HomeMy WebLinkAbout1993-07-13 - AGENDA REPORTS - TRAFSIG INSTALL PROJ 95-022 (2)AGENDA REPORT
City Manager ApprovaAy:1 Item to be presented
Anthony J. Nisfch (pP%
CONSENT CALENDAR o
DATE: July 13, 1993
SUBJECT: TRAFFIC SIGNAL INSTALLATION AT THE INTERSECTION OF ORCHARD
VILLAGE ROAD AT DALBEY DRIVE - PROJECT NO. 95-022
AWARD PROJECT
DEPARTMENT: Community Development
BACKGROUND
On May 25,1993, Council authorized the advertisement of the subject project. The project provides
for the installation of a traffic signal and modification of the existing median at the intersection of
Orchard Village Road and Dalbey Drive.
On June 22, 1993 the following bids were received by the City Clerk:
Company Bid Amount
Steiny & Company, Fullerton, Ca. $91,500.00
Padilla Paving, Santa Clarita, Ca. $116,484.00
Evans & Sons, Santa Clarita, Ca. $122,037.00
The Engineer's Estimate to complete this project is $119,830.00. A total of $149,000.00 has been
budgeted under account #25-95022-227 for design, contract administration, inspection and
construction of this project.
Staff recommends that the project be awarded to Steiny and Company, the low bidder. The .
contractor possess the necessary state contractor's license and Is a member In good standing.
This contractor has completed similar projects for the City and the references indicated that the
contractor performed satisfactory work.
RECOMMENDATION
Award the contract to Steiny and Company In the amount of $91,500.00.
ATTACHMENT
Location Map
RPN; hd�s...a appG�OdC�D
Agenda item:
LYONS AVENUE
PROJECT N0, 95-002
VICINITY MAP