Loading...
HomeMy WebLinkAbout1994-11-22 - AGENDA REPORTS - PH PORTA BELLA DEVAGMT PLAN (2)i AGENDA REPORT i City Manager Approval Item to be presented by: Ha Rich Henderson PUBLIC HEARING DATE: November 22, 1994 SUBJECT: CONTINUED PUBLIC HEARING REGARDING THE PORTA BELLA SPECIFIC PLAN AND DEVELOPMENT AGREEMENT AS WELL AS THE THREE APPEALS FILED CONCERNING THE DECISION ON JUNE 21, 1994, BY THE PLANNING COMMISSION TO ADOPT A STATEMENT OF OVERRIDING CONSIDERATION; TO CERTIFY THE FEIR AND ADDENDUM SCH 92-041041; TO ADOPT A MITIGATION MONITORING PROGRAM; TO APPROVE VESTING TENTATIVE TRACT MAP 51599 AND OAK TREE PERMIT 91-033; AND TO RECOMMEND THAT THE CITY COUNCIL APPROVE SPECIFIC PLAN 91-001 AND CONSIDER DEVELOPMENT AGREEMENT 93-003. DEPARTMENT: COMMUNITY DEVELOPMENT BACKGROUND On November 8, 1994 the Council held a continued public hearing on this project in which they received a matrix summary of the responses to questions Council and the public have asked to date. Council took action on the three appeals. Community Development staff are following Council direction to gather documentation and draft conditions which address the appeals by Keysor-Century and the applicant. This information will be provided to Council in a subsequent meeting. ANALYSIS At the last meeting the Council expressed an interest in making confidential City Attorney letters regarding this case open to the public. The Council requested that the City Attorney address and advise them on the appropriateness and possible risk of doing such; Several alternative Magic/Princessa alignments have been submitted over the course of the Council hearings. The current alignment under consideration is the one shown on the map dated October 19, 1994. The question has been raised by the Council as to why bridges for Magic/Princessa are necessary over San Fernando Road and Oakdale Canyon. The EIR Traffic Study Appendix "J" identifies four reasons why a bridge is the only reasonable option for crossing San Fernando Road and the railroad tracks: Continued To: =gel Agenda Item:._.. 1) Due to railroad policies, construction of an at -grade crossing of the railroad for the Magic Mountain extension will require the closing of the Drayton crossing. The existing at -grade crossing at Drayton provides the only access to many businesses and properties in that area; 2) An undercrossing cannot be used because it is geometrically impossible to achieve acceptable grades to gain the elevations existing east of San Fernando Road; 3) The extensive delay analysis in the EER Traffic Study indicates that an at -grade crossing is unacceptable due to anticipated queue lengths. For example, at the time of train crossings, a queue of 120 cars is anticipated. Assuming that the roadway will have three lanes, this is a back-up of 40 cars per lane resulting in extreme traffic conditions; 4) There are also significant safety concerns posed by a major highway crossing a railroad which would need to be considered with an at -grade crossing. Concerns of neighboring residents about the Oakdale Canyon Bridge have centered around the location of the bridge in the Circle J open space, noise impacts and visual impacts. Noise impacts were addressed in the EIR Addendum which found the noise levels proposed by the Oakdale Bridge to be acceptable and the visual impacts to be less than significant.. There are, however, several options available to address resident concerns with the Oakdale Canyon bridge: 1) The canyon can be filled to accommodate the roadway. A berm could be constructed around the roadway which would result in greater noise attenuation and screen the roadway from view. Were the roadway to be located as presently shown on the plan, then the fill slope to support the road would be approximately 60 feet high. 2) The roadway could be moved on to Porta Bella property. This would address the concerns of the Circle J residents to reduce impacts upon their open space and lower noise levels. The roadway may be at a higher elevation which may increase its visibility to the surrounding area depending on whether a bridge or fill option is used. Moving the roadway onto the Porta Bella site may have internal project impacts due to the pedestrian orientation of the project, but these could be minimized if the roadway was designated a collector, rather than a highway. The Porta Bella project in itself does not need a highway to serve it. The project could be internally served by a collector street. The need for highways through the project is externally driven by the existing circulation constraints and anticipated ambient growth in the unincorporated County as well as the City. It is the City's General Plan and CTAC recommendation which show community serving major arterials crossing Porta Bella. The applicant is attempting to meet the City's General Plan in providing for an extension to Magic Mountain Parkway. Construction of major arterials in the City will impact existing property owners. Alignments may be designed and negotiated to minimize the need for relocation and condemnation, however, these issues are features of any large roadway development. Conditioning large land owners to build portions of arterials on their land as entitlements are given for that land reduces the need for condemnation and relocation. However, this type of roadway development policy is piecemeal and is not effective in developing arterials through already developed areas. It is not realistic to expect to build an east/west arterial through the center