HomeMy WebLinkAbout1992-11-24 - AGENDA REPORTS - AGMT STATE LOCAL TRANS PROJ (2)CONSENT CALENDAR
DATE:
SUBJECT:
DEPARTMENT:
BACKGROUND
AGENDA REPORT
November 24, 1992
i
Clry Manager Approval
Item to be presented by:
`kA Anthony J. Nisich ► 4
PROGRAM SUPPLEMENT AGREEMENTS FOR
TRANSPORTATION PARTNERSHIP PROJECTS
Community Development
STATE/LOCAL
The State/Local Transportation Partnership Program identifies and participates In funding locally
supported projects, and the following projects have been previously approved by Caltrans for
participation in this program:
• 1991-92 Annual Overlay Program (Project No. 91-09 -Supplement Nos. 006, 008, and 011) -This
project provided for overlay of Newhall Avenue, Soledad Canyon Road, and Valencia Boulevard.
• Sierra Highway north of Soledad Widening and Restriping (Project No. 91.13 - Supplement
No. 007) - This project provided for dual left turn medlan, and widening of lane widths.
• Soledad Canyon Road east of Sand Canyon Road Widening (Project No. 91-04 - Supplement
No. 009) - This project provides for street, drainage, utility undergrounding, and street lighting
Improvements on Soledad Canyon Road between Sand Canyon Road and Shadow Pines
Boulevard.
• Commuter Rail Station (Project No. 91-17 - Supplement No. 010) = This project provided for
Commuter Rail, Street, and traffic signal Improvements.
Caltrans' procedures for the Partnership Program requires the execution of a Local Agency -State
Master Agreement. In addition, a Program Supplement must be executed for each approved project.
On January 28, 1992 Council. approved Master Agreement No. SLTPP•5450. At this time staff
recommends processing Supplement Nos. 006, 007, 008, 009, 010, and 011 forthe above mentioned
projects.
Approve Program Supplement Nos. 006 thru 011 to the State/Local Entity Master Agreement, and
direct staff to process this supplement through Caltrans.
ATTACHMENT
Program Supplement Nos. 006 thru 011 to State/Local
Agreement No. SLTPP-5450.
sitppsa.jcd
APPROVED
Transportation Partnership
_Prooram— --- —�
Agenda (tem:
Date:. September 28, 1992
PROGRAM SUPPLEMENT No. 006' Location: 07-LA-O-SCTA
to Project Number: SB93-5450(057)
STATE -LOCAL TRANSPORTATION I E.A. Number: 07-928623
PARTNERSHIP PROGRAM AGREEMENT NO. SLTPP-5450
This Program Supplement is hereby incorporated into the State -Local Trans-
portation Partnership Program Agreement for State Share Funds which was
entered into between. the Local Entity and the State on 03/09/92 and is
subject to all the terms and conditions thereof. This Program Supplement
is adopted in accordance with Paragraph 3 .of Article I of the aforemen-
tioned Master Agreement under authority of Resolution No.
approved by the Local Entity on (See copy,attached).
The Local Entity further stipulates that as a condition to payment of funds
obligated to this project, it accepts and will comply with any covenants or
remarks setforth on the following pages.
PROJECT TERMINI:
NEWHALL AVE.: SAN FERNANDO ROAD TO 5,500' NORTH
TYPE OF WORK: OVERLAY PAVEMENT LENGTH: 1.0 (MILES)
PROJECT CLASSIFICATION OR PHASE(S) OF WORK
[X] Construction/Construction Engineering/Contingencies
Estimated Cost State Share Funds Matching Funds
IFY93 $ 58843 Local OTHER OTHER
$ 313502 FY94 $ OI$ 254659I$ 0 $ 0
FY95 $ 0
CITY OF SANTA CLARITA STATE OF CALIFORNIA
Department of Transportation
By By
CHIEF, LOCAL STREETS AND ROADS
BRANCH
Date Date
Attest
Title
I hereby Certify upon my personal knowledge that budgeted funds are available for this encumpbrance:
Accounting Offic Date �/ L $ 58843.00
Chapter Statutes I Item Yearly Program ISCI Fund Source I AMOUNT
587 1992 2660.101•D42 92.93 20.25.010.100 C 258010 042.7 5884'
Page 1 of 2
0
07-LA-0-SCTA
SB93-5450(057)
SPECIAL COVENANTS OR REMARKS
DATE: 09/28/92
1. It is mutually understood between the parties that this
contract may have been written before ascertaining the
availability of legislative appropriation of funds, for
the mutual benefit of both parties, in order to avoid
program..and fiscal delays that would occur if the
agreement were executed after that determination was
made.
