HomeMy WebLinkAbout1992-02-25 - AGENDA REPORTS - SOLEDAD CYN RD WIDENING PROJ (2)1
AGENDA REPORT
City Manager
Item to be D
CONSENT CALENDAR
DATE: February 25, 1992
SUBJECT: SOLEDAD CANYON ROAD EAST,OF SAND CANYON ROAD WIDENING
(PROJECT 91-04) - BID AWARD
DEPARTMENT: Community Development
BACKGROUND
On January 14, 1992 Council authorized the advertisement of the subject
project. The project consists of widening Soledad Canyon Road east of Sand
Canyon Road, to provide, at this time; two travel lanes in each direction and
left -turn pockets. Sufficient pavement will be ,provided to accommodate three
lanes in each directionwhen the bike way is 'relocated from the current
roadway. Also proposed is curb and gutter, sidewalks on the north. side, an
unlandscaped raised median, drainage structures, street lights, and the
installation of a traffic signal system on Soledad Canyon Road at the on/off
ramp of State Route 14.
To ensure a competitive bid process, this project was advertised with two bid
alternates. Alternative I provides for deposit of the grading material at the
County's Whites Canyon Bridge site. Alternative II provides for deposit of the
grading material, at the contractors chosen site.
On February 18, 1992 the following bids were received by the City Clerk:
Comoanv Bid Amount
ALTERNATE I (LLA, COUNTY DEPOSIT SITE)
1. Excel Paving Company $29791,880.94
2. D.W. Burhoe Construction, Inc. $2,802,781.93
3. Random Construction Company $20965,016.75
4. Security Paving Company, Inc. $3,014,915.09
5. Granite Construction Company $3,273,492.00
The Engineer's estimate for Alternate I of this project is $4.46 million.
Comnanv
ALTERNATE II (CONTRACTOR DEPOSIT SITE)
1. D.W. Burhoe Construction, Inc.
2. Excel Paving Company
3. Granite Construction Company
4. Random Construction Company
5. Security Paving Company, Inc.
Bid Amount
$2,689,066.93
$2,856,860.94
$3,153,267.00
$3,988,451.75
$5,061,785.09
Agenda lten%
r
STREET IMPROVEMENTS ON SOLEDAD CANYON ROAD
Page 2
The Engineer's estimate for Alternate II of this project is $4.69 million.
A total of $5.5 million has been budgeted under Account No. 25-95004-227 for
design, contract administration, inspection, and construction of this project.
In addition, this project is eligible for State/Local Partnership (SB 300)
funds, however, it appears that the City's share will be only between 10 and 15
percent of the actual contract costs.
Since the bids received for both alternates are lower than the Engineer's
Estimate, funds will be available to -fully landscape the raised medians. The
estimated cost necessary to complete this work is $865,000.00, which includes
engineering, inspection and contingencies. .The total estimated. cost, including
landscaping is $3.65 million, which is within the budgeted amount for this
project.
Pursuant to the provisions of the California Environmental Quality Act, the
Department of Community 'Development completed an Initial Study for this project
on February 12, 1992: Based on the information set forth in the 'Initial Study,
and with the incorporation of mitigation .measures identified therein, the
project will not have a significant adverse impact on the environment and a
Negative Declaration has been prepared. The Negative Declaration is currently
in the final week of the public review process, which will close on March 7,
1992. The Negative Declaration for this project will be set for the City
Council meeting on March 10, 1992 for final certification.
Staff recommends that the project be awarded to Excel Paving Co., the low bidder
for alternate I, because the County has agreed to accept all of the grading
material for this project. In addition, the County's Whites Canyon Bridge
(Phase III) has the environmental clearance to accept this material. Excel
Paving Co. possesses the necessary State Contractor's license and is a member in
good standing. This contractor has satisfactorily completed a similar project
for the City of Santa Clarita, and the references -indicated that the contractor
has performed satisfactory work.