of the City, which is surrounded by developed areas, without impacting existing property and business owners.. Condemnation and relocation will be a necessary feature for completion of any of the City's General Plan arterials. No new environmental information has been presented to the Council which was not previously seen by the Planning Commission. The Commission specifically stated during their consideration of the project that they would limit their consideration on land use impacts, not financial ones which they felt was outside their purview. Nothing this far presented to the Council regarding land use issues would have changed the Commission's decision on this project. Financial impacts are not discussed in the EIR and Addendum because the California Environmental Quality Act (CEQA) specifically directs that economic impacts are not to be included in an EIR. The purpose of an EIR is to address only environmental, not financial, impacts. Therefore, the EIR and Addendum is not incomplete because it lacks a; fiscal analysis. A matrix of traffic improvements is attached. RECOMMENDATION 1. Receive staff report and reopen the continued public hearing; 2. Review the attached matrix of traffic; improvements and focus discussion on traffic circulation; 3. Direct staff as to the release of confidential letters from the City Attorney; 4. Continue the public hearing to the December 13, 1994, City Council meeting and return with appropriate documentation. ATTACHMENTS Matrix of Traffic Improvements CURRENT\PR CCRO5.LH9 INFRASTRUCTURE PHASING PLAN The land use assumptions for each phase of the development as outlined in the traffic study is shown below. Some uses have been reduced from the values assumed in the traffic study to reflect the reduction in the number of units proposed by the applicant. A. PHASE 1: Single Family Units 298 Multi Family Units 285 Commercial (Square Feet) 163,350 Office (Square Feet) 258,485 Business Park (Square Feet) -- Neighborhood Park (Acres) Driving Range (Acres) Recreational (Square Feet) School Church (Acres) -- Hotel (Rooms) TE -2 A total of 24 intersections will be significantly impacted as referenced In Table 8, page 51 of the Traffic Study. The mitigation measures Identified In Table 12, pages 58 to 62 shall be in place prior to issuance of occupancy permits for Phase 1. TE -3 A minimum of two new traffic signals (Magic Mountain Parkway/Rio Vista, Soledad Canyon Road/Santa Clarita Parkway) shall be In place prior to Issuance of occupancy permits for Phase 1. TE -4 Magic Mountain Parkway (Magic/Princessa) shall be extended with a minimum of four traffic lanes from San Fernando Road/Bouquet Canyon Road to Rio Vista Road prior to Issuance of occupancy permits for Phase 1. TE -5 Magic Mountain Parkway (Magic/Princessa) shall be extended with a minimum of two traffic lanes from Rio Vista Road to Rainbow Glen Drive prior to Issuance of occupancy permits for Phase 1. A maximum threshold of development may be permitted within Phase 1 prior to extending this roadway subject to the satisfaction of the City Traffic Engineer. TE -6 Santa Clarita Parkway shall be extended with a minimum of two traffic lanes from Soledad Canyon Road to "D" Street prior to Issuance of occupancy permits for Phase 1. TE -7 "D" Street shall be extended with a minimum of two traffic lanes from Santa Clarita Parkway to Main Street prior to Issuance of occupancy permits for Phase 1. INFRASTRUCTURE PHASING PLAN B. PHASE 2: Single Family Units 931 Multi Family Units 510 Commercial (Square Feet) 374,939 Office (Square Feet) 398,574 Business Park (Square Feet) 561,520 Neighborhood Park (Acres) 22.0 Driving Range (Acres) -- Recreational (Square Feet) 45,000 School One Church (Acres) 1.8 Hotel (Rooms) 140 TE -8 A total of 25 intersections will be significantly Impacted as referenced In Table 9, page 52 of the Traffic Study. The mitigation measures identified in Table 12, pages 58 to 62 shall be in place prior to issuance of occupancy permits for Phase 2. TE -9 A minimum of two new traffic signals (Santa Clarita Parkway/D Street, Santa Clarita parkway/Via Princessa) shall be In place prior to Issuance of occupancy permits for Phase 2. The applicant shall be required to assess the need for signalization at other Intersections to the satisfaction of the City Traffic Engineer. TE -10 Magic Mountain Parkway shall be restriped to accommodate six traffic lanes from Valencia Boulevard to San Fernando Road/Bouquet Canyon Road place prior to Issuance of occupancy permits for Phase 2. TE -11 Mag lc Mountain Parkway (Magic/Princessa) shall be widened to six traffic lanes from San Fernando Road/Bouquet Canyon Road to Rio Vista Road place prior to Issuance of occupancy permits for Phase 2 In accordance with Traffic Engineering condition TE -1 TE -12 Magic Mountain Parkway (Magic/Princessa) shall be widened to four traffic lanes from Rio Vista Road to Rainbow Glen Drive prior to Issuance of occupancy permits for Phase 2 in accordance with Traffic Engineering condition TE -1. TE -13 Santa Clarita Parkway shall be widened and extended to have a minimum of four traffic lanes from Soledad Canyon Road to Via Princessa prior to Issuance of occupancy permits for Phase 2 in accordance with Traffic Engineering condition TE - 1. C. PHASE 3: INFRASTRUCTURE PHASING PLAN Single Family Units 419 Multi Family Units 765 Commercial (Square Feet) Office (Square Feet) 313,632 Business Park (Square Feet) 411,850 Neighborhood Park (Acres) 8.5 Driving Range (Acres) 3,75 Recreational (Square Feet) 