The total amount of State -Local Transportation
Partnership funds payable by the State.shall not exceed
$58843 to be encumbered and reimbursed as follows:
FY 92-93 $ 58843
FY 93-94 0
FY 94-95 0
Any increase in State Partnership funds will require a
revised program supplement.
Any decrease in State Partnership funds will require a
revised finance letter.
2. After completion of all work under this agreement and
• after all costs are known, LOCAL ENTITY shall have a
financial audit of the project costs performed. The audit
report is due by December 30th following the fiscal year of
the project completion and must provide specific responses
to the five criteria specified in paragraph 9 of the Master
Agreement.
•
3. The State Funds Share is calculated based on the lower
of the approved eligible application amount or the
eligible award amount.
4. within 120 days of project completion a Final Report of
Expenditures must be transmitted to the Caltran's District Local
Streets and Roads Engineer.
5. A Final Audit must be completed and transmitted to.the Caltran's
District Local Streets and Roads Engineer by December 30th (the
State fiscal year following project completion).
6. The Reimbursement Ratio for this Cycle 3 (92/93) project is
21.570.
Page 2 of 2
Date: September 28, 1992
PROGRAM SUPPLEMENT NO. 007_ Location: 07-LA-0-SCTA
to I Project Number: SB93-5450(060)
STATE -LOCAL TRANSPORTATION E.A. Number: 07-928624
PARTNERSHIP PROGRAM AGREEMENT NO. SLTPP-5450
This Program Supplement is hereby incorporated into the State -Local Trans,
portation Partnership Program.Agreement for State Share Funds which was
entered into between the Local Entity and the State on 03/09/92 and is
subject to all the terms and conditions thereof. This Program Supplement
is adopted in accordance with Paragraph 3 of Article I of the aforemen-
tioned Master Agreement under authority of Resolution No.
approved by the Local Entity on (See copy attached).
The Local Entity further stipulates that as a condition to payment of funds
obligated to this project, it accepts and will comply with any covenants or
remarks setforth on the following pages.
PROJECT TERMINI:
SIERRA HWY: SOLEDAD CYN RD. TO N/O SIERRA CROSS ST.
TYPE OF WORK: WIDEN AND RESTRIPE LENGTH: 1.1 (MILES)
PROJECT CLASSIFICATION OR PHASE(S) OF WORK
[X] Construction/Construction Engineering/Contingencies
Estimated Cost State Share Funds I Matching Funds
IFY93 $ 11847 Local I OTHEROTHER
$ 54924 FY94 $ 0 $ 43077 $ 0 $ 0
FY95 $ 0
CITY OF SANTA CLARITA STATE OF CALIFORNIA
Department of Transportation
By By
CHIEF, LOCAL STREETS AND ROADS
BRANCH
Date Date
Attest
Title
1 hereby Certify upon my n
persona( knowledge
that budgeted funds are available for this`encyuibrance:
Accounting officer/ML/;y moi Date $ 11847.00
Chapter Statutes I Item Year Program 18C1 Fund Source AMOUNT
587 1992 2660.101.042 92.93 20.25.010.100 C 258010 042-T 11847.00
•
Page 1 of 2
r �
u
07-LA-0-SCTA
SB93-5450(060)
SPECIAL COVENANTS OR REMARKS
DATE: 09/28/92
1. It is mutually understood between the parties that this
contract may have been written before ascertaining the
availability of legislative appropriation of funds, for
the mutual benefit of both parties, in order to avoid
program and fiscal delays that would occur if the
agreement were executed after that determination was
made.
