year 1993-94 and is available in account #24-99018-227 in the amount of $812,000.00. RECOMMENDATION The City Council award the contract for the construction of the Santa Clara River Trail - Phase I to Granite Construction Company fora total of $689,213.00, and that an additional $70,000.00 be approved should any change orders become necessary, for a grand total of $759,213.00. Additionally, that the City Council authorize staff to issue a purchase order to Granite Construction Company in the amount of $759,213.00 from account #24-99018-227. REP:RJL.dis council/agscrtl.rep