25,000 School One Church (Acres) Hotel (Rooms) TE -14 A total of 31 intersections will be significantly Impacted as referenced In Table 11, page 54 of the Traffic Study. The mitigation measures identified in Table 12, pages 58 to 62 shall be in place prior to Issuance of occupancy permits for Phase 3. TE -15 A minimum of three new traffic signals (Magic Mountain Parkway/Via Princessa, Santa Clarita Parkway/Via Porta Bella, Main Street/Via Princessa) shall be in place prior to Issuance of occupancy permits for Phase 3. The applicant shall be required to assess the need for slgnallzation at other Intersections to the satisfaction of the City Traffic Engineer. TE -16 Magic Mountain Parkway (Magic/Princessa) shall be widened to Include six traffic lanes from Rio Vista Road to Rainbow Glen Drive prior to issuance of occupancy permits for Phase 3 in accordance with Traffic Engineering condition TE -1. TE -17 Santa Clarlta Parkway shall be widened and extended to the north and south beyond the project boundary to Include six traffic lanes from Bouquet Canyon Road to Sierra Highway at the Placerita Canyon Road junction prior to issuance of occupancy permits for Phase 3 in accordance with Traffic Engineering condition TE - 1. TE -18 Via Princessa shall be extended from Magic/Princessa west to connect to existing Wiley Canyon Road west of San Fernando Road as a six lane arterial with an overcrossing at San Fernando Road and the railroad track prior to Issuance of occupancy permits for Phase 3 in accordance with Traffic Engineering condition TE - 1. PHASE 11 PHASE X PHASING FOR TRAFFIC ANALYSIS Pk(f).'4I RIO VISTA RD Z , c� b 4 � G A PRINCESSA O PREPARED NOVEMBER 22, 1994 9�. s \l�G�SSP Py¢ OC wRD .. �q "!I?N E` ol#LR� 4"" ��yp4 2 LANES 4 LANES 6 LANES _ FREEWAY - PHASE 3 The many layers of The Anden Group The Anden Group and Salvatore (Sam) Veltri are strange and wondrous creatures. The first is 21,o octoppus of a company, and Mr. Veltri is its very talented spokesperson. They want to build what they like to call Porta Bella. Anden is a large, nationwide builder. Its practices of seeing, conquering, building and leaving are legion. It is for that reason that it is so difficult to pin down exactly who Is in charge. Another reason is that there have been some 17 filings for Fictitious Name Statements in Los Angeles County since 1988 in- volving Anden. All use the ad- dress 15260 Ventura Blvd., Sher- man Oaks. The problem is that The Anden Group and their co- horts have not been In that build- ing for years. At least, that is what the building manager told me yesterday when I went there. Whittaker Corp. made a filing under the name "Anden Santa Clarita Partners, etc." at the 15260 Ventura Blvd. address. Al- though the filing shows on the microfiche as having been filed as document number 90-0005200 on July It, 1990, the hard copy is missing from the Recorder's file. Therefore, this paragraphist was unable to find out who are the principals in that set of partners. Please, Mr. Veltri or someone, please furnish us with a con- formed copy from your file. There is a BMC Nonholme Corp. with a Chicago address qualified to do business in Cal!- fomia. However, this paragraphist was unable to find a Fictitious Name Statement or a Statement of Doing Business as a Partnership for Notthholme Partners in the county records. Again, Mr. Veltri, if there is such a filing, please furnish us with a conformed copy. DanHon ;TOA DIFFERENT BEAT' That company uses the address 330 Washington Blvd., 4th Floor, Marina del Rey, CA 90292. It is an upscale building near the ocean. Neither Mr. Veltri nor Nonhholme Partnershas a name on the building directory. The manager directed me to the recep- tionist on the fourth floor_. She is ensconced in a nice lobby answering � phones. I asked for Mr. Veltri. She looked at her book, which showed that he was out to a meeting and would return later in the afternoon. She assured me that he had been a tenant in the building for a couple of years. He shares the floor with others, who share the receptionist. Please, Sam, put your name and that of your company on the Building Directory. It would save a lot of problems! Mr. Veltri makes no secret that Northhoime Partners, whomever they may be, intend to get the necessary permits to build the project. They, whoever they are, will parcel them out to other de- velopers to do the actual building. Unlike Newhall Land and Farm- ing Co. or American Beauty Homes, the developers of Porta Bella will not be local. They, more than likely, will build and leave. Anden has a poor record in re- cent years of paying its small suppliers. It makes a practice of stiffing the little guy. Westlaw re- search shows about 30 Small Claims Court judgments against The Anden Group since 1989. Small suppliers of construction materials and office supplies got these judgments. No one knows that many more didn't bother to take them to court. Assuming that Northholme Part ners is a part of Anden, there is no reason to believe that their conduct will differ from that of their associate. Scott Bentley pointed a lot of this out to the City Council at a meeting held in October. The city attorney; said it was not the job of the city or its council to check the bona fides of developers. He told them it is up to the bonding company to do that. His statement, at best, is naive. At worst, disingenuous. Bonding companies pass off big risks to worldwide financiers such as Lloyd's of London and others. They are ofttimes hard to find when payoff time comes around. The sophisticated and sometimes ditty tactics of many of the inter- national bonding financiers have left more than one bond holder sucking air. Visalia did not check up on William Courtney, who contracted with Visalia with the help of then -City Manager Donald Duck- worth to build the Visalia Radis- son Hotel. It cost the city some $20 million to get out of that one. " If our City Council and city manager don't check up on North- holme and Anden to protect us, then why in the, hell did we form a city in the first place? Dan Hon is a Newhall probate and real estate attorney. His col- umn appears on Thursdays. RECEIVED AND MADE A PART 07-^rrORDAT --41-�?