HomeMy WebLinkAbout1996-06-11 - AGENDA REPORTS - APPLICATION SLTPP (2)r'11
&'
City Manager Approval
Item to be presented by:
Steve Stark
CONSENT CALENDAR
DATE: June 11, 1996
SUBJECT: APPLICATION FOR STATE -LOCAL TRANSPORTATION
PARTNERSHIP PROJECTS
Resolution No. 96-76
DEPARTMENT: Administrative Services
Caltrans is currently accepting project applications for the eighth cycle of the State -Local
Transportation Partnership Program (SLTPP). The SLTPP is a state sponsored program
designed to encourage local agencies to support roadway improvements with funds other than
gas tax or developer contributions. Eligible projects must be locally constructed on a local road,
a State highway, or an exclusive mass transit guideway. The completed project must either
increase capacity, extend service to a new area, or extend useful life of the roadway a minimum
of ten years.
Only contract and construction engineering costs are eligible for reimbursement under this
program. The percentage of reimbursement for this program is dependent upon the number
of approved projects statewide. It is expected that Cycle 8 reimbursements will be between 3.5
and 19 percent of the actual project contract costs.
As a procedural matter, Caltrans requires that the City Council approve the submission of
potential projects for the program. Staff recommends that the following projects be selected for
consideration:
1. Valencia Boulevard - I-5 to McBean Parkway - Overlay
2. Sierra Highway - Soledad Canyon to San Fernando Road - Interconnect
3. Bouquet Canyon - Magic Mountain to Plum Canyon - Interconnect
Seco Canyon - Bouquet Canyon to Copper Hill - Interconnect
Adapted: �- 1 /-qAgenda item:_ 9
RESOLUTION NO. 96-76
June 11, 1996 - Page 2
4. Sierra Highway - San Fernando Road to Soledad Canyon - Restripe
5. Bouquet Canyon - Plum Canyon to North City limits - Overlay
6. Valley Street - Lyons Avenue to 8th Street - Overlay
7. Calgrove - I-5 to 600' W/O Wiley Canyon - Overlay
8. Soledad Canyon - Miss Grace to Sand Canyon - Overlay
9. Orchard Village McBean Parkway to Lyons Avenue - Overlay
10. Valencia Boulevard and Soledad Canyon - Creekside Drive to Commuter Way - Bikeway
RECOMMENDATION
Adopt Resolution No. 96-76, and authorize the City Engineer to submit these projects to
Caltrans for consideration.
ATTACHMENT
Resolution No. 96-76
Applications are in the Council Reading file in the City Clerk's Office
RGN:CMR:hds
..61%res%-76.e
RESOLUTION NO. 96-76
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF SANTA CLARITA, CALIFORNIA
APPROVING FORMAL APPLICATION FOR CYCLE 8
STATE/LOCAL TRANSPORTATION PARTNERSHIP PROJECTS
WHEREAS, the California State Legislature has authorized the State/Local
Transportation Partnership Program to identify and construct locally supported transportation
projects; and
WHEREAS, the adopted procedures established by the State of California
Department of Transportation require the applicant to certify the City Council's approval by
resolution prior to submission of applications to the Department of Transportation: and
WHEREAS, the City Council of the City of Santa Clarita hereby resolves as follows:
SECTION 1. The City Engineer is authorized to submit appropriate transportation
projects for consideration of grant funding.
SECTION 2. The City Council certifies that the City of Santa Clarita understands
the assurances and certifications contained in the applications.
