SUBJECT: VIA ONDA - II (PROJECT NO. 95-913) ACCEPTANCE
DEPARTMENT: Community Development
On October 11, 1994, Council awarded the contract for the subject project to the low bidder,
Padilla & Sons Co., Sylmar, California in the amount of $40,802.90 for the second phase work
on Via Onda, damaged as a result of the Northridge Earthquake. This work consisted of repairs
of damaged walkways, landscaping, grading of lawns, replacement of brick steps and borders,
replacement of flagstone walks, irrigation systems and driveways between the back of sidewalk
to the property line, all within the public road right-of-way.
In addition, several driveways, walks, and brick work that fell outside of the public road
right-of-way resulted in less than pleasing appearance because of adverse grade breaks at these
locations. Since the abrupt grade changes on private property were the result of the
earthquake, the repairs made to these existing improvements were eligible expenses for CDBG
Emergency Supplemental funds.
The Contractor, Padilla & Sons Co., Sylmar, California hqs completed emergency street
restoration work on Project No. 95-913, Via Onda - II. This project was completed to the
satisfaction of the Director of Community Development on December 22, 1994, for a total project
cost of $84,520.58.
RECOMMENDATION
1. That Council accept the work performed by Padilla & Sons, Co.
2. That Council direct the City Clerk to file the attached Notice of Completion for the project.
3. Staff be directed to release the ten percent retention 35 days after the Notice of
Completion is recorded, provided no stop notices, as provided by law, have been filed.
ATTACHMENTS
Notice of Completion of Public Improvement and Work
Location Map
comd1Nprj913.by �� APPROVED Agenda Item:
When Recorded, Please Return To:
Donna Grindey, City Clerk
City of Santa Clarita
23920 Valencia Boulevard, Suite 301
Santa Clarita, California 91355
NOTICE IS HEREBY GIVEN that the City of Santa Clarita, Los Angeles County
California, has caused a public improvement, to wit:
PROJECT NO, 95-913
OFF -SYSTEM ROADS - VIA ONDA II
to be constructed upon the property hereinafter described. The contract for furnishing of all
plant, labor, services, materials and equipment and all utilities and transportation, including
power, fuel and water, and performing all work necessary to construct and complete, in a good
and workmanlike manner in strict accordance with the specifications, plans, and drawings
therefore on file in the office of the City Clerk of the City of Santa Clarita, for the construction,
installation, and completion of the above described public improvement and work, was
heretofore made and entered into with Padilla & Sons, Co. on the 4th day of November, 1994,
and filed for record in the office of the City Clerk of the City of Santa Clarita; that the work
upon said public improvement was actually completed on the 22nd day of December, 1994 and
that the Director of Community Development has notified the City Council that she has made
and completed a final inspection of the materials furnished and installed and the work
performed in the construction, installation and completion of said public improvement
hereinabove more particularly described and set forth in, and has certified in writing to the City
Council that all of the provisions of the contract and contract documents for the furnishing of
all plant, labor, services, materials, and equipment, and the performing of all work necessary
for the construction, installation and completion of said public improvement above described
have been fully complied with to her satisfaction as required by the contract documents; that
Anal acceptance of the construction, installation and completion of said public improvement
above described was made on the 22nd day of December, 1994 that the nature of the title to said
property improvement in fee except for the right-of-way upon which it is constructed, and that
it owns an easement upon, over and along said right-of-way for the purpose of the construction,
installation, and completion of said public improvement hereinabove referred to and on which
said public improvement is situated is described as follows:
OFF -SYSTEM ROADS - VIA ON_ DA II
PROJECT NO. 95-913
NAME OF SURETY ON MATERIAL AND LABOR BOND:
American Motorist Insurance Company
7470 North Figueroa Street
Los Angeles, CA 90041
DATED this day of 19 _
Jo Anne Darcy, Mayor
City of Santa Clarita
STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES ) §
CITY OF SANTA CLARITA
I certify or declare that under penalty of perjury that the foregoing is true and correct.
ATTEST:
Donna M. Grindey, City Clerk
City of Santa Clarita
BY:hds
munrnPd95913.by
Date