�- MEMO ITEM N0. November 22, 1994 GEORGE PEDERSON, MAYOR CITY COUNCIL MEMBERS CITY OF SANTA CLARITA 23920 VALENCIA BLVD. SANTA CLARITA, CA. 91355 Dear City Council, 1 REC E A PAR, �, .. _.,JRDAT MEETING REM N0. It is a privilege to join with many other groups and individuals from throughout Santa Clarita Valley in imploring the City Council to adopt the best possible system of roads to accommodate any development in the PortaBella area. These proposals are being made by a consortium of interests including homeowners, small business owners, organizations including the chambers of commerce, merchant groups and the industrial association. We assure you the proposals we offer this evening are not examples of nimbyism or lulus, (locally unwanted land uses), but rather recommendations that will benefit the greatest number of residents, and allow quality, creative and beneficial development while safeguarding the community. Engineering analysis, history of the area, the General Plan and common sense converge on offering the following recommendations: FIRST THE PRIMARY ARTERIAL. We propose an East West corridor linking Interstate 5 to State Route 14 be built. This long -agreed upon corridor is best suited to move the greatest number of vehicles, and will provide much needed additional capacity. It is the "optimum crossing" of the valley. It should be designed to connect Newhall Ranch Road, bridge across the Santa Clara River, enter the PortaBella property to the immediate East of Metrolink and reach SR14, byway of Via Princessa and White's Canyon. Its proximity to the Metrolink station will accommodate the best access for multi -modal connections at Metrolink and a maximum interface with both trains and City buses now and into the future. A sizeable portion of this road already has been dedicated for such usage, and it has been analyzed for its sufficiency. Portabella can readily be redesigned to accommodate this major arterial. Dumping PortaBella traffic onto Magic Mountain Parkway will further exacerbate an already overburdened road especially at the I-5 interchange. Why, in spite of requests by City Council members has staff not addressed the long Supported East West road as the principle road accommodating thio proposal? SECONDLY, We recommend that a bridge crossing San Fernando Road at Princessa to Wiley Canyon Road be built, as is included in the General Plan. This proposed road/bridge alignment will add needed capacity and facilitate traffic from PortaBella. It would not negatively impact either the commercial businesses at Springbrook or Circle J homeowners with intrusive construction and would safely move residents and commercial traffic in combination with the major East/West corridor. Why has there been no definitive discussion of thio alternative in spite of numerous inquirieo and requests? THIRDLY, we recommend the development of a local, four lane, grade level road at Magic Mountain Parkway as it enters PortaBella, this alignment was on the original design for the PortaBella proposal. As a local road, or secondary roadway, it should circle behind and avoid negatively impacting the Commercial Development at Springbrook: It would eliminate the unsightly bridge in Circle J and would provide more road capacity in combination with the E/W Corridor and the Princessa/Wiley connection. It is an alignment which the vast majority of residents prefer. Why hay staff assiduously avoided Studying this propcoal even though it hao been requested by Council membero? FOURTH, we specifically request that an urgent study be made of other roads to comprise the network of roads which any significant development on the Bermite property will require. A North/South alignment can begin at the proposed Santa Clarita Parkway, connect to Princessa and exit to the proposed Golden Valley Road which is already designated as a major arterial from SR 14.I should not bisect AES, ARCO, MWD and other "topographically challenging" areas. Why hao there been no search for other north/youth alignments than the proposal to go through this problematic area? The citizens and Civic groups before TheCity Council this evening applaud the Council's decision to require total toxic clean up before allowing development on this property. The safety and the future of the Santa Clarita Valley are too important to compromise. WE REQUEST THESE ROADS BE ADOPTED AS THE PRIMARY NETWORK FOR ANY DEVELOPMENT ON THE PROPERTY CURRENTLY CALLED PORTABELLA. CONNIE WORDEN, PRESIDENT, VALENCIA INDUSTRIAL CENTER CO-CHAIRMAN, SCV CHAMBER OF COMMERCE TRANSPORTATION COMMITTEE REU A Al PART .. ;D AT `f l MEETING 11/22/94 - PLACERITA CANYON ISSUES: RE PROPOSED SANTA CLARITA PARKWAY OFFSITE ALIGNMENT FOR PORTA BELt 1. Design/alignment not in concert with Placerita Canyon Special Standards District (City of Santa Clarita Development Code, Section 17.16.080). 