RECOMMENDATION
1. Review for conceptual certification the Negative Declaration prepared for
the project and direct staff to prepare a resolution for adoption on March
10, 1992.
2. Award the contract to Excel Paving Co. in the amount of $20791,880.94
ATTACHMENTS
Initial Study
t
X
ENVIRONMENTAL ASSESSMENT
(Initial Study Form B)
CITY OF SANTA CLARITA
MASTER CASE NO: 92-013
Case Planner: Jeff Chaffin, Assistant Planner
Project Location: Two mile portion of Soledad Canyon Road between Sand Canyon
Road and Shadow Pines Boulevard, immediately north of the Antelope Valley
Freeway (State Route .14), in the eastern most portion of the City of Santa
Clarita.
Project Description and Setting: The applicant proposes to widen Soledad
Canyon Road from two traffic lanes to six traffic lanes. Initial grading and
paving will accommodate the full six lane width. Street striping will, be
phased: Initially from two lanes to four lanes, then from four lanes to six
lanes. The project includes right-of-way acquisition, grading and removal of
approximately 300,000 cubic yards of cut material, and constructing full
roadway improvements.
General Plan Designation: Primary Arterial, Community Commercial, Residential
Very Low, Residential Suburban, and Residential Moderate.
Zoning: A-1-1, A-2-1, and C-3.
Applicant: City of Santa Clarita.
Environmental Constraint Areas: Grading, dust, drainage.
A. ENVIRONMENTAL EFFECTS
YES MAYBE NO
1. Earth. Will the proposal result in:
a. Unstable earth conditions or in.changes in geologic
substructures? ....................................... [ ] [ I [XI
b. Disruptions, displacements, compaction or
overcovering of the soil? ........... [X] [ ] [ ]
c. Change in topography or ground surface relief
features? ......... :................................. [X] [ I [ I
d. The destruction, covering or modification of any
unique geologic or physical features? ............... [ ] [ I [X]
e. Any increase in wind or water erosion of soils,
either on- or off-site? ............................. [XI [ ] ( ]
f. Exposure of people or property to geologic hazards
such as earthquakes, landslides, mudslides, ground
failure, or similar hazards? ........................ [ I [ I [XI
g. Changes in deposition, erosion or siltation? ........ [X] [ ] El
YES MAYBE NO
c. Alteration of air movement, moisture, or temperature
or any change in climate, either locally or
regionally? ......................................... I l
d. Other? [ l
3. Water. Will the proposal result in:
a.
h.
Other modification of a wash, channel, creek, or
or the rate and amount of surface runoff? ...........
river? ..............................................
[ ]
i.
Earth movement (cut and/or fill) of 10,000 cubic
c.
Change in the amount of surface water in any
yards or more? .......................................
[X]
j.
Development and/or grading on a slope greater than
d.
Discharge into surface waters, or any alteration of
25Znatural grade? ..................................
[X]
k.
Development within the Alquist-Priolo Special
temperature, dissolved oxygen or turbidity? .........
Studies Zone? .......................................
[ ]
1.
Other?
I l
2. Air.
Will the proposal result in:
f.
a.
Substantial air emissions or deterioration of
through direct additions or withdrawals, or through
ambient air quality? ................................
[XI
b.
The creation of objectionable odors? ................
[XI
c. Alteration of air movement, moisture, or temperature
or any change in climate, either locally or
regionally? ......................................... I l
d. Other? [ l
3. Water. Will the proposal result in:
a.
Changes in absorption rates, drainage patterns,
or the rate and amount of surface runoff? ...........
[X]
b.
Alterations to the course or flow of flood waters?
[ ]
c.
Change in the amount of surface water in any
water body? .........................................
[ l
d.
Discharge into surface waters, or any alteration of
surface water quality, including but not limited to
temperature, dissolved oxygen or turbidity? .........
[XI
e.
Alteration of the direction or rate of flow of
ground waters? ......................................
[ l
f.
Change in the quantity of ground waters, either
through direct additions or withdrawals, or through
interception of an aquifer by cuts or excavations?
