HomeMy WebLinkAbout1994-03-22 - AGENDA REPORTS - TELECOMMUNICATIONS WIRING (2)AGENDA REPORT
XV
Counci pproval
Item to be presented by:
Carolynn W. Deller
CONSENT CALENDAR
DATE: March 22; 1994
SUBJECT: Telecommunications Wiring
DEPARTMENT: Management Services
BACKGROUND
The City of Santa Clarita faces an emergency situation based upon earthquake damage which
was suffered by the City Hall as a result of the earthquake which occurred on January 17,
1994 and subsequent aftershocks.
Damage to the City Hall building included damage to the City's data and voice wiring. This
agenda item identifies the processes to correct the damage.
Due to the short time period available to repair or replace the wiring without impeding
restoration of the City Hall, bid specifications were written that would enable the City to
evaluate repair or replacement of data wiring only, voice wiring, or both.
Based upon the expediency of the project, known wiring contractors were contacted and
invited to participate in the bid process. To ensure uniformity, a mandatory walk through of
the site was conducted. At that time the potential bidders were advised that they were
required to bid the specification and therefore exceptions would be considered non-
compliant. They were further advised that that would allow all the bids to be evaluated
fairly. It was emphasized that any difference they may have with the specification would be
resolved with the successful bidder. Five wiring contractors participated in the four hour
detailed review of the site and the wiring needs of the City. As a result of the walk through,
two additional addendums to the specifications were faxed to participating contractors.
Of the five contractors participating in the walk through, three submitted bid packages;
Accelerated Technologies, Digital Networks, and American Tel -A -Com, Accelerated
Technologies did not complete the check lists and price information so were declared non-
responsive to the bid. Digital Networks did not include critical addendum information
needed to itemize changes in the price specifications so were declared non-responsive to the
bid. Attached is a spreadsheet (Attachment 1) identifying available cost information for
comparison, Due to the emergency nature of the project, American Tel -A -Com was selected
to correct and replace the telecommunications wiring for a total of $95,091.59.
Because of the urgent need to accomplish these repairs prior to an opportunity for City
APPROWED Ags7
Council approval, the City Manager (Director of Emergency Services), under the authority of
the California State Public Contract Code, Section 22035, Emergencies, Procedure (See
Attachment 1) entered into this contract (See Attachment 2) on March 10,`1994, to be ratified
by the City Council at the earliest opportunity,"
RECOMMENDATION:
Staff recommends that the Council ratify said contract with American Tele -A -Com
Corporation of Utah for emergency repairs in the amount of $95,091.59. Therefore, authorize
staff to expend $95,091.59 from account 01-9999-999.,
ica;
wiring.agn.
City of Santa Clarita
Telecommunications Wiring Bid Results
American Tel -A -
Cost Description Com Digital Networks
V21.2 The total material cost to install a fully functional
voice station wiring system or network, in
accordance with these specifications: 7,971.40 14,256.00
V21.3 The per jack materials cost to provide the City of
Santa Clarita a voice station wiring system in
accordance with these specifications: 30.08 54.00
V21.4 The total material cost to install a fully functional
data terminal wiring system or network, in
accordance with these specifications: 20,580.37 27,324.00
V21.5 The per jack materials cost to provide the City of
Santa Clarita a data terminal wiring system in
accordance with these specifications: 77,95 103.50
V21.6 The total labor cost to install a functional voice
station siring system or network, in accordance
with these specifications: 12,685.00 19,536.00
V21.7 The per jack labor cost to install the City of Santa
Clarita's voice station wiring system or network, in
accordance with these specifications: 48.04 74.00
V21.8 The total labor costs to install a fully functional data
terminal wiring system or network, in accordance
with these specifications: 18,965.00 19,008.00
V21.9 The per jack labor costs to install the City of Santa
Clarita's data terminal wiring system or network, in
accordance with these specifications: 71.83 72.00
V21.10 The combined total of materials and labor costs for
installing voice station wiring and jacks: 20,602.40 33,792.00
V21.11 The combined per jack materials and labor costs
for installing voice station wiring and jacks: 78.03 128.00
V21,12 The combined total of materials and labor costs for
installing data terminal wiring and jacks: 39,545.37 46,332.00
V21.13 The combined per jack materials and labor costs
for installing data terminal wiring and jacks: 149.79 175.50
WIItEBIDSALS Pagel 3/15/94
City of Santa Clarita
Telecommunications Wiring Bid Results
V21,14 The combined total for voice station and data
V21.154 The total labor cost to install the data MDFs: 640.02 1,680.00
V21,16 The costs of all the material required to install a
completely functional and operational riser cable
and cross -connect it to the PacBell MPOP on one
end and the voice MDF on the other: 2,785.11 3,935.00
The costs of all the labor required to install a
V21,17 completely functional and operational riser cable
and cross -connect it to the PacBell MPOP on one
end and the voice MDF on the other: 2,960.00 985.00
Total cost to replace data and voice wiring and
move main entry point of voice wiring. $95,092
*Cost information for addendums including multi -
pairs and conduit not clearly identified.
WIREBIDSALS Paget 3/15/94
terminal wiring costs:
60,201.77
80,124.00
V21.14A
Additional materials and cost of bond.
29,194.79
2,250.00 "
V21,14Tot
Total combined for voice and data:
89,346.48
82,374.00
V21,15.1
The total material cost to install the voice MDFs:
307.90
3,955.00
V21..15.2
The total material cost to install the data MDFs:
2,834.27
3,864.00
V21,15.3
The total labor cost to install the voice MDFs
75.00
1,680.00
V21.154 The total labor cost to install the data MDFs: 640.02 1,680.00
V21,16 The costs of all the material required to install a
completely functional and operational riser cable
and cross -connect it to the PacBell MPOP on one
end and the voice MDF on the other: 2,785.11 3,935.00
The costs of all the labor required to install a
V21,17 completely functional and operational riser cable
and cross -connect it to the PacBell MPOP on one
end and the voice MDF on the other: 2,960.00 985.00
Total cost to replace data and voice wiring and
move main entry point of voice wiring. $95,092
*Cost information for addendums including multi -
pairs and conduit not clearly identified.
WIREBIDSALS Paget 3/15/94