2. Visual obstruction/impact of 6 lane road due to size and light of 80 foot high slope in at least one area. 3. Excessive traffic noise in an area designated as rural. 4. Traffic and access issues with regard to connection proposed to a rural, privately maintained road, i.e. Placerita Canyon Road. 5. Impact of filling and berming Placerita Canyon Creek which .is within a flood plane (LACO Flood Control District; FEMA issues) and is also a blue lined stream (State of California Department of Fish & Game). 6. Obstructs horse trails, both existing and planned. 7. Loss of, additional oak trees, including heritage oaks. 8. Seismic and engineering concerns. 9. Economic and cost concerns re building, compensation to those impacted whether businesses, property and/or homeowners and who will make those payments, i.e. the City taxpayers or the Applicant who has an appeal pending over this very issue. 10. No mitigation measures or conditions suggested with regard to the offsite section of Santa Clarita Parkway as submitted by staff 10-4-94. SOLUTION: AS WAS SUBMITTED TO YOU, AND WHICH YOU REQUESTED BE MODELLED, CONSIDER THE ALTERNATIVE OF EXTENDING SANTA CLARITA PARKWAY TO THE EAST WHEN IT GOES OFFSITE SO AS TO CONNECT WITH GOLDEN VALLEY ROAD, WHICH SHOULD ALSO PROVE TO BE A LESS COSTLY, ENVIRONMENTALLY COMPATIBLE AND FEASIBLE ALTERNATIVE ACCEPTABLE TO THE APPLICANT, ENGINEERS, AND RESIDENTS OF THE CITY INCLUDING THOSE WITHIN THE PLACERITA CANYON COMMUNITY. (Note: The map was submitted to, you by Connie Woyden-Roberts at. your Study Session of 9-14-94). Chris�pher Townsley Placerita Canyon Property Owner , • .•, !=;,.383 0�;, '�\; 0�'1�'�.. /P "'`� C C �„/,%1/' /// %a � \ '+-.:� !"\_ /ops � '•;n •` VC rcl p' O yC �� �� ':i /� _ails. '::,.:. <'Jr .. .. � {--•.�.���0�•`/�'� i �...- i ' Ucr 1 � � ; a o • � , r ., r ,•. . �4 41,0 ;:�1 �l, ,-��-�•1� Ilr`I•r\��� iij Al 49 nks �---ice! ��• t \ � �: - �T � �� ��;l�i }13. 1 / •ice i ' X +- � -.• -•- • . P 0. 1360-5� '�:-= � �. :' i1 • ;�].. C .�J w ow I 7 LAW OFFICES OF MICHAEL McENTEE MICHAEL McENTEE JENNY CHURCH November 21, 1994 To: Carl Boyer City Council of Santa Clarity 444 — � 9595 WILSHIRE BLVD. STE. 900 BEVERLY HILLS, CA.. 90212-2509 PHONE (310) 273.3342 FAX (310) 271-4062 -` REQ -E A PARI L. =ORDAT -� -�7e/ MEETING REM N0. Re: Item 1 Porta Bella Specific Plan and Development Agreement, Statement of Overriding Consideration, proposed E.I.R. and Addendum Sch 92-041041, Mitigation Monitoring Program, Tentative Tract Map 51599, Specific Plan 91- 001 and Development Agreement 93-003; of Whittaker, Bermite and Porta Bella, City Council meeting date: November 22, 1994 Hand delivery Dear Carl: As you requested, I am giving you some short answers concerning the cost of clean up, time, and related issues for the above referenced matters. I have reviewed the nearly five hundred pages of well boring logs, expert reports, and maps concerning the Bermite Whittaker site. I enclose Tables 3- 11 TCE Concentration in Soil Gas and Table 3-9, Previous Investigations, taken from one of the reports I reviewed. I am an engineer and an attorney, with 17 years experience in environmental issues and litigation, I will take this in the order of issues raised by you: 1. Q Can we put a ballpark number on the probable overall clean un cost of the Bermite project remediation? A. Yes. We can safely estimate a minimum clean up cost of $96,000,000. A typical rule of thumb is to take the entire site in acres times $100,000/ acre. 1 On the other hand, some sites such as Stringfellow acid pits have smaller overall acreage but much deeper contaminated soils, and the cost has averaged over $1,000,000 per acre. The costs include all the expert studies and physical remediation of the site. Even though some of the Bermite site may be found to be uncontaminated, other parts of it will be found extremely contaminated. Again, $100,000 /acre times all the acreage is a good starting point to get a ball park number. Therefore, the Bermite project with more than 960 acres in 64 groups, will certainly cost a minimum in the range of $96,000,000 for surface remediation. Now, selecting the most probable cost means applying a safety factor, and in these cases, a safety factor of 1.5 times $96,000,000 rounds out to $150,000,000. 2. Q Can we make a ballpark estimate as to the time for full remediation of the site, prior to grading for the 3,000 homesites9 A. Yes. For a complex site, such as Bermite, we can look to the Stringfellow acid pits for an indication. In Stringfellow, the time is 11 years. Both Bermite and Stringfellow have a contamination plume into the ground water. On the other hand, a minimum estimated time for full remediation would be seven years if everything goes well the first time through. 3. Q At what point can the Portabella Specific Plan EIR Development Agreement, and related matter be approved? A. Certainly not until the full RCRA compliance plan is approved by the State and Federal EPA's can the EIR draft be deemed complete. Only after the full detailed set of plans for first phase remediation and second phase (verification of remediation) are finished can there be adequate "project description" FOR PURPOSES OF THE draft ENVIRONMENTAL IMPACT REPORT. Adequate project description is key to an Environmental Impact Report since project description identifies the scope of the enquiries that must be made as to environmental impact. For example, remediation or clean up of the site prior to construction of the project is a major impact on the environment. The amount of construction, in the form of scraping the earth, hauling, burning of the earth either on-site or off-site, the hauling of earth to replace contaminated earth, the drilling, boring, removal of hills, etc. All of these must be described in detail sufficient to make adequate guantitV estimates of what work will be done. Consider the impact of 7 years of dust clouds, noise, hauling, and burning. Apparently Whittaker experts have testified that the preparation of the Phase I plans will take a year. 2 Preparation of such test plans would require a large amount of additional drilling of test wells, and lab work. Only after that work is finished can there be an intelligent definition of the the scope of the project. 