[X]
g.
Substantial reduction in the amount of water other-
wise available for public water supplies? ...........
[ ]
- 2 -
[ I [XI
[I II.
X
YES MAYBE NO
- 3 -
h. Exposure of people or property to water related
hazards such as flooding? ...........................
[ ] [ ]
[X]
i. Other?
[ ] [ ]
[ J
4.
Plant Life. Will the proposal result in:
a. Change in the diversity of species or number of
any species of plants (including trees, shrubs,
grasses, crops, and microflora)? ....................
[X] [ ]
( ]
b. Reduction of the numbers of any unique, rare or
endangered species of plants? .......................
[ J [ ]
[X]
c. Introduction of new species of plants into an area,
or in a barrier to the normal replenishment of
existing species? ...................................
[ ] [ ]
[X]
d. Reduction in acreage of any agricultural crop? ......
[ ] [ ]
[X]
5.
Animal Life. Will the proposal result in:
a. Change in the diversity of species, or numbers
of any species of animals (birds, land animals,
including reptiles, fish, insects or microfauna)? ...
[ ] ( ]
[X]
b. Reduction of the numbers of any unique, rare or
endangered species of.animals? ......................
[ ] [ ]
[XJ
c. Introduction of new species of animals into an
area, or result in a barrier to the migration or
movement of animals? ................................
[ ] [ ]
(X]
d. Deterioration to existing fish or wildlife habitat
and/or migratory routes? ............................
( J [ ]
[X]
6.
Noise. Vill the proposal result in:
a. Increases.in existing noise levels? .................
[ ] [ ]
[X]
b. Exposure of people to severe or unacceptable
noise levels? ....................................
[ 1 [ ]
[XJ
c. Exposure of people to severe vibrations? ............
[ ] [ ]
[X]
7.
Light and Glare. Will the proposal produce any
substantial new light or glare? .........................
[ J [ ]
[XJ
8.
Land Use. Vill the proposal result in:
a. Substantial alteration of the present land use
of an area? .........................................
[ J [ J
[XJ
- 3 -
YES MAYBE NO
b. A substantial alteration of the planned land use
of an area? ......................................... [ I
c. A use that does not adhere to existing zoning laws? [ ]
d. A use that does not adhere to established
development criteria? ............................... ( ]
9. Natural Resources. Will the proposal result in:
a. An increase in the rate of use of any natural
resources? .......................................... L 1
b. Substantial depletion of any nonrenewable natural
resources? .......................................... [ ]
10. Risk of Upset/Man-Made Hazards. Will the proposal:
a. Involve a risk of an explosion or the release.of
hazardous substances (including, but not limited to,
oil, pesticides, chemicals or radiation) in the
event of an accident or upset conditions? ........... [ ]
b. Use, store, transport or dispose of hazardous or
toxic materials (including, but not limited -to,
oil, pesticides, chemicals or radiation)? .........:. [ ]
c. Possible interference with an emergency response
plan or an emergency evacuation plan? ............... [ ]
d. Otherwise expose people to potential safety
hazards? ............................................ [XI
11. Population. Will the proposal:
a. Alter the location, distribution, density, or
growth rate of the human population of an area? ( ]
b.. Other? [ I
12. Housing. Will the proposal:
a. Remove or otherwise affect existing housing, or
create a demand for additional housing? [ ]
b. Other? [ ]
[ I [XI
[ I [X)
[ I [XI
[ I I l
[ I [Xl
[ I [XI
[ l [XI
[ I IXI
13. Transportation/Circulation. Will the proposal result in:
a. Generation of substantial.additional vehicular
movement? ........................................... I 1 [ I [XI
- 4 -
X
YES MAYBE NO
b.
Effects on existing parking facilities, or demand
for new parking? ....................................
[ I
[ l [XI
c.
Substantial impact upon existing transportation
systems, including public transportation? ...........
[ ]
[ I [X]
d.
Alterations to present patterns of circulation
or movement of people and/or, goods? .................
