DATE: April 27, 1993
SUBJECT: TRAFFIC SIGNAL INSTALLATION AND STREET IMPROVEMENTS ON LYONS
AVENUE AT WAYMAN STREET - PROJECT NO. 91-10
DEPARTMENT: Community Development
BACKGROUND
On November 10, 1992, Council awarded a contract for the subject project to Hovey Electric. This
project was completed to the satisfaction of the Director of Community Development on
April 23, 1993, for a total construction, cost of $109,982.50 plus design, Inspection and
administration costs of approximately $30,000. The original budget amount was $196,400.
That Council accept the work performed by Hovey Electric, Inc.
2. That Council direct the City Clerk to file the attached Notice of Completion for the project.
3. That staff be directed to release the ten percent retention 35 days after the Notice of
Completion is recorded, provided no stop notices as provided by law have been filed.
ATTACHMENT
Notice of Completion of Public Improvement and Work