4. Q Ugally, what requires the City Council to know about the clean un work. A. At a minimum, the law requires that the EIR include the details of all the work near the surface which might affect the environment. Here, the prospect of 7 to 11 years of intensive surface work, hauling of dirt, a decontamination [soil burning] plant on site, dust, energy consumption, co2 release, smog increase, road obstruction, etc. all are factors to describe in detail. Otherwise, failure to fully reveal and quantify the whole site remediation would be failure to comply with the State requirements for an EIR. 5. Q. Can't Whittaker Bermite just say they will clean it up and give a rough estimate of time? A. No, the project description must go into sufficient detail so that concerned citizens and the city councilpersons can make their own assessment of just how much impact. that will arise from the remediation. i.e. it makes a big difference whether 500,000 cubic yards of soil must be burned, taking 3 years, versus a more likely 30,000,000 cubic yards of soil being dug out, hauled, burned, hauled back and compacted, taking 11 years. 6, Q Are there legal risks to the City separate and apart from certifying the E.I.R.? A. Yes, the Stringfellow site is a good example of the risk, not only of approving the site for residential use, but also the risk of owning any part of the site. Apparently one third of the site will be dedicated to City ownership in the next few years. This is legally very harzardous to the City solvency. Any owner of a site at any point in time can be stuck with the full clean up cost. The City is the only deep pocket around. I think all property attorneys experienced with environmental problems would immediately say, no, do not take title, or dedications, or easements to the property, in any form, until after all Phase II monitoring work showed complete and final site remediation. Otherwise the City easily will find itself paying for part of the $150,000,000 or more clean up bill. Whittaker apparently claims to have the money to clean up the site provided they can develop it in stages. That is a strange statement 3 because it reveals a financial inability to presently pay for clean up. As an additional point, as a homeowner in Santa Clarita, I suggest that the city council owes its future city councils to objectively quantify the risk of future lawsuits from the site against the city; Note that the costs to the government agency approving a site which later involves toxic liability involves huge expenses for defense and settlement of the case. 7. Q Can't Bermite/ Whittaker just post a bond to assure clean up? A. No, for several reasons. We cannot at this time even tell how much work is needed. Suppose it is $200,000,000? But the easier answer is, never trust a bond involving millions of dollars. The hard experience of many agencies has shown failure of these bonding companies when called on to pay, simply cannot pay. The County of Los Angeles Parks department has experienced such problems, for example with the Kenneth Hahn County Park. As an alternative, I think it might do to have Whittaker put up $150,000,000 in cash at the time of certifying the EIR. The money should go into a trust account supervised by a major engineering outfit like Dames and Moore, or Bechtel, as a condition to even certifying the EIR, when it is ready to certify, about 1 year or 18 months from now. 8. Q But, the $96,000,000 to $150,000,000 exceeds the $80,000,000 value of the property? A. Right, and this is often the problem with these toxic sites. The duty and expense to Whittaker to clean up the site is absolute and unavoidable. I would challenge the suggestion that the site is worth $80,000,000 or worth anything at all. Not until it passes all Phase II and the aquifer remediation is an unqualified success would any lender finance construction of any homes on the site,: And who would want to live on a site which was toxic at one time. The only persons who would gravitate to such a site would be those receiving subsidized government low income housing. I think that effect has to be fully explored in detail in the proposed EIR since it affects the alternative uses of the site as open space. 4 9. 0. Isn't the "Resource Conservation and Recovery Act Facility Investigation Work Plan" dated May 3 1994 sufficient? A. To begin with, the data on which that plan is based appears to raise serious doubts its credibility and reliablity. Look at Table 3-11, a copy of which I attach. Notice that the readings taken from some sample wells are very high up until the month Bermite undertook to try to sell the property, December. 