[ ]'
[ j [X]
e.
Increase in traffic hazards to motor vehicles,
bicyclists or pedestrians? ..........................
[ I
[ ] [X]
f.
A disjointed pattern of roadway improvements? .......
[-]
[ 1 [X]
14. Public Services. Will the proposal have an effect upon,
or
result in a need for new or altered governmental
services in any of the following areas:
a.
Fire protection? ....................................
[ l
[ I [XI
b.
Police protection? ..................................
[ I
[ I [X1
c.
Schools? ............................................
[ l
[ I [Xl
d.
Parks or other recreational facilities? .............
[ ]
[ ] [Xl
e.
Maintenance of public facilities, including roads?
[X]
[ ] [ ]
f.
Other governmental services? ........................
[ J
[ I [XI
15. Energy. Will the proposal result in.-
n:a.
a.
Use of substantial amounts of fuel or energy? .......
[ J
[ I [X]
b.
Substantial increase in demand upon existing
sources of energy, or require the development of
new sources of energy? ..............................
[ l
[ 1 [XI
16. Utilities. Will the proposal result in a need for new
systems, or substantial alterations to the following
utilities:
a.
Power or natural gas? ...............................
[ l
[ I [XI
b.
Communications systems? .............................
[ ]
[ I [XI
c.
Water systems? ......................................
[ ]
I I [XI
d.
Sanitary sewer systems? .............................
[ I
[ I [XI
e.
Storm drainage systems? .............................
[ I
[ I [Xl
- 5 -
X
YES MAYBE NO
f. Solid waste and disposal systems? ................... [ ]
g. Will the proposal result in a disjointed or
inefficient pattern of delivery system improvements
for any of the above? ................................ [ ]
17. Human Health. Will the proposal result in:
a. Creation of any health hazard or potential health
hazard (excluding mental health)? ................... [ ]
b. Exposure of people to potential health hazards? [ ]
18. Aesthetics. Will the proposal result in:
a. The obstruction of any scenic vista or view open
to the public? ...................................... L I
b. The creation of an aesthetically offgnsive site
open to public view? ................................ L I
c. The creation of a visual impact that is detrimental
to the surrounding area? [ ]
19. Recreation. Will the proposal result in an impact
upon the quality or quantity of existing recreational
opportunities? .......................................... [ l
20. Cultural Resources. Will the proposal result in:
a. The alteration of or the destruction of a historic
or prehistoric archaeological site? [ I
b. Any adverse physical or aesthetic effects to a historic
or prehistoric building, structure, or object? ...... [ ]
c. Does the proposal have the potential to cause a
physical change which would affect unique ,ethnic
cultural values? .................................... [ I
d. The restriction of existing religious.or sacred uses
within the potential impact area? ................... [ ]
DEPARTMENT OF FISH AND GAME "DE MINIMUS" FINDING
Will the project.have an adverse effect either individually
or cumulatively, on fish and wildlife resources? Wildlife
shall_ be defined for the purpose of this question as "all
wild animals, birds, plants, fish, amphibians, and related
ecological communities, including the habitat upon which
the wildlife depends for its continued viability•.
(Section 711.2; Fish and Game Code.) ........................ [ ]
[ I LXI
[ I [XI
[ I [XI
[ I [XI
[ I [XI
[N/A] [X]
Discussion of Impacts.
Section Answer and Evaluation of Impacts
1.a,d NO. Project grading will actually reduce the geologic instability
that is present on the site by reducing the steepness of cut
slopes on existing hillsides. The hillside grading portion of
this project is located along the north side of Soledad Canyon
Road, at the Antelope Valley Freeway on/off ramps, .extending
approximately 1400 feet to the east. The existing cut slopes are
steeper than 1:1. The proposed slopes will be constructed flatter
or equal to 1:1. The project site has not been identified as
possessing any unique geological or physical features. No
significant adverse impact to earth- stability or geologic
substructure is anticipated.