SECTION 3. The City Council supports the following transportation projects for
SLTPP funding cycle 8 and endorses the application submittal for:
1. Valencia Boulevard - I-5 to McBean Parkway - Overlay
2. Sierra Highway - Soledad Canyon to San Fernando Road - Interconnect
3, Bouquet Canyon - Magic Mountain to Plum Canyon -Interconnect
Seco Canyon - Bouquet Canyon to Copper Hill - Interconnect
4. Sierra Highway - San Fernando Road to Soledad Canyon - Restripe
5. Bouquet Canyon - Plum Canyon to North City limits - Overlay
6. Valley Street - Lyons Avenue to 8th Street - Overlay
7. Calgrove - I-5 to 600'W/0 Wiley Canyon - Overlay
8. Soledad Canyon - Miss Grace to Sand Canyon - Overlay
9. Orchard Village - McBean Parkway to Lyons Avenue - Overlay
10, Valencia Boulevard and Soledad Canyon - Creekside Drive to Commuter Way -
Bikeway
RESOLUTION NO. 96-76
June 11, 1996 - Page 2
PASSED, APPROVED AND ADOPTED this
19
MAYOR
ATTEST:
CITY CLERK
STATE OF CALIFORNIA
COUNTY OF LOS ANGELES
CITY OF SANTA CLARITA
day of
I, Donna M. Grindey, City Clerk of the City of Santa Clarita, do hereby certify that
the foregoing Resolution was duly adopted by the City Council of the City of Santa Clarita at
a regular meeting thereof, held on the day of 19_ by the
following vote of Council:
AYES: COUNCILMEMBERS:
NOES: COUNCILMEMBERS:
ABSENT: COUNCILMEMBERS:
CITY CLERK
RGN:CMR:hds
m 61\ree6&76.c
EXHYRI T A (APP.05)
(PAGE 1 OF 2) STATE USE ONLY
PROJECT NO.
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUND
Part I: Information and Certification
Pursuant to California Streets and Highways Code, Division 3, Chapter 16, Section 2600 et seq.,
application for State -Local Transportation Partnership Program Funds is hereby made by:
Applicant: CITY OF SANTA CLARITA
Address: 23920 VALENCIA BLVD.. SUITE 300
SANTA CLARITA, CA 91355
Contact Person: Anthony J. Nisich, City Engineer Phone: 805-255-4963
Expenditure Authorization (EA): Project Planning Number:
State Administered Project []Yes ®No
Transit Project Yes ®No
Caltrans District: 7
State Route: N/A
State Highway []Yes ®No
Staged Project []Yes ®No
County: LOS ANGELES
Post Mile Limits: N/A to N/A
Project Location / Limits: Valencia Boulevard from I-5 to McBean Parkway
Type of Work: STREET OVERLAY
Source of Local Share Funds: General Fund, Local Bonds and/or TDA Article 8
Justification of Project: To reestablish the integrity of the pavement that adversely affects the
quality of the ride. Extends the useful life of the roadway by ten years.
Part II: Project Costs
(A) Contract Items
$ 600,400 A
(B) Less Ineligible Amount (Contract Items) $ (
(C)
Total Eligible Amount = A - B
$
600,400
(D)
Maximum State Share = 0.5 x (C)
$
300,200
'c: \monim \clepp\altppl.npp
.hed I
C
u
EXHIBIT A
(PAGE 2 OF 2)
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUND
Part III: Quarterly Expenditure Plan
SLTPP CYCLE NUMBER X= 8
Percent by Quarter of Total Eligible Local Agency Expenditures
(Do not adjust for early reimbursement procedures)
STATE F.Y.
QUARTER 1
(JUL-SEPT)
QUARTER 2
(OCT -DEC)
QUARTER 3
(JAN -MAR)
QUARTER 4
(APR -MAY)
TOTAL
199(X -1)/199X = 1997/1998
199X/199(X+1) = 1998/1999
50
50
100
199(X+1)/199(X+2) = 1999/2000
199(X+2)/199(X+3) = 2000/2001
GRAND TOTAL: 100%
CERTIFICATION: To the best of my knowledge and belief, the data and information provided in this
application are true and correct, and I am authorized to file this application on behalf of the applicant.
Applicant acknowledges that it understands, and can comply with the time limits for award of contracts
and expenditure of funds.
Name and title:
Al�✓A4 -,l Sill
Signature:
Attachments: Location Map, Typical Cross -Section, Engineers Estimate
e Annie.\.ltpp% .Ifpplapp
.heel 2
Date:
Q ry p
>
U (] U OP 4S
U Z O m
Ll
Mp OEAN z 31 N0 d
R Q d
� o
GS 7 S S u
sm CANYON
0 U
s 1
V U
K}
F
Z
.. 0 RO FP��,HPY
/
a`"A
spa 5S P�
pp10EN
� Z
U O
wF
—�� 0 Q
Ov
�o
R; W
VARIES R/W
VARIES
g' 8,
COLD MILL COLD MILL
LIMITS
LIMITS
EXISTING �-
JI
SURFACE PAVING FABRIC OR S.A.M.I.