1990. All of a sudden very high readings drop to near zero This is a sure sign that data taking is corrupted Nature just does not change that fast. Even if the selected sampling on which the work plan is based might have some validity, it was done at a time when Whittaker Bermite was claiming that only 14 isolated sites on the acreage were contaminated. Only after a search warrant was served by Cal EPA and threat of criminal prosecution did Whittaker Bermite finally admit in mid-1994 that there were at least 64 sites on the acreage which were contaminated, in addition to ground water contamination of the aquifer deep under the property. Table 3-9, a copy of which is attached, likewise shows an effort to simply narrow the scope of the work, by treating little portions of the site as if each were completely isolated from others. Even the May, 1994 work plan only selects a few sites to work on, and plans on doing further studies to locate additional sites of contamination. Thus, the work plan is simply not a complete and final site analysis. 10. 0. Isn't the city always immune from suits? A. Not where the City becomes landowner of the dedicated streets and open space. The duty of the City to pay for clean up is imposed by federal law and state law, and is separate and apart from anybody getting hurt on the property. There is no immunity for a citv from waste site clean up costs for property owned or Purchased by the city. In addition, there is the liability of the City for approving a site which later causes trouble. That is the meaning of the Stringfellow case, wherein the State, which approved the site, ended up paying 13.5 million to dispose of its proportionate liablity for approving the site. 11. Summary: The request to certify the EIR is a year to 18 months premature because the EIR document must include the fulldetailedplans for Phase I and Phase II site remediation. What is included now is simply not complete. The costs will be at a minimum, for site remediation, $96,000,000 and very likely $150,000,000. The time will be in the range of 7 to 11 years, just like the Stringfellow project. The City must not accept dedications, or in any way take a possessory or title interest in the project until Phase II is fully completed. 5 If called upon as a witness, I could and would competently testify to the foregoing statements. I certify under penalty of perjury under the laws of the State of California that the foregoing is true and correct. Executed on November 21, 1994, at Beverly Hills, California. Michael McEntee 0 TABLE 3-11 ICE CONCENTRATION IN SOIL GAS PROBE P1-20 P1-40 P1-60 P1-80 PI -100 P1-120 P2-20 P2-40 P2-60 ELEVATION 1443 1423 1 1403 1383 1363 1343 1442 1422 1402 MARCH 22, 1989 200 400 5,000 200 150 0 2,700 3,900 11,900 MARCH 29, 1989 400 700 7,500 1,100 800 80 1,500 6,500 8,000 APRIL 6, 1989 500 1,000 7,000 800 800 20 1,500 4,000 4,000 APRIL 13, 1989 1,200 2,000 8,000 1,200 900 600 4,800 7,500 9,000 APRIL 20, 1989 1,200 2,600 11,000 1,200 1,000 70 3,200 8,000 8,000 MAY 3 1989 MAY 5 1989 MAY 22 1989 JUNE 14, 1989 1,800 4,000 10,000 1,600 800 150 4,000 8,000 7,000 JUNE 21 1989 2,500 7,500 10,000 3,000 1,400 250 6,000 9,000 8,500 JUNE 28, 1989 900 2,000 16,000 1,100 750 450 2,500 3,000 2,500 JULY 5, 1989 2,200 4,000 10,000 2,500 1,200 400 4,500 6,000 3,500 JULY 19, 1989 250 500 1,500 2,700 1,500 400 8,000 12,000 9,000 AUGUST 4, 1989 200 400 1,200 2,500 1,200 300 5,000 9,000 8,000 AUGUST 10, 1989 220 300 1,000 2,200 1,100 250 4,000 7,500 7,000 AUGUST 17, 1989 2,000 4,000 10,000 1,800 1,000 350 4,500 6,000 7,000 AUGUST 24,1989 2,200 4,000 9,000 1,600 900 300 4,000 6,500 7,000 AUGUST 31 1989 2,000 3,800 10,000 1,900 1,000 270 4,200 6,200 10,000 SEPTEMBER 8, 1989 1,700 4,000 9,000 1,500 900 300 9,000 11,000 12,000 SEPTEMBER 15-1989 1,500 3,500 9,000 1,400 1,000 450 9,000 10,000 9,000 SEPTEMBER , 1 9 1 1 900 350 10,000 9,000 60 FE RDECEMBER 8OCTOBER 9 9199 1,400 D3,50O0000 .1,000 700 2050 50 9,000 9,000 73 195 ,000 UARY -2t, 40 3 MARCH 8, 1991 0 0 130 0 0 20 0 200 60 MARCH 22, 1991 0 0 120 0 0 35 4 250 250 APRIL 8 1991 6 0 35 0 0 10 0 100 15 APRIL 25, 1991 0 0 7 0 0 10 0 120 30 MAY 10, 1991 0 0 10 0 0 35 0 160 30 MAY 30, 1991 4 2 6 0 0 20 10 90 55 JUNE 10, 1991 0 0 10 0 0 6 0 100 19 AUGUST 1 1991 0 0 3 0 0 9 3 90 100 AUGUST 15, 1991 0 0 2 0 0 0 0 40 3 AUGUST 29, 1991 0 0 3 0 0 2 0 0 0 SEPTEMBER 12, 1991 0 0 110 4 6 0 0 60 12 SEPTEMBER 26, 1991 0 0 4 0 0 2 0 20 0 OCTOBER 24, 1991 0 0 3 0 0 2 0 30 4 MARCH 18 1992 9 12 80 25 20 45 7 80 22 AUGUST 26, 1992 0 0 100 0 0 0 0 40 2 OCTOBER 15, 1992 0 0 35 0 0 0 0 25 4 NOVEMBER 4, 1992 0 0 80 0 0 15 0 15 0 DECEMBER 3, 1992 3 1 20 0 0 18 0 15 14 MARCH 9, 1993 0 0 70 12 3 40 1 45 6 JUNE 15, 1993 1 0 8 15 4 25 0 35 15 DECEMBER 14, 1993 2 2 45 9 2 40 7 40 16 MARCH 31, 1994 2 0 25 4 1 3 0 25 6 READINGS ARE IN PPM TABLE 3-11 (continued) PROBE P2-80 P2-100 P2-120 P3-20 P3-40 P3-60 P3-80 P3 -100P3-120 ELEVATION 1382 1362 1342 1442 1422 1402 1382 1362 1342 MARCH 22, 1989 3,400 55 350 300 200 600 350 50 MARCH 29, 1989 5,500 230 400 900 850 700 230 210 APRIL 6,1989 2,500 100 200 500 1,000 900 200 250 220 APRIL 13, 1989 5,000 700 250 1,000 2,000 1,500 850 240 170 APRIL 20,1989 4,000 50 190 1,000 2,500 2,000 1,000 320 200 MAY 3, 1989 MAY 5, 1989 MAY 22, 1989 JUNE 14, 1989 3,500 800 200 2,500 4,000 4,000 1,500 400 250 JUNE 21, 1989 4,500 900 400 2,600 4,000 3,500 1,700 400 250 JUNE 28, 1989 1,500 400 100 2,900 5,000 4,500 1,500 400 100 JULY 5, 1989 2,000 500 150 2,500 4,400 3,500 1,500 320 150 JULY 19, 1989 4,000 1,500 350 4,000 6,000 6,000 2,000 500 400 AUGUST 4,1989 4,000 1,100 200 3,000 4,500 5,000 1,800 300 250 AUGUST 10 1989 3,500 900 200 2,500 4,000 3,500 1,500 270 250 AUGUST 17, 1989 3,000 1,000 200 2,500 4,000 3,500 1,700 450 250 AUGUST 24 1989 2,800 900 200 2,000 4,000 4,000 1,500 1,000 220 AUGUST 31, 1989 2,500 750 170 6,000 5,000 4,500 1,500 900 200 SEPTEMBER 8, 1989 5,000 1,600 200 4,000 6,000 6,000 2,500 650 100 SEPTEMBER 15, 1989 5,000 1,500 400 5,000 6,500 6,000 2,200 800 200 SEPTEMBER 27, 1989 4,500 1,400 400 4,500 6,000 7,000 2,000 700 250 OCTOBER 9, 1989 3,500 1,000 250 4,200 5,000 6,000 2,100 500 190 DECEMBER 18, 1990 16 .35 6 0 4 600 15 17 16 FEBRUARY 20, 1991 0 3 0 0 0 45 0 2 0 MARCH 8; 1991 24 24 0 0 0 600 9 15 5 MARCH 22, 1991 110 25 15 0 3 500 35 10 15 APRIL. 