DATE: February 23, 1993
SUBJECT: Award of Contract for Valencia Meadows Park Pool Replaster
DEPARTMENT: Parks, Recreation, and Community Services
BACKGROUND
On February 3, 1993, the Parks, Recreation, and Community Services .Department successfully
completed the bid opening for the Valencia Meadows Park pool renovation. The renovation will
include replastering and new tile throughout the entire pool.
Construction is planned to start the beginning of March 1993, with completion scheduled 30 days
after. This schedule will allow Aquatics staff time to prepare for the summer aquatics program.
A total of two proposals were submitted to the City and publicly opened at 11:00 a.m. on
Wednesday, February 3, 1993. The base bid includes the removal of the old plaster in the pool
and the installation of new plaster. Alternate 1 includes the replacement of pool tile throughout
the pool. The following bids were received:
California Commercial Pools
Western Waterfeatures
Base Bid Alternate 1
$24,800 $ 6,500
$26,595 $ 7,900
The award of this contract is to be made to the lowest responsible base bid proposal. Staff is
recommending the purchase of the base bid and alternate 1 at this time. Approximately $35,000
was budgeted and is available in account number 01-9240-227 to complete this project. The total
contract amount is to include the following:
Base Bid $24,800
Alternate 1 6.500
Total $31,300
Agenda Item:
Award of Contract for
Valencia Meadows Park Pool Replaster
Page 2
RECOMMENDATION
It is recommended that the Valencia Meadows Park pool renovation contract be awarded to
California Commercial Pools in the amount of $31,300, and that an additional $3,000 be
encumbered which may become necessary for change orders once construction begins.