WHERE REQUIRED
1-1/2" TO 2" THICK
ASPHALT RUBBER HOT MIX
TYPICAL SECTION
N. T. S.
NOTE1 THE ROADWAY CROSS-SECTION AND EXTENT OF REPAIR AND
RECONSTRUCTION IS PRELIMINARY IN NATURE. THE FINAL
DESIGN CROSS-SECTION, EXTENT OF R & R, MEDIANS, AND OTHER
DETAIL DESIGN CONSIDERATIONS WILL BE DETERMINED DURING
FINAL DESIGN
Part A - Engineer's Estimate
To be used as a basis for computation of State -Local Transportation Partnership Program funds.
Project Title: Valencia Blvd. from the 1-5 to McBean Parkway
Description of Work: Street Overlay
Length:
5,252 feet
Item Description
Unit
Quantity
Unit
Price
Extended
Amount
Asphalt -Rubber Hot Mix (ARHb
TON
4,600
$ 75.00
$ 345,000
Paving Fabric (or SAMI)
SY
41,000
1.50
61,500
Cold Milling
SF
250,000
0.50
125,000
Adjust Manhole
EA
25
350.00
8,750
Adjust Pull/Meter Boxes
EA
15
300.00
4,500
Project Signs
EA
6
500.00
3,000
Traffic Control Plan
LS
100%
2,500.00
2,500
Traffic Loop Detectors
EA
20
350.00
7,000
Painted Lane Line Striping
LF
5,000
0.70
3,500
Turn Arrows
EA
6
150.00
900
Raised Pavement Markers
LF
25,000
0.75
18,750
Construct Curb Ramps
EA
10
2,000.00
20,000
Subtotal Contract Items $ 600,400
sltpp.X1S
sheet4
EXHIBIT A
(PAGE 1 OF 2)
(APP.05)
STATE USE ONLY
PROJECT NO.
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUNDS
Part I- Information and Certification
Pursuant to California Streets and Highways Code, Division 3, Chapter 16, Section 2600 et seq.,
application for State -Local Transportation Partnership Program Funds is hereby made by:
Applicant: CITY OF SANTA CLARITA
Address: 23920 VALENCIA BLVD., SUITE 300
SANTA CLARITA, CA 91355'
Contact Person: Anthony J. Nisich, City Engineer Phone: 805-255-4963
Expenditure Authorization (EA): Project Planning Number
State Administered Project
Transit Project
Caltrans District:
7
❑ Yes ® No
[]Yes [NNo
State Highway
Staged Project
County:
E]Yes ®No
[]Yes ®No
LOS ANGELES
State Route: N/A Post Mile Limits: N/A to N/A
Project Location / Limits: SIERRA HIGHWAY FROM SOLEDAD CANYON ROAD TO
SAN FERNANDO ROAD
Type of Work:
TRAFFIC SIGNAL INTERCONNECT
Source of Local Share Funds: TDA
Justification of Project: To improve the mobility of vehicles, improve access and relieve congestion
in the area.
Part II: Project Costs
(A)
Contract Items
$
300,000
A
(B)
Less Ineligible Amount (Contract Items)
$ (
0
) B
(C)
Total Eligible Amount = A - B
$
300,000
C
(D)
Maximum State Share = 6.5 x (C)
$
150,000
D
c: Vmonimisf[pp\.aurroti.aDD
sheet !
EXHIBIT A
(PAGE 2 OF 2)
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUNDS
Part III: Quarterly Expenditure Plan
SLTPP CYCLE NUMBER X= 8
Percent by Quarter of Total Eligible Local Agency Expenditures
(Do not adjust for early reimbursement procedures)
STATE F.Y.
QUARTER 1
(JUL-SEPT)
QUARTER 2
(OCT -DEC)
QUARTER 3
(JAN -MAR)
QUARTER 4
(APR -MAY)
TOTAL
199(X -1)/199X = 1997/1998
50
50
100
199X/199(X+1) = 1998/1999
199(X+1)/199(X+2) = 1999/2000
199(X+2)/199(X+3) = 2000/2001
GRAND TOTAL: 100%
CERTIFICATION: To the best of my knowledge and belief, the data and information provided in this
application are true and correct, and I am authorized to file this application on behalf of the applicant.
Applicant acknowledges that it understands, and can comply with the time limits for award of contracts
and expenditure of funds.
