HomeMy WebLinkAbout1994-07-12 - AGENDA REPORTS - LYONS AVENUE TRAFSIG0
AGENDA REPORT
City Manal
Item to be
Anthony J. Nisich_ 01
CONSENT CALENDAR
DATE:: July 12, 1994
SUBJECT: LYONS AVENUE AND SOLEDAD CANYON ROAD TRAFFIC SIGNAL
INTERCONNECT DESIGN CONTRACT
DEPARTMENT: Community Development
BACKGROUND
The project includes preparation of traffic signal modification and interconnect plans for
Lyons Avenue and Soledad Canyon Road to improve traffic flow in the east/west direction
through the City. The budget for the design and construction is as follows:
Soledad Canyon Road $330,000 (Account No. 1695024-227)
Lyons Avenue $419,000 (Account No. 1696076-227)
The funding for this project is shown on the attached agenda report, dated
December 14, 1993.
The staff received proposals for professional services from nine firms as follows:
Firm Name
Kimley-Horn
Austin -Foust
Willdan
JHK
Korve
A. Grover
Transtech
Meyer, Mohaddes
Barton-Aschman
Location
Orange
Santa Ana
Industry
Pasadena
San Bernardino
Fullerton
Walnut
Los Angeles
Irvine
Based on technical qualifications and methodology for the project, Meyer, Mohaddes
Associates, Inc. is the recommended firm. Staff has negotiated a price of $81,080,00 for these
services. APPROVED
LYONS AVENUE AND SOLEDAD CANYON ROAD
TRAFFIC SIGNAL INTERCONNECT DESIGN CONTRACT
July 12, 1994 - Page 2
RECOMMENDATION
That Council direct the Mayor to execute a contract with Meyer, Mohaddes Associates, Inc.
in the amount of $81,080.00, subject to the approval of City Attorney as to form.
ATTACHMENT
Agenda Report - December 14, 1993
Location Map
BRB:hds:lkl
..61%e;g.AbA
AGENDA REPORT
CONSENT CALENDAR
DATE: December 14, 1993
prove
Ity Ma /g
Item to be presented by:
Anthony J. Nisic!(%
SUBJECT: MEMORANDUM OF UADERSTANDING FOR THE
SIGNAL INTERCONN.lWT, SIERRA HIGHWAY RE
CANYON TRAFFIC SIGNAL INTERCONNECT (PHI
DEPARTMENT: Community Development
BACKGROUND -
mbyAVENUE TRAFFIC
IIPING AND SOLEDAD
9) PROJECTS
The Los Angeles County Metropolitan Transportation Authority (LACMTA) has award
Improvement grants totaling $784,000 for the above projects. t
MTA procedures require that ed street
rtify that matching funds will
Memorandum of Understanding (MOU) be executed and that Council Ce
be made available to complete each project. The status of the three projects is provided below.
Lyons Avenue Signal Interconnect
• The local matching funds required for this project ($168,000) have been set aside In a TDA
Article 8 Grant match account for FY 1993.94.
The LACMTA has awardeda th$251,D00 discretionarygrant for this project for use in FY 1993-94.
Staff estimates at the total cost for this project will be $419,000.
It Is anticipated that $120,000 will be utilized In FY 1993.94 for design work. The remaining
funds will be needed In FY 1994.95.
Sierra Highway Restrloe
The local matching funds required for this project ($110,000) have been set aside In a TDA
Article 8 Gram match account for FY 1994.95.
The LACMTA has awarded a $328,000 discretionary grant for this project for use In FY 1994-95.
Staff estimates that the total cost for this project will be $438,000.
Soledad Canyon Interconnect phase 11
• Local matching funds required for this project ($69,000) flays been aside In a TDA Article 8
grant master account for FY 1994-95.
Agenje oem
''a�"
MEMORANDA OF UNDERSTANDING
Page 2
Budget has not yet been authorized for this project.
The LACTC has awarded a $230,000 discretionary grant for this project.
Staff estimates that the total cost for this project will approach $330,000
RECOMMENDATION
1. Adopt Resolution No. 93.31, certifying that matching funds will be made available to completi
the subject projects and authorizing the City Manager to execute the necessary Memoranda ccc
Understanding on behalf of the City.
2. Direct staff to bring before the Public Financing Authority the necessary actions to appropriate
$100,000 of PFA funds from the Valencia/Soledad Restriping project to a new Soledad Canyon
Traffic Signal Interconnect project as a substitute project (see Item 5 below).
3. Authorize a budget appropriation for the Soledad at Santa Clara River ("Camp Plenty") Bridge
Widening project as follows:
Account No. 25-95003-227 $1.25 million LACTC Grant
6�1 4. Authorize that work proceed on the Valencia/Soledad Restriping project and that budget be
appropriated as follows: 0
Account No. 28-95020.227 $500,000 PFA Fund
Account No. 25-95020.227 $500,000 LACTC Grant
r 5. Authorize that work proceed on a new Soledad Canyon Traffic Signal Interconnect project and
that budget be appropriated as follows:
Account No. 28-95023-227 $100,000 PFA Fund
Account No. 25-95023-227 $230,000 LACTC Grant
6. Direct staff to adjust revenue accounts as required to reflect amounts to be received from the
LACTC grants and PFA fund.
ATTACHMENTS
1. Resolution No. 93.31
2. Memorandum of Understanding for the 1-5/Route 14 Metrolink Corridor Access Soledad Canyon
Bridge Widening Project
3. Memorandum of Understanding for the 1-5/Route 14 Metrolink Corridor Access Widening/Traffic
Signal System and Improvements Project
4. Memorandum of Understanding for the 1-5/Route 14 Metrolink Corridor Access Signal
Interconnect Project
Note: Resolution No. 93-31 Is attached. Memoranda of Understanding are available in the reading
file in the City Clerk's office.
hds/re93-31.kdn
CITY OF SANTA CLAR.ITA
Vicinity Map
� .vE
WE 7
PROJI
L IM17
LYONS AVENUE FROM AlTERSTATE 5 6 TO ,.S.4AJ!!l FfffIVAIIDD RD.
1 � 3 `. �� 3 is S .-...... •'+ "� V
C�nyon
untry
•f i a 1' � 1 E.. J1_ �N
WETT PR9 CT Ll>Yl/T
EASE"- df�T L4 Jul'
MEND CANYDAI ED, FROM GOLDEN DAIf RD. TO GALETDA/ RD.
`5 PROJECT SITE
�CIT, 50 0pl �f r�
d1FT0,V RA
q POAD
ea
L
0
P
SANTA CLARITA
LOCATION MAP
NT$