HomeMy WebLinkAbout1991-10-22 - AGENDA REPORTS - WHITE CNY RD SIDEWALK IMPROV (2)P r'�
AGENDA REPORT
City Manager
Item to be presented
CONSENT CALENDAR
DATE: October 22, 1991
SUBJECT: WHITES CANYON ROAD AND BOUQUET CANYON ROAD (PROJECT NO. 90-4)
CURB, GUTTER AND SIDEWALK IMPROVEMENTS - PROJECT ACCEPTANCE
DEPARTMENT: Community Development
BACKGROUND
On January 29, 1991, Council awarded a contract for the subject project to Blois
Construction, Inc. This project was completed to the satisfaction of the
Director of Community Development on October 2, 1991 for a total construction
cost of $41,511.81. The construction period was extended three months due to
additional work for the repair of sunken pavement and broken curb on the east
side of Bouquet Canyon Road, adjacent to bridge over the Santa Clara River.
This project was completed within the overall budget for annual curb, gutter and
sidewalk maintenance projects.
1. That Council accept the work performed by Blois Construction, Inc.
2. That Council direct the City Clerk to file the attached Notice of Completion
for the project.
3. That Staff be directed to release the 10 percent retention 35 days after the
Notice of Completion is recorded, provided no stop notices as provided by
law have been filed.
ATTACHMENT
Notice of Completion of Public Improvement and Work
AGN:rm:532
1
-u-4 Item: i
When recorded please return to:
Donna Grindey, City Clerk
City of Santa Clarita
23920 Valencia Boulevard, Suite 301
Santa Clarita, California 91355
NOTICE OF COMPLETION OF
PUBLIC IMPROVEMENT AND WORK
NOTICE IS HEREBY GIVEN that the City of Santa Clarita, Los Angeles County,
California, has caused a public improvement, to wit:
PROJECT NO. 90-04
WHITES CANYON ROAD AND BOUQUET CANYON ROAD CURB, GUTTER AND SIDEWALK IMPROVEMENT
To be constructed upon the property hereinafter described. The contract for
furnishing ofall plant, labor, services, materials and. equipment and all
utilities and transportation, including power, fuel and water, and performing
all work necessary to construct and complete, in a good and workmanlike manner
in strict accordance with the specifications, plans, and drawings therefore on
file in .the office of the City Clerk of the City. of Santa Clarita, for the
construction, installation, and completion of the above described public
• improvement and work, was heretofore made and entered into with Blois
Construction Inc, on the 20th day of February 1991, and filed for record in the
office of the City Clerk of the City of Santa Clarita; that the work upon said
public improvement was actually completed on the 17th day of July, 1991 and that
the Director of Community Development has notified the City Council that he has
made and completed a final inspection of the materials furnished and installed
and the work performed in the construction, installation and completion of said
public improvement hereinabove more particularly described and set forth, and
has certified in writing to the City Council that all of the provisions 'of the
contract and contract documents for the furnishing of all plant, labor,
services, materials and equipment, and the performing of all work necessary for
the construction, installation and completion of said public improvement above
described have been fully complied with to his satisfaction as required by the
contract documents; that final' acceptance of the construction, installation and
completion of'said public improvement above described was made on the 2nd day of
October, 1991 that the nature of the title to said property of said City of.
Santa Clarita is as follows -- that is to say, it owns said public improvement
in fee except for the right-of-way upon which it is constructed, and that it
owns an easement upon, over and along said right-of-way for the purpose of the
construction, installation, and completion of said public improvement
hereinabove described and. the use thereof after said completion; that the
property hereinabove referred to and on which said public improvement is
situated is described as follows:
WHITES CANYON ROAD AND BOUQUET CANYON ROAD CURB, GUTTER AND SIDEWALK IMPROVEMENT
•
NAME OF SURETY ON MATERIAL AND LABOR BOND;
iInsurance Company of -the West
1111 East Katella, Suite 250
Orange, California 92667
DATED this day of 19
0
CARL BOYER, Mayor
City of Santa Clarita
STATE.OF CALIFORNIA )
COUNTY OF LOS ANGELES) ss
CITY OF SANTA CLARITA)
I certify or declare that under penalty of perjury that the foregoing is
true and correct.
ATTEST:
Donna M. Grindey, City Clerk
City of Santa .Clarita
1
S
Date