Name and title: 1' pc—kr / _(,)✓!5 /tsi (l ✓� E,v�j/N�f✓�
Signature:
Attachments: Location Map, Typical Cross -Section, Engineer's Estimate
c' \manim \a8pp4ie�rati.aPP
duet 2
Date:
Part VI - Engineer's Estimate
To be used as a basis for computation of State -Local Transportation Partnership Program funds.
Project Title: Sierra Highway From Soledad Canyon Road to San Fernando
Road (SR -126)
Description of Work: Traffic Signal Interconnect
Length:
Subtotal Contract Items $300,000
RGN:lkl
eng-civi\engestrgn
Unit
Extended
Item Description
Unit
Quantity
Price
Amount
Conduit Cable Installation
LF
15,000
$15.00
$225,000
Miscellaneous
LS
75,000
Subtotal Contract Items $300,000
RGN:lkl
eng-civi\engestrgn
PROJECT LOCATION MAP
SIERRA HIGHWAY/STATE ROUTE 14
CONGESTED CORRIDOR INTERCONNECT
LL
.o
v�v MATCH UNE -SEE LEFT
N
O
Jfy� �f
lli�
y
MATCH UNE - SEE RIGHT
LEGEND: `
O - EXISTING TRAFFIC SIGNALS- �^p
- PROPOSED INTERCONNECT
EXHIBIT A
(PAGE 1 OF 2)
(APP.05)
STATE USE ONLY
PROJECT NO.
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUNDS
Part I: Information and Certification
Pursuant to California Streets and Highways Code, Division 3, Chapter 16, Section 2600 et seq.,
application for State -Local Transportation Partnership Program Funds is hereby made by:
Applicant:
Address:
CITY OF SANTA CLARITA
23920 VALENCIA BLVD., SUITE 300
SANTA CLARITA. CA 91355
Contact Person: Anthony J. Nisich, City Engineer
Expenditure Authorization (EA):
State Administered Project E]Yes [NNo
Transit Project
Caltrans District:
State Route:
N/A
E]Yes [NNo
7
Phone: 805-255-4963
Project Planning Number:
State Highway F]Yes [NNo
Staged Project E]Yes ®No
County: LOS ANGELES
Post Mile Limits:
N/A to N/A
Project Location / Limits: Bouquet Canyon Road from Magic Mountain Parkway to Plum
Canyon Road and Seco Canyon Road from Bouquet Canyon Road and Copper Hill Road..
Type of Work:
TRAFFIC SIGNAL INTERCONNECT
Source of Local Share Funds: TDA
Justification of Project: To improve the mobility of vehicles, improve access and relieve congestion
congestion in the area.
Part II: Proiect Costs
(A)
Contract Items
$
530,000 A
(B)
Less Ineligible Amount (Contract Items)
$ (
) B
(C)
Total Eligible Amount = A - B
$
530,000 C
(D)
Maximum State Share = 0.5 x (C)
$
265,000 D
e\rnonim Is(rpo ��gs<Fa�rP
sheet I
EXHIBIT A
(PAGE 2 OF 2)
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUNDS
Part III: Quarterly Expenditure Plan
SLTPP CYCLE NUMBER X= 8
Percent by Quarter of Total Eligible Local Agency Expenditures
(Do not adjust for early reimbursement procedures)
STATE F.Y.
QUARTER 1
(JUL-SEPT)
QUARTER 2
(OCT -DEC)
QUARTER 3
(JAN -MAR)
QUARTER 4
(APR -MAY)
TOTAL
199(X -1)/199X = 1997/1998
50
50
100
199X/199(X+1) = 1998/1999
199(X+1)/199(X+2) = 1999/2000
199(X+2)/199(X+3) = 2000/2001
GRAND TOTAL: 100%
CERTIFICATION: To the best of my knowledge and belief, the data and information provided in this
application are true and correct, and I am authorized to file this application on behalf of the applicant.
Applicant acknowledges that it understands, and can comply with the time limits for award of contracts
and expenditure of funds.
Name and title: ?,oBFpr A4tiiw,4AI
A
Signature:
Attachments: Location Map, Typical Cross -Section, Engineer's Estimate
CN r mw\eapp\Wo ftmapp
&&Kf2
Date:
Part VI - Engineer's Estimate
To be used as a basis for computation of State -Local Transportation Partnership Program funds.