8, 1991 30 0 0 0 0 80 0 6 0 APRIL 25, 1991 18 10 2 0 0 200 10 6 0 MAY 10, 1991 30 11 25 0 0 100 0 6 12 MAY 30, 1991 70 9 20 0 0 400 14 8 10 JUNE 10, 1991 18 10 0 0 0 200 7 5 0 AUGUST 1, 1991 70 12 3 0 0 110 3 3 0 AUGUST 15 1991 3 5 0 0 0 40 1 4 0 AUGUST 29, 1991 0 4 0 0 0 23 0 2 0 SEPTEMBER 12 1991 12 8 0 0 0 4 0 0 0 SEPTEMBER 26, 1991 0 2 0 0 0 30 0 2 0 OCTOBER 24, 1991 3 6 0 0 0 50 3 4 0 MARCH 18 1992 38 30 1 l 1 180 50 25 0 AUGUST 26, 1992 0 7 0 0 0 7 0 0 0 OCTOBER 15, 1992 0 7 0 0 0 15 0 4 0 NOVEMBER 4, 1992 0 4 0 0 0 4 0 4 0 DECEMBER 3 1992 9 4 24 5 3 30 6 7 9 MARCH 9, 1993 2 15 2 1 4 80 18 30 14 JUNE 15, 1993 5 0 10 4 5 60 20 0 4 DECEMBER 14, 1993 70 16 9 8 120 80 18 14 MARCH 31, 1994 3 0 0 4 3 50 20 2 0 READINGS ARE IN PPM TABLE 3-11 (continued) 1989 1989 89 989 MAY 3, 1989 700 15 50 110 MAY 5 1989 25 160 MAY 22, 1989 50 JUNE 14, 1989 5,000 35 800 250 160 450 100 JUNE 21, 1989 4,500 150 1,000 300 200 450 140 JUNE 28, 1989 6,000 80 450 240 200 400 140 JULY 5, 1989 5,000 120 600 250 200 500 150 JULY 19, 1989 4,500 150 400 300 250 450 200 AUGUST 4, 1989 500 180 350 200 250 600 180 AUGUST 10, 1989 7,000 180 300 150 200 600 150 AUGUST 17, 1989 6,000 120 400 1,000 250 400 350 AUGUST 24, 1989 6,500 150 400 1,000 400 500 300 AUGUST 31, 1989 6,000 220 300 900 300 450 250 SEPTEMBER 8; 1989 6,000 400 500 1,000 250 430 200 SEPTEMBER 15, 1989 9,000 200 400 1,200 300 500 400 SEPTEMBER 27, 1989 9,000 350 450 900 210 400 300 OCTOBER 9, 1989 5,000 350 350 500 200 320 200 DECEMBER 18, 1990 2 2 9 0 4 0 FEBRUARY 20, 1991 0 0 0 0 0 0 0 MARCH 8, 1991 0 0 0 4 0 0 0 MARCH 22, 1991 5 25 40 15 0 0 0 APRIL 8, 1991 0 0 0 0 0 0 0 APRIL 25, 1991 5 10 0 0 0 0 0 MAY 10, 1991 3 40 0 0 0 0 0 MAY 30, 1991 0 35 3 0 0 0 0 JUNE 10, 1991 2 8 2 5 0 0 0 AUGUST 1, 1991 0 2 0 0 0 0 0 AUGUST 15 1991 0 0 0 0 0 0 0 AUGUST 29 1991 0 0 0 0 0 0 0 SEPTEMBER 12, 1991 0 0 0 0 0 0 0 SEPTEMBER 26, 1991 0 0 0 0 0 0 0 OCTOBER 24 1991 0 0 0 0 0 0 0 MARCH 18 1992 28 35 40 30 0 1 1 AUGUST 26, 1992 0 0 3 2 0 0 0 OCTOBER 15, 1992 0 0 3 5 0 0 0 NOVEMBER 4, 1992 0 0 0 0 0 0 0 DECEMBER 3, 1992 20 40 9 5 0 0 0 MARCH 9, 1993 1 10 6 5 0 0 0 JUNE 15, 1993 28 26 0 5 0 0 0 DECEMBER 14, 1993 30 35 16 16 0 0 0 MARCH 31, 1994 9 3 3 6 0 0 0 READINGS ARE IN PPM TABLE 3-9 (continued) PREVIOUS INVESTIGATIONS RCRA Ground Water Quality Monitoring Report, 342 Surface Impoundment Hazardous Waste Management Unit - March 1992, AMV, May 27, 1992. Assessment of the Soil Vapor Monitoring and Extraction System at the Former 317 Surface Impoundment Hazardous waste Management Unit, AMV, July 22, 1992. National Pollutant Discharge Elimination System, Quarterly Report, April through June 1992, AMV, July 27, 1992. Area 317 RCRA Quarterly Ground Water Quality Monitoring Report No. 16, AMV, July through September 1992. Water Quality Monitoring and Response Plan for the Interim Status Area 317 Surface Impoundment, AMV, October 1992. Preliminary Endangerment Assessment, Whittaker Corporation, Bermite Division 10.30 -Acre Santa Clarita Commuter Rail Station Site, AMV, October 9, 1992. RCRA Ground Water Quality Monitoring Report, 342 Surface Impoundment Hazardous Waste Management Unit, July September 1992, AMV, October 16, 1992. Area 317 RCRA Quarterly Ground Water Quality Monitoring Report No. 17, AMV, October through December 1992. RCRA Ground Water Quality Monitoring Report, 342 Surface Impoundment Hazardous Waste Management Unit, October - December 1992, AMV, January 14, 1993. Area 317 Quarterly Ground Water Monitoring Report No. 18, AMV, January through March 1993. Whittaker-Bermite, Excavation, Sampling and Disposal of Materials From the Miscellaneous Bum Area Solid Waste Management Unit, AMV, February 16, 1993. RCRA Ground Water Quality Monitoring Report, 342 Surface Impoundment Hazardous Waste Management Unit, January - March 1992, AMV, April 9, 1993. Certification of Clean Closure for Resource Conservation and Recovery Act Hazardous Waste Management Unit: Former Area 342 Surface Impoundment, Whittaker Corporation, Bermite Division, 22116 West Soledad Canyon Road, Santa Clarita, California, EPA No. CAD064573108, AMV, April 23, 1993. Area 317 RCRA Quarterly Ground Water Monitoring Report No. 19, AMV, April through June 1993. TABLE 3-9 (continued) PREVIOUS INVESTIGATIONS Proposal for Abandonment of Ground Water Monitoring Wells MW -2, MW -7, MW -8, and MW -9 at the 342 Surface Impoundment Area, Whittaker Corporation, Bermite Division, 22116 West Soledad Canyon Road, Santa Clarita, California, AMV, June 22, 1993. Geotechnical Feasibility Report, Bermite Property, Saugus Area, City of Santa Clarita, County of Los Angeles, California. Site Ground Water Sampling and Analysis Plan, Appendix IV of 40 CFR 264, WAL Site Assessment Bermite Property, Burn Pit Area, International Technology Corporation. Specific Plan for a Ground Water Quality Assessment Program for the 317 Surface Impoundment Area, WAL