l.b,c,j YES. Grading activities will result in the removal of
approximately 300,000 cubic yards of earth. This grading will
change the existing topography and modify slopes that are
currently steeper than twenty-five percent (25X). The majority of
the grading activity will be conducted near the intersection of
Soledad Canyon and Sand Canyon Roads -and will result in slopes
that are less steep than are currently found on-site. A portion
of the terminal segment of an identified Significant Ridgeline
will be removed by project development. However, removal of this
previously graded portion of the ridge does not compromise the
visual integrity of the remaining ridgeline. The City's draft
Hillside Development and Ridgeline Preservation Ordinance does
provide exceptions for, Significant Ridgeline development for
projects which "...provide for public street access; facilities or
utilities to promote the public health, safety and general
welfare.' This project will increase the carrying capacity of
this road, thereby removing existing congestion and line -of -site
limitations, andimproving its level of safety and service.
Finally, the majority of the project site consists of previously
developed and undeveloped future roadway. No significant adverse
impact to soils, topography, and slopes in excess of 25Z is
anticipated.
l.e,g YES. Short-term increases in erosion will occur as a result of
grading and construction activities. These impacts can be reduced
to a less than significant level by using standard erosion control
management practices during the construction process. There is
minimal potential for long-term erosion impacts from the cut -slope
areas near the western end of the project. This potential impact
can be reduced to a less than significant level by using standard
revegetation and erosion control management practices.
l.f NO. The project does not involve locating people or property in a
geologic hazard area.. Existing steep slopes an a portion of the
project site will be made more stable (less steep) as a result of
project grading. No significant adverse impact is anticipated.
- 7 -
Section Answer and Evaluation of Impacts
l.h NO. The project will modify existing drainage improvements for
engineered channels. These modifications will be designed to
accommodate the runoff generated by this proposed six -lane
roadway. Such runoff and drainage will be conveyed to existing
storm drain facilities with adequate capacity. No creek, wash, or
any natural drainage will be modified by this project. No
significant adverse impact is anticipated.
l.i YES. The project includes the excavation and removal of
approximately 300,000 cubic yards of earth. This material.will be
deposited at the Whites Canyon Bridge project site, located
approximately one-half mile south-southwest of the intersection of
Soledad Canyon Road and Whites Canyon Road. This material will be
used by the County of Los Angeles for topography modification to
complete the extension of Whites Canyon Road across the Santa
Clara River to connect with Via Princessa (this County project
shall also provide public benefit by improving City-wide
circulation with access to and from the Antelope Valley Freeway.)
No significant impact is anticipated.
l.k N0. The project is not located in an .Alquist-Priolo Special
Studies Zone. No significant impact is anticipated.
2.a,b YES. Construction of the project will generate short-term
increases in dust (from grading) and exhaust emissions (from the
operation of construction equipment). An increase in particulate
emissions in the vicinity of this project will occur during
project construction. The amount of increase will vary with the
type and scale of activity and prevailing wind conditions. These
impacts can be reduced to a level of insignificance by,. using
standard air pollution control techniques during the construction
process, including: wetting of exposed soil; hydromulching bare
slopes; proper maintenance of heavy equipment; employment of
exhaust control devices; cessation of grading during high velocity
(30 miles per hour or more) wind periods.
Long-term air quality will be improved by the increased level of
service provided by widening this road from two lanes to six
lanes. The duration of vehicle trips will be reduced due to less
restricted traffic flow allowing vehicles to reach their
destinations in a shorter time period. No long-term or short-term
adverse air quality impacts are anticipated.
2.c NO. The project does not include any physical characteristics
that could restrict or alter the characteristics of the local and
regional climates. No significant adverse impact is anticipated.