Project Title: Bouquet Canyon Road from Magic Mountain Parkway to Plum
Canyon Road and Seco Canyon Road from Bouquet Canyon
Road and Copper Hill Road
Description of Work: Traffic Signal Interconnect
Length:
Subtotal Contract Items $530,000
RGN:IkI
eng-cMN engeSt Tg
Unit
Extended
Item Description
Unit
Quantity
Price
Amount
Conduit Cable Installation
LF
30,000
$15.00
$450,000
Miscellaneous
LS
80,000
Subtotal Contract Items $530,000
RGN:IkI
eng-cMN engeSt Tg
PROJECT LOCATION MAP
NORTH/SOUTH METROLINK FEEDER CORRIDOR INTERCONNECT
AT�61 t�,
`
`j� a
-
1
w
/
Y I
f
LEGEND:
O - EXISTING 'TRAFFIC SIGNALS \
- PROPOSED INTERCONNECT
EXHIBIT A
(PAGE 1 OF 2)
(APP.05)
STATE USE ONLY
PROJECT NO.
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUNDS
Part I: Information and Certification
Pursuant to California Streets and Highways Code, Division 3, Chapter 16, Section 2600 et seq.,
application for State -Local Transportation Partnership Program Funds is hereby made by:
Applicant: CITY OF SANTA CLARITA
Address: 23920 VALENCIA BLVD., SUITE 300
SANTA CLARITA, CA 91355
Contact Person: Anthony J. Nisich, City Engineer
Expenditure Authorization (EA):
State Administered Project
Transit Project
Caltrans District:
State Route: I
7
[]Yes ®No
[]Yes [NNo
Phone: 805-255-4963
Project Planning Number:
State Highway
Staged Project
County:
E]Yes [NNo
E]Yes ®No
LOS ANGELES
Post Mile Limits: N/A to N/A
Project Location / Limits: SIERRA HIGHWAY FROM SAN FERNADO ROAD TO SOLEDAD
CANYON ROAD
Type of Work: Restriping from four to six lanes of travel, modification of catch basins,
signing, standardizing traffic signals.
Source of Local Share Funds: MTA Grant and Local Funds
Justification of Project: This project is a regional corridor, and it parallels the State Route 14,
which is in the CMP Network and considered in the MTA's Congested Corridors. This project will
reduce delays, noise, and pollution which are the goals of the Air Quality Management Program.
Part II: Project Costs
(A) Contract Items
$ 438,000 A
(B) Less Ineligible Amount (Contract Items) $ (
(C) Total Eligible Amount = A - B
(D) Maximum State Share = 0.5 x (C)
c: \maxum\a!lpplakrropp.:(a
rheet 7
$ 438,000 C
$ 219,000 D
ENGINEER'S ESTIMATE
To be used as a basis for computation of State -Local Transportation Partnership Program
Funds.
Project Title: Sierra Highway Restripe from San Fernando Road to Soledad Canyon Road
Description of Work: Restripe Sierra Highway from four to six lanes of travel, modification
catch basins, signing, standardizing traffic signals, installing new
traffic signal loops, median nose modifications at intersections, and
construct bus turnouts.
Length: Five miles
ITEM ESTIMATE
ITEM$ ITEM DESCRIPTION I INTT AMOUNT
001 Signing and Striping Lump Sum $120,000
002 Traffic Signal Modification Lump Sum $140,000
Traffic Signal Loops
003 Median Modifications Lump Sum $140,000
Catch Basin Modifications
004 Bus Turnouts Lump Sum $38,000
Total $438,000
EXHIBIT A
(PAGE 2 OF 2)
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUNDS
Part III: Quarterly Expenditure Plan
SLTPP CYCLE NUMBER X= 8
Percent by Quarter of Total Eligible Local Agency Expenditures
(Do not adjust for early reimbursement procedures)
STATE F.Y.
QUARTER 1
(JUL-SEPT)
QUARTER 2
(OCT -DEC)
QUARTER 3
(JAN -MAR)
QUARTER 4
(APR -MAY)
TOTAL
199(X -1)/199X = 1997/1998
50
50
100
199X/199(X+l) = 1998/1999
199(X+1)/199(X+2) = 1999/2000
199(X+2)/199(X+3) = 2000/2001
GRAND TOTAL: 100%
CERTIFICATION: To the best of my knowledge and belief, the data and information provided in this
application are true and correct, and I am authorized to file this application on behalf of the applicant.
