HomeMy WebLinkAbout1991-08-27 - AGENDA REPORTS - BOUQUET CYN RD PROJ 89 5 (2)CONSENT CALENDAR
DATE: August 27, 1991
SUBJECT:
DEPARTMENT:
BACKGROUND
AGENDA REPORT
City Manager Approval
Item to be presented b7:4
/—r-Lvnn M Harris
BOUQUET CANYON ROAD FROM CENTURION dWAY TO URBANDALE AVENUE
PROJECT N0. 89-5 - PROJECT ACCEPTANCE
Community Development
On February 12, 1991, Council awarded a contract for the subject project to
Granite Construction Company. Field work was completed and tentatively accepted
on May 10, 1991. The project was accepted by Caltrans and completed to the
satisfaction of. the Director of Community Development on July 24, 1991, for a
total construction cost of $461,325.45.
This project is eligible for Federal Aid Urban (FAU) funds, and has been
identified as FAU project No. M -Q064(005) CRP -2089 (300). Council approved FAU
Master Agreement 07-5450 and Program Supplement 001 on October 9, 1990. The
City is expected to receive $321,937.96 in federal funds toward the cost of this
project.
RECOMMENDATION
1. That Council accept the work performed by Granite Construction Company.
2. That Council direct the City Clerk to.file the attached Notice of Completion
for the project.
3. That Staff be directed to release the 5 percent retention 35 days after the
Notice of Completion is recorded; provided no stop notices as provided by
law have been filed.
ATTACHMENT
Notice of Completion of Public Improvement and Work
jcd/186
APPROVED Agenda Item:
When recorded please return to:
Donna Grindey, City Clerk
City of Santa Clarita
23920 Valencia Boulevard, Suite 301
Santa Clarita, California 91355
NOTICE OF COMPLETION OF
PUBLIC IMPROVEMENT AND WORK
NOTICE IS HEREBY GIVEN that the City of Santa Clarita, Los Angeles County,
California, has caused a public improvement, to wit:
PROJECT NO. 89-5
BOUQUET CANYON ROAD FROM CENTURION WAY TO URBANDALE AVENUE
to be constructed upon the property hereinafter described. The contract for
furnishing of all plant, labor, services, materials and equipment and all
utilities and transportation,. including power, fuel and water, and performing
all work necessary to construct. and complete, in a good and workmanlike manner
in strict accordance with the specifications, plans, and drawings therefore on
file in the office of the City Clerk of the City of Santa Clarita, for the
construction, installation, and completion of the above described public
improvement and work, was heretofore made and entered into with Granite
Construction Company on the 14th day of March, 1991, and filed for record in the
office of the City Clerk of the City of Santa Clarita; that the work upon said
public improvement was actually completed .on the 10th day -of May, 1991 and that
the Director of Community Development has notified the City Council that she has
made and completed a final inspection of the materials furnished and installed
and the work performed in the. construction, installation and completion of said
public improvement hereinabove more particularly described and set forth, and
has certified in writing to the City Council that all of the provisions of the
contract and contract documents for the furnishing of all plant, labor,
services, materials and equipment, and the performing of all work necessary for
the construction, installation and completion of said public improvement above
described have been fully complied with to her satisfaction as required by the
contract documents; that final acceptance of the construction, installation and
completion of said public improvement above described was made on the 10th day
of May, 1991 that the nature of the title to said property of said City of Santa
Clarita is as follows -- that is to say, it owns said public improvement in fee
except for the right-of-way upon which it is constructed, and that it owns an
easement upon, over and along said right-of-way for the purpose of the
construction, installation, and completion of said public improvement
hereinabove described and the use thereof after said completion; that the
property hereinabove referred to and on which said public improvement is
situated is described as follows:
BOUQUET CANYON ROAD FROM CENTURION WAY TO URBANDALE AVENUE
NAME OF SURETY ON MATERIAL AND LABOR BOND:
Federal Insurance Company
15 Mountain View Road
Warren, NJ 07060
DATED this day of
CARL BOYER, Mayor
City of Santa Clarita
STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES) ss
CITY OF SANTA CLARITA)
19
I certify or declare that under penalty of perjury that the foregoing is
true and correct.
ATTEST:
Donna M. Grindey, City Clerk
City of Santa Clarita
0
Date