3.a,d,f YES. The widening of Soledad Canyon Road may reduce the amount of
soil absorption, increase the amount of surface run-off, and
incrementally decrease. the quality of water (stormwater run-off)
draining to the Santa Clara River. The net increase of surface
run-off is expected to be small because the majority of the
10
Section Answer and Evaluation of Impacts
project site currently consists of paved roadway and steep
slopes. The existing pavement (approximately 1,267,500 square
feet) will be increased by 52,500 square feet for a 4Z increase of
the impermeable surface area. The corresponding proportional
run-off increase is expected to be negligible. Most precipitation
that occurs in the project area is conveyed to the Santa Clara
River. No significant impact to water quality or quantity .is
anticipated.
3.c N0. The increase of stormwater flow to the Santa Clara River is
expected to be very minor. All existing and future run-off will
be conveyed to existing and improved drainage facilities with
adequate capacity. No significant impact is anticipated.
3.b,e,g,h N0. The project site is not located within a flood hazard area
(per FEMA Community Panel No. 060729 0365C), nor is. it occupied by
any "blueline" stream or drainage (per USGS Mint Cnyon Quadrangle
Map.) The project site has not been identified as an aquifer
recharge area. This project will not result in any further
disruption of the watershed due to the minor increase (41) of the
total area to be graded and paved. No significant impact is
anticipated.
4.a YES. Project construction will incrementally decrease the numbers
of various sage scrub species as natural habitat is lost to
development. . Most of the project area is paved and unpaved
roadway, Past habitat modification and removal (from roadway
construction and adjacent residential and commercial development)
have degraded habitat value and decreased species diversity -and
population. The small areas of natural vegetation (in the
immediate vicinity of the ridge) consist of plant species
associated primarily with the Riversidian Sage Scrub community,
which is not considered rare or endangered. No significant impact
is anticipated.
4.b,c,d N0. The project site does not exhibit the habitat characteristics
needed to sustain the Slender -horned Spineflower, the only
rare/endangeredplant species in the Santa Clarita Valley. No
prime agricultural land occurs on or adjacent to the site. No
significant impact to botanical resources is anticipated.
5.a,b,c,d N0. Project construction will not result in a change of the
number and types of species as this roadway is widened. The small
existing areas of natural vegetation consist of animal species
associated primarily with the Riversidian Sage Scrub community,
which is not considered rare or endangered. Past habitat
modification and removal (from existing roadway construction and
adjacent residential and commercial development) have previously
degraded habitat value and decreased species diversity' and
population. This project will result in the incremental and
negligible loss of a previously disturbed and degraded habitat,
and may result in a corresponding loss of species population,
10
tJ
Section Answer and Evaluation of Impacts
which would be less than significant. The project site does not
contain, consist of, or connect any significant animal habitat.
It is also unlikely that new species of animals will be attracted
to a new roadway. No significant impact to zoological resources
is anticipated.
6.a,b.c N0. Short-term high noise and vibration levels may occur during
the construction of this project. These impacts can be reduced to
a less than significant level by controlling the hours and days of
operation. Because the project site is currently affected by
noise generated from the Antelope Valley Freeway, and the existing
portion of Soledad Canyon Road, no net increase of ambient noise
levels are -expected; traffic volumes should remain the same but
traffic flow rates will increase. Based upon this consideration,
no short or long-term adverse noise impacts are expected from this
project. No significant noise impacts are anticipated.
7. N0. Street lighting, designed to public safety standards, has
been included in this project. Light and glare are not expected
to increase above existing levels as a result of this project. No
significant impact is anticipated.
8.a,b,c,d N0. The primary existing and proposed land use on the project
site is Primary Arterial Highway as designated under the City of
Santa Clarita General Plan. This project will improve this
existing substandard road to a width of six lanes as required for
any road designated as, a Major Highway (as specified by the
General Plan and Zoning- Code.) This improved portion of Soledad
Canyon Road will provide better access and circulation for area
residents and businesses. No significant impact on land use is
anticipated.
9.a,b N0. The project will result in an incremental increase in the use
of natural resources, the loss of which is expected to be less
than significant in relation to increases normally associated with
development. No significant impact on natural resources is
anticipated.