Applicant acknowledges that it understands, and can comply with the time limits for award of contracts
and expenditure of funds.
Name and title: t— 414-1mA/i✓
Signature:
Ctv'n E,11(—iA14kt_
Attachments: Location Map, Typical Cross -Section, Engineer's Estimate
' N.. %,Ltpp \ aiermpp.:la
sheet 2
Date: 1A -O&
1
I
I
• �+ ® Proposed bridge widening
— - - 1). Santa Clarita River
2). Railroad
Proposed Traffic Signal Interconnect
�� �. Proposed 6 Lanes Striping
EXHIBIT A
(PAGE 1 OF 2)
(APP.05)
STATE USE ONLY
PROJECT NO.
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUNDS
Part I: Information and Certification
Pursuant to California Streets and Highways Code, Division 3, Chapter 16, Section 2600 et seq.,
application for State -Local Transportation Partnership Program Funds is hereby made by:
Applicant: CITY OF SANTA CLARITA
Address: 23920 VALENCIA BLVD.. SUITE
SANTA CLARITA, CA 91355
Contact Person: Anthony J. Nisich, City Engineer
Expenditure Authorization (EA):
State Administered Project
Transit Project
Caltrans District:
State Route: N/A
E]Yes ®No
E]Yes [NNo
Phone: 805-255-4963
Project Planning Number:
State Highway
Staged Project
[]Yes ®No
E]Yes ®No
7 County: LOS ANGELES
Post Mile Limits: N/A to N/A
Project Location/ Limits: Bouquet Canyon Road from Plum Canyon Road to North City Limits
Type of Work:
STREET OVERLAY
Source of Local Share Funds: General Fund, Local Bonds and/or TDA Article 8
Justification of Project: To reestablish the integrity of the pavement that adversely affects the
quality of the ride. Extends the useful life of the roadway by ten years.
Part II: Project Costs
(A)
Contract Items
$
104,745
A
(B)
Less Ineligible Amount (Contract Items)
$ (
0
) B
(C) Total Eligible Amount = A - B
(D) Maximum State Share = 0.5 x (C)
aNMnimWepp\eifPPs PP
ghee[ ]
$ 104,745 C
$ 52,373 D
EXHIBIT A
(PAGE 2 OF 2)
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSIIIP PROGRAM FUNDS
Part III: Quarterly Expenditure Plan
SLTPP CYCLE NUMBER X=
Percent by Quarter of Total Eligible Local Agency Expenditures
(Do not adjust for early reimbursement procedures)
STATE F.Y.
QUARTER 1
(JUL-SEPT)
QUARTER 2
(OCT -DEC)
QUARTER 3
(JAN -MAR)
QUARTER 4
(APR -MAY)
TOTAL
199(X -1)/199X = 1997/1998
199X/199(X+1)= 1998/1999
50
50
100
199(X+1)/199(X+2) = 1999/2000
199(X+2)/199(X+3) = 2000/2001
GRAND TOTAL: 100%
CERTIFICATION: To the best of my knowledge and belief, the data and information provided in this
application are true and correct, and I am authorized to file this application on behalf of the applicant.
Applicant acknowledges that it understands, and can comply with the time limits for award of contracts
and expenditure of funds.
Name and title: L>o/3FrZT �(%u rt11
Signature:
Attachments: Location Map, Typical Cross -Section, Engineer's Estimate
,%M.ni.%,Up, Wfpp�p,
eheel2
Date:
JEN
•
r.,.
.ODD
.....
AY
..
-
SUSA
•
..
Of
C)
CIR
.,S;l
-.
.,
.
PROJECT
.0,
RJW
VARIES
VARIES
8'
8'
COLD MILL
LIMITS COLD MILL
LIMITS
I
EXISTING
SURFACE PAVING FABRIC OR S. A.M.L
WHERE REQUIRED
1-1/2" TO 2" THICK
ASPHALT RUBBER HOT MIX
TYPICAL SECTION
N. T. S.
NOTE THE ROADWAY CROSS-SECTION AND EXTENT OF REPAIR AND
RECONSTRUCTION IS PRELIMINARY IN NATURE, THE FINAL