The total amount of State -Local Transportation
Partnership funds payable by the State shall not exceed
$11847 to be encumbered and reimbursed as follows:
FY 92-93 $ 11847
FY 93-94 0
•FY 94-95 0
Any increase in State Partnership funds will require a
revised program supplement.
Any decrease in State,Partnership funds will require a
revised finance letter.
• 2. After -completion of all work under this agreement and
after all costs are known, LOCAL ENTITY shall have a
financial audit of the project costs performed. The audit
report is due by December 30th following the fiscal year of
the project completion and must provide specific responses
to the five criteria specified in paragraph 9 of the Master
Agreement.
LJ
3. The State Funds Share is calculated based on the lower
of the approved eligible application amount or the
eligible award amount.
4. Within 120 days of project completion a Final Report of
Expenditures must be transmitted to the Caltran's District Local
Streets and Roads Engineer.
5. A Final Audit must be completed and transmitted to the Caltran's
District Local Streets and Roads Engineer by December 30th (the
State fiscal year following project completion).
6. The Reimbursement Ratio for this Cycle 3 (92/93) project is
21.57%.
I
Page 2 of 2
Date: September 28, 1992•
,.PROGRAM SUPPLEMENT NO. 008 Location: 07-LA-0-SCTA
to Project Number: SB93-5450(062)
STATE -LOCAL TRANSPORTATION E.A. Number: 07-928625
PARTNERSHIP PROGRAM AGREEMENT NO. SLTPP-5450 '
—14
This -Program Supplement is hereby incorporated into the State -Local Trans-
portation Partnership Program Agreement for State Share Funds which was
entered into between the Local Entity and the State on 03/09/92 and is
subject to all the terms and conditions thereof. This Program Supplement
is adopted in accordance with Paragraph 3 of Article I of the aforemen-
tioned Master Agreement under authority of Resolution No.
approved by the Local Entity on (See copy attached).
The Local Entity further stipulates that as a condition to payment of funds
obligated to this.project, it accepts and will comply with any covenants or
remarks setforth on the following pages.
PROJECT TERMINI:
VALENCIA BLVD.: MCBEAN PARKWAY TO MAGIC MTN PARKWAY
TYPE OF WORK: OVERLAY PAVEMENT LENGTH: 0.8 (MILES)
PROJECT CLASSIFICATION OR PHASE(S) OF WORK
[X] Construction/Construction Engineering/Contingencies
Estimated Cost State Share Funds
IFY93 $ 50996
$ 236420 FY94 $ OI$
FY95 $ 0
CITY OF SANTA CLARITA
By
Date
Attest
Title
Matching Funds
Local OTHEROTHER 111854241$ 01$ 0
STATE OF CALIFORNIA
Department of Transportation
By
CHIEF, LOCAL STREETS AND ROADS
BRANCH
Date
I hereby Certify upon my personal knoiyledge that budgeted funds are available for this encumbrance:
Accounting Off icEV y"1V-yy1&W C (aZ4C-T Date
Chapter statutes I Item t ^ y4p-'i Program
LL $ 50996.00
ISCI Fund Source
AMOUNT
587 1992 2660-101.062 92.93 20.25.010.100 C 258010 062-T 50996.00
Page 1 of 2
•
07-LA-0-SCTA DATE: 09/28/92
SB93-5450(062)
SPECIAL COVENANTS OR REMARKS
1. It is mutually understood between the parties that this
contract may have been written before ascertaining the
availability of legislative appropriation of funds, for
the mutual benefit of both parties, in order to avoid
program and fiscal delays that would occur if the
agreement were executed after that determination was
made...
The total amount of State -Local Transportation
Partnership funds payable by the State shall not exceed
$50996 to be encumbered and reimbursed as follows:
FY 92-93 $ 50996
FY 93-94 0
FY 94-95 0
Any increase in State.Partnership funds will require a
revised program supplement.
