HomeMy WebLinkAbout1991-06-11 - AGENDA REPORTS - TRAFFIC SIGNAL PROJ 90 19 (2).4,
CONSENT CALENDAR
DATE: June 11, 1991
AGENDA REPORT
City Manager Approval
Item to be presented b 4
John E. Medina
SUBJECT: VALENCIA BOULEVARD FROM CREEKSIDE ROAD TO BOUQUET CANYON ROAD
(PROJECT N0. 9 -19) TRAFFIC SIGNAL SYNCHRONIZATION
REQUEST TO AD RTISE FOR BIDS
DEPARTMENT: Public Work f`
BACKGROUND
Project No. 90-19 provides for installation of interconnect cables and conduits
along Valencia Boulevard from Creekside Road to Bouquet Canyon Road. The
existing "radio corrected time" equipped traffic signals along Valencia Blvd
will be replaced with a hard wire interconnect system; thus providing a more
flexible and reliable system and greater coordination with other traffic
signals. Once completed, the upgraded traffic signals will have the ability to
tie into the proposed Master Computer Control System being developed with the
mall.
$1009000 is currently budgeted for this work, and Account No. 25-96054-227 has
been established to track all costs associated with the project. Of this
amount, the City has been successful in securing State /Local partnership (SB
300) funding for this project,.which will amount to approximately 10 percent of
the contract cost.
Plans and specifications for this.project have been completed and are available
for review in the offices of the City Clerk and the Director of Public Works.
RECOMMENDATION
Approve the plans and specifications- for- this project, and authorize the
advertising for bids.
APPROVED
/Jed -82
Agenda Item: