HomeMy WebLinkAbout2026-09-22 - AGENDA REPORTS - FTM 83605 RIVERVIEWO
Agenda Item: 6
CITY OF SANTA CLARITA
.` AGENDA REPORT
CONSENT CALENDAR
CITY MANAGER APPROVAL:
DATE: September 22, 2026
SUBJECT: FINAL TRACT MAP FOR TRACT NO. 83605 (RIVERVIEW)
DEPARTMENT: Public Works
PRESENTER: Amalia Marreh
RECOMMENDED ACTION
City Council:
1. Approve Final Tract Map for Tract No. 83605.
2. Accept the following on behalf of the public the offer of dedication and grant of: (1) the
easements for public use and road purposes; (2) the easements for sanitary sewer and sanitary
sewer ingress and egress purposes; (3) all sanitary sewers and appurtenant structures; (4) the
easements for covered storm drain appurtenant structures and ingress and egress purposes;
(5) the easement for flood control purposes; (6) the easement for public use and sidewalk
purposes; (7) the easement for sight distance purposes; and (8) the right to restrict or prohibit
the erection or construction of any buildings or structures within the restricted use areas.
3. Make findings as follows: This project is consistent with the provisions of Sections 66474
and 66474.1 of the Subdivision Map Act and should be approved.
4. Instruct the Director of Administrative Services to endorse the Special Assessment Statement
on the face of Tract Map for Final Tract No. 83605, which indicates all special assessments
levied by the City of Santa Clarita are paid.
5. Instruct the City Clerk to endorse the City Clerk's Statement on the face of Final Tract Map
for Tract No. 83605, which embodies the approval of said map.
6. Instruct the City Surveyor to endorse the City Surveyor's Statement on the face of Final
Tract Map for Tract No. 83605, which provides for verification that the map is technically
correct.
Page 1
Packet Pg. 30
O
7. Instruct the City Engineer to endorse the City Engineer's Statement on the face of Final Tract
Map for Tract No. 83605, which provides for verification of substantial conformance with
the Tentative Parcel Map and all provisions of local ordinances and state laws applicable at
the time of approval.
BACKGROUND
The Final Tract Map for Tract No. 83605, a Location Map of which is attached, has been
reviewed by City of Santa Clarita (City) staff and found to be in substantial conformance with
the principles and standards required by the Unified Development Code and State Subdivision
Map Act. Tentative Tract Map 83605 was approved by the City Council on November 12, 2024,
under Resolution No. 24-71 for Master Case MC21-205, to allow for the subdivision of one
existing lot into five lots located at the former Saugus Speedway site.
Lots 1 through 4 provide for a total of 318 residential units, and lot 5 designated for a light
manufacturing building. Lot 5 is currently undergoing the development review process to allow
for a proposed residential use under separate discretionary application. The proposed Final Tract
Map is approximately 35.44 acres.
The Final Tract Map for Tract No. 83605 was reviewed to the satisfaction of the City Engineer
and found to be in substantial conformance with the previously approved tentative tract map. The
conditions of approval adopted by the City have been met and fees have been and/or will be paid
as indicated on the attached Fact Sheet. Therefore, the Tract Map for Tract No. 83605 is ready
for City Council approval.
Pursuant to CEQA Guideline 15162(a) no subsequent CEQA review is required for the actions
requested by this agenda item, because there are no substantial changes to the project or the
circumstances under which the project is being undertaken, and no new information of
substantial importance regarding the project has come to light triggering the need for subsequent
review. A separate application, for changes to Lot 5, is under review and will be addressed by the
City Council at a future meeting.
Pursuant to Section 66474.1 of the Subdivision Map Act, a legislative body shall not deny
approval of a final or parcel map if it was previously approved as a tentative map for the
proposed subdivision and if it finds the final or parcel map is in substantial compliance with the
previously approved tentative map.
ALTERNATIVE ACTION
Staff has not identified alternative actions that would conform to requirements set forth in the
Subdivision Map Act.
FISCAL IMPACT
The resources required to implement the recommended action are contained within the City's
adopted Fiscal Year 2026-27 budget.
Page 2
Packet Pg. 31
O
ATTACHMENTS
Location Map
Fact Sheet
Page 3
Packet Pg. 32
Packet Pg. 33
Attachment: Location Map (FINAL TRACT MAP FOR TRACT NO. 83605; RIVERVIEW)
6.b
FACTSHEET
TRACT NO.83605
Location: 22500 Soledad Canyon Road
Acreage: Approximately 35.44 acres
Number of Lots: Five (5) lots
Use: Subdivision of one (1) existing Mixed -Use Commercial lot, located at 22500
Soledad Canyon Road, into four (4) residential lots and one (1) non-residential
lot.
Owner: Millrose Properties California LLC
Trails/Paseos: No new trails are being dedicated to the City by this map.
B&T Fees: Bridge and Thoroughfare (B&T) fee(s) will be paid prior to issuance of
building permits.
Transit Fees: Transit Mitigation fee(s) will be paid prior to issuance of building permits
Quimby Fees: Quimby fee(s) will be paid prior to issuance of building permits.
School Fees: School fee(s) will be paid prior to issuance of building permits.
Packet Pg. 34