Any decrease in State Partnership funds will require a
revised finance letter.
2. After completion of all work under this agreement and
is
after all costs are known, LOCAL ENTITY shall have a
financial audit of the project costs performed. The audit
report is due.by December 30th following the fiscal year of
the project completion and must provide specific responses
to the five criteria specified in paragraph 9 of the Master
Agreement.
3. The State Funds Share is calculated based on the lower
of the approved eligible application amount or the
eligible award amount.
4. within 120 days of project completion a Final Report of
Expenditures must be transmitted to the Caltran's District Local
Streets and Roads Engineer.
5. A Final Audit must be completed and transmitted to the Caltran's
District Local Streets and Roads Engineer by December 30th (the
State fiscal year following project completion).
6. The Reimbursement Ratio for this Cycle 3 (92/93) project is
21.57%.
Page 2 of 2
Date: octcher 1992
PROGRAM SUPPLEMENT NO. 0091I Location: 07-LA-0-SCTA
to Project Number: SB93-5450(064)
STATE -LOCAL TRANSPORTATION E.A. Number: 07-928630
PARTNERSHIP PROGRAM AGREEMENT NO. SLTPP-5450
This Program Supplement is hereby incorporated into the State -Local Trans-
portation Partnership Program Agreement for State Share Funds which was
entered into between the Local Entity and the State on 03/09/92 and is
subject to all the terms and conditions thereof. This Program Supplement
is adopted in accordance with Paragraph 3 of Article I of the aforemen-
tioned Master Agreement under authority of Resolution No.
approved by the Local Entity on (See copy attached).
The Local Entity further stipulates that as a condition to payment of funds
obligated to this project, it accepts and will comply with any covenants or
remarks setforth on the following pages.
PROJECT TERMINI:
SOLEDAD CYN RD: E/O SAND CYN RD TO SHADOW PINES BL.
TYPE OF WORK: WIDEN ROADWAY AND STRIPING LENGTH: 2.1 (MILES)
PROJECT CLASSIFICATION OR PRASE(S) OF WORK
(X] Construction/Construction Engineering/Contingencies
Estimated Cost State Share Funds
FY
93 $ 539250
$ 2791880 FY94 $ 629591$
FY95 $ 0
CITY OF SANTA CLARITA
By
Date
Attest
Title
I hereby Certify upon my personal
Accounting Officer!
Matching Funds
Local OTHER-1OTHER
21896711$ p$ 0
STATE OF CALIFORNIA
Department of Transportation
By
CHIEF, LOCAL STREETS AND ROADS
BRANCH
Date
that budgeted funds are available for this encumbrance:
Date Jo/2142- $ 539250.00
Chapter Statutes I
V Item I Year ( Program 18cl Fund Source I AMOUNT
587 1992 2660.101-042 92-93 20.25.010.100
C 258010 042-T 53925
Page 1 of 3
E
is
E
07-LA-0-SCTA
5893-5450(064)
SPECIAL COVENANTS OR REMARKS
DATE: 10/02/92
PAGE: 2
1. It is mutually understood between the parties that this
contract may have been written before ascertaining the
availability of legislative appropriation of funds, for
the mutual benefit of both parties, in order to avoid
program and fiscal delays that would occur if the
agreement were executed after that determination was
made.
The total amount of State -Local Transportation
Partnership funds payable by the State shall not exceed
$602209 to be encumbered and reimbursed as follows:
FY 92-93 $ 539250
FY 93-94 62959
FY 94-95 0
This agreement is valid and enforceable only if
sufficient funds are made available by the California
State Legislature.
Any increase in State Partnership funds will require a
revised program supplement.
Any decrease in State Partnership funds will require a
revised finance letter.
2. After completion of all work under this agreement and
after.all costs are known, LOCAL ENTITY shall have a
financial audit of the project costs performed. The audit
report is due by December 30th following the fiscal year of
the project completion and must provide specific responses
to the five criteria specified in paragraph 9 of the Master
Agreement.