10.a,b,c N0. No portion of the project interferes or conflicts with
existing emergency response and evacuation plans. The widening of
this portion of Soledad Canyon Road will improve. access, which
will be beneficial should an evacuation become necessary in the
future. The project does not include the use, storage, or
disposal of hazardous and toxic substances or create an additional
potential health hazard. No significant impact is anticipated.
10.d. YES. Some short-term safety hazards will occur during the
construction of the project. The potential hazards include heavy
equipment use, and disruptions to bicycle, pedestrian, and
automobile travel. The hazards from these disruptions will be
reduced to an insignificant level with' the preparation and
implementation of a Safety Program. This program will include the
stem
Section Answer and Evaluation of Impacts
phasing of project construction activities with appropriate public
noticing and advertisement, and route detouring with construction
personnel flagging the flow of traffic. Detouring routes around
the project area during construction will effect the approximately
400 dwelling units located within 500 feet of the project site,
and may effect a majority of the units in the area east of Sand
Canyon Road and north of the Antelope Valley Freeway. The haul
route for transporting the excavated material to the Whites Canyon
Bridge project site will be subject to the review and approval of
the City Engineer. The days and hours of use of the haul route
will be limited to minimize any traffic impacts which may occur.
The project will eliminate long-term safety hazards adjacent to
the roadway by providing a uniform width and six.through traffic
lanes, along with gutter curb and sidewalk, on this portion of
Soledad Canyon Road. Raised medians, street lighting, and signal
synchronization are also included to improve street safety. As
such, the long-term level of safety will be improved. No
significant safety impacts are anticipated.
11.a NO. This project in and of itself will not - influence population
growth, density, or distribution. However, improved circulation
and access may encourage land owners to pursue additional
residential and commercial development in the area serviced by
this roadway. Implementation of this project may enable
additional development in areas east of Sand Canyon Road. Any
future development on adjacent properties will be subject to City
review and approval on an individual basis. No significant impact
is anticipated.
12.a NO. The proposed project will not result in the removal or
relocation of any dwelling units. The short-term construction
related traffic impacts will effect the approximately 7,000
residents of the eastern -most portion of the City of Santa Clarita
(in that area commonly known as Canyon Country). These impacts
will be reduced to a less than significant level through the
preparation of a Public Information Program to inform residents of
the project, it's timing, and the.alternative routes that will be
available. The estimated duration of project construction is
approximately eight months. No significant housing impacts are
anticipated.
13.,a -f NO. The proposed widening of Soledad Canyon Road will not
generate additional vehicle traffic. However, improved traffic
circulation may encourage motorists to use this road as an
alternate or primary.access. Such an increase would be minor and
the overall level of service of the roadway will still be better
than that which exists. The traffic volume on this portion of
Soledad Canyon Road is approximately 25,000 vehicle trips per
day. The current peak hour Level of Service (LOS) is at level E.
No significant increase in traffic is expected upon completion of
this road widening, but peak hour traffic flow is expected to
-11-
Section Answer and Evaluation of Impacts
improve to LOS A. The proposed roadway improvements are expected
to reduce congestion along Soledad Canyon Road and result in
improved transit services to the area. The project will improve
the area travel pattern by eliminating. an existing disjointed
portion of Soledad Canyon Road. No .significant transportation or
circulation impacts are anticipated.
14.a-d,f NO. The construction of this project will not significantly
increase the demand for governmental services. No significant
impact is anticipated.
14.e YES. Many parts of the existing roadway are .in need of repair at
the present time. Construction of this project will reduce. these
repair needs. An incremental increase in the cost and demand of
roadway maintenance is expected to occur in the future due to the
increased width of Soledad Canyon Road. However, the need for
maintenance and the rate of repair work should be reduced, because
a wider roadway with the same volume of traffic would tend to wear
at a slower rate. No significant impact is -anticipated.
15.a,b N0. See discussion under Item 9.
16.a -g NO. The project does not require the significant alteration or
create a demand or need for these utilities. No significant
impact is anticipated.