3. The State Funds Share is
of the approved eligible
eligible award amount.
calculated based on the lower
application amount or the
4. Within 120 days of project completion a Final Report of
Expenditures must be transmitted to the Caltran's District Local
Streets and Roads Engineer.
5. A Final Audit must be completed and transmitted to the Caltran's
District -Local Streets and Roads Engineer by December 30th (the
State fiscal year following project completion).
Page 2 of 3
����te: October 6, 1992
PROdRAlf BIIPPLEilLNT 0. f Luca�ion7 07-LA-0-SCTA
to project !lumbers SB93-5480(066)
BTATZ-LQCAL TII�[BpORTATION I E.Ae Fumbert 07-928638
k PARTMQUIP VROQ AX AUNZKZNT NO. SLTPP-5450
This Program Supplement is hereby incorporated into the State -Local Trans-
portation Partnership Program Agreement for state Share !hinds which was
entered into between the Local Entity and the State on 03/09/92 and is
subject to all the terms and conditions thereof. This Program Supplement
is adopted in aeaordance with Paragraph 3 of Article I of the aforemen-
tionad Kastar Agreement under authority of Resolution No. ,
approved by the Local Entity on (Seo copy attached).
The Local Entity further stipulates that as a condition to payment of funds
Obligated to this project, it' accepts and will comply with any covenants or
remarks setforth on the following pages.
PROJECT TLAXINI:
SOLBOAD CYN RDsO.75 KI E/O SOUQM CYN RD. -•/91-17
TT7E Or -WORKS CONST COMM=ER RAIL STATION 6 PARKING LZXQT8s Q.0 (MILES)
FRon= cLassiricATIOY OR lEA6E(a) or WORK
(X] Construction/Construction Engineering/Contingencies
Estimated coat State Share Funds I Matching Funds
• FY93 s 487698 Local OTHER OTHER
$ 2280220IFY95
PY94 $ OI$ 1792522I$ OI$ 0
$ 0
CITY or Sunk MARITAL STATE OF CALI7091IA
Department of Transportation
By By
CHIEF, LOCAL STREETS AND ROADS
BRANCH
Date Data
Attest
Titla
1 aareby Certify tame y paesmeal kn t
adpa tha�twhudpatd fueefa are ova{laAla fer to is ewet•�irmetes
Ld *n
Accounting OfficDate 6 s 487698.00
*up Carl 2NtVtr I Itr 1'or/raprr Sawa* Ierd •eAetOVrT
j Litt 1R2 2660.101-0e2 12-M 20.17.010.100 t 272010 042-7 4674".00
i
l•
i
Page 1 of 2
NOJ-04-'9e k�D 09:58 1D:37-L3&R TEL PO4 _1 1
07'�LA-O-SCTA
SB93-5430(066)
11�j
SPECIAL COVENANTS OR REMARKS
DATE: 10/06/91
PAGE: 2
I. It is mutually understood between the parties that this
contract $ay have been written before ascertaining the
availability of legislative appropriation of funds, for
the mutual benefit of both parties, in order to avoid
Program and fiscal delays that would occur if the
agreement were executed after that determination was
Lade.
The total amount of State -Local Transportation
Partnership funds payable by the State shall not exceed
$497698 to bo oncunbored and reimbursed as follows*
rY 92-93 6 48.7698
FY 93-94 0
FY 94-95 0
Any increase in. State Partnership funds will require a
revised program supplement.
Any decrease in State Partnership funds will require a
revised finance letter.
2. After completion of all work under this agreement and
atter all costs are known, LOCAL ENTITY shall have a
financial audit of the project costs performed. The audit
report is due by December 30th following the fiscal year of
the project completion -and must provide specific responses
to the five criteria specified in paragraph 9 of the luster
Agreement.
3. The State Funds Share is calculatedbased on the lower
of the approved eligible application amount or the
eligible award amount.
4. Within 120 days of project completion a Final Report of
Expenditures must be transmitted to the caltran's District Local
Streets and Roads Engineer.
5. A Sinal Audit must be eomplated and tranemitted to the caltrante
District Local Streets and Roads Engineer by December 30th (the
State fiscal year following project completion).
6. The Reimbursement Ratio for this Cycle 3 (92/93) project ie
11.57=.
Paga.2 of 2
s
•
�tes October 6, 1992
< PRo3sM SIIPPLEKENT�O.= WO& ont 07-LA-o-BCTA
to project Number: -8993-5450(063)
9TATR-LOCAL TRANSPORTATION E.A. Numbers 07-928637
• PARTNERSUP P OM= AGRZtMENT NO. SLTPP-5450
This Program supplement is hereby incorporated into the State -Local Trans-
portation Partnership Program Agreement for State Share fiends which was
entered into between the Local Entity and the state On 03/09/92 and is
subject to all the terms and conditions thereof. This Program Supplement
is adopted in accordance with Paragraph 3 of Article I of the aforemen-
tioned Baster Agreement under authority of Resolution No. ,
approved by the Local Entity on (see copy attached).
The Local Entity further stipulates that as a condition to payment of funds
obligated to this project, it accepts and will comply with any covenants or
remarks satforth on the following pages.
� PROJiCT T=9][INi:
i SOLEDAD CYN RD.: 3,00' TO 513001 L/O BOUQUET CYN RD
i
TYPz OF WORRs OVERLAY AND RECONSTRUCT PAVZMWT LRMCT$s 0.4 (HILt6)
PRWICT CLa00IlrCATION OR Tz"N (s) OF WORK.
(X) construction/Construction Engineering/Contingencies
I
Eatimated Costf State share Funds Matching Funds
FY9] $ 17206 Local OTHER II OTHER
$ 181753IFY943 $$ 00 6 164547 $ 0I$ 0
' CITY OT SANTA CLAAITA STATL 01 CAL170RWXA j
Department of Transportation
By BY
CHTV , LOCAL S
BRANCH
Date Date
Attest.
Title '
I herehy Certify upon W prramrl bwwtatge that baloatad funds are avella0la far thla aMubrann:
Accounting Offi nit Data 144-69-7w $ 17206.00
Chapter) status"' stem rser IQ Marr 1841 fund same. j MMMT
197 Ion 2i60.101-042 92.93 27.29.710.100 t 25s717 00.1 17276.00
Page 1 of 2
-- NUJ -64-'92 WED 69:59 ID:67-LS&R TEL
07-LA-O-SCTA
SH93-5450(063)
SPECIAL COVENANTS OR REUMS
x
poba
DATES 10/06/92
PAGES Z
1. it is mutually understood between the parties that this
contract stay nave been written before ascertaining the
availability of _legislative appropriation of funds, for
the mutual benefit of both parties, in order to avoid
progran and fiscal delays that would occur if the
agreement were executed after that deteraination was
made.
The total amount of Stata-Local Transportation
Partnership funds payable by the State shall not exceed
$17206 to be encumbered and reimbursed as followsi
rY 92-93 6 17106
rY 93-94 0
FY 94-95 0
Any increase in State Partnership funds will require a
revised program supplement.
Any decrease in State Partnership funds will require a
revised finance letter.
2. After completion of all work under this agreement and
after all coats are known, LOCAL ENTITY shall have a
financial audit of the project costs performed. The audit
report is due by December 30th following the fiscal year or
the project completion and must provide specific responses
to the five criteria specified in paragraph 9 of the Master
Agreement,
3. The State Funds Share is calculated based on the lower
of the approved eligible application amount or the
eligible award amount.
4. within 120 days of project completion a Final Report of
Expenditures must be transmitted to the Caltran's District Local
Streets and Roads Engineer.
5. A Final Audit must be completed and transmitted to the Caltrans
District Local Streets and Roads Engineer by December 30th (the
State fiscal year following project completion).
6. The Reimbursement Ratio for this Cycle 3 (92193) project is
21.376.
Page 2 of 2
I]
0