17.a.b N0. See discussion under Item 10.
18.a,b NO. A majority of the existing roadway in this area appears
somewhat barren with little landscaping or other elements to
soften or buffer the streetscape. The ridge at the intersection
of Soledad Canyon Road and Sand Canyon Road has been previously
graded, which has resulted in unappealing visual characteristics.
The construction of the roadway, and removal of portions of the
existing cut slope on this ridge (near the intersection of Soledad
Canyon Road and Sand Canyon Road) will not increase existing poor
aesthetic_ quality; nor. will it obstruct any existing scenic
vista.
The planting of street trees and landscaped medians will improve
the aesthetic quality of this roadway. Also, impacts to all
graded slopes can be reduced. to a level of insignificance by
providing tree wells, appropriate drought tolerant and/or native
vegetation, and by contour grading. With these implementation
measures, this roadway improvement project is not expected to be
visually offensive. No significant impact is anticipated.
19. NO. The project will not impact the quality or quantity of
available recreational opportunities. This project will not
result in the loss of any recreational areas, nor will it hinder
the availability of any existing recreational opportunities. No
significant impact is anticipated.
-12-
Section Answer and Evaluation of Impacts
20.a,b,c N0. The project site consists of an existing roadway of varying
width, cut slope, and hillside. The site lacks the traditional
water, cover, and natural resources that would have attracted
prehistoric man to the site. In addition, the project site
contains no cultural or historic artifacts, or any other evidence
which indicate that this site could be culturally significant.
The City's archaeological resource maps do not identify this area
as being archaeologically sensitive.. No significant impacts to
cultural or historical resources are anticipated.
-13-
X
C. MANDATORY FINDINGS OF SIGNIFICANCE
Section 15065 of the California Environmental Quality Act states, in
part, that if any of the following can be answered yes or maybe, the
project may have a significant -effect on the environment and an
Environmental Impact Report shall be prepared.
YES MAYBE NO
1. Does the project have the potential to degrade the
quality of the environment, substantially reduce the
habitat of a fish or wildlife species, cause a fish
or wildlife population to drop below self sustaining
levels, threaten to eliminate a plant or animal
community, reduce the number or restrict the range of
a rare or endangered plant or animal or eliminate
important examples of the major periods of California
history or prehistory? ................................. [ J [ l [Xl
2. Does the project have the potential to achieve short-
term, to the disadvantage of long-term, environmental
goals? (A short-term impact on the environment is one
which occurs in a relatively brief, definitive period
of time while long-term impacts will endure well.into
the future.) ............................................ [ ] [ l [Xl
3. Does the project have impacts which are individually
limited but cumulatively considerable? (A project may
impact on two or more separate resources where the
impact on each resource is relatively small, but where
the effect of the total of those impacts on the
environment is significant.) ........................... [ ] [ ] [X]
4. Does the project have environmental effects which will
cause substantial adverse effects on human beings,
either directly or indirectly? [ ] [ ] [XJ
WEI!
D. DETERMINATION
On the basis of this Initial Study, it is determined that:
The proposed project COULD NOT have a significant effect on the
environment, and a NEGATIVE DECLARATION WILL BE PREPARED . ............... [ ]
Although the proposed project COULD have a significant effect on the
environment, there WILL NOT be a significant effect in this case
because the mitigation measures described in this Initial Study have
been added to the project. A NEGATIVE DECLARATION WILL BE PREPARED. [X]
The proposed project MAY have a significant effect on the environment,
and an ENVIRONMENTAL IMPACT REPORT is required . ......................... [ ]
LYNN M. HARRIS
DIRECTOR OF COMMUNITY DEVELOPMENT
CITY OF SANTA CLARITA, CALIFORNIA
Prepared By:
lid ` Jeff Chaffin, Assistant Planner �Z L
(S' re) V V. (Name/Title) at
Reviewed By:
(Signature)
(Name/Title)
JC/516
-15-
2 iy Z -
(AL) (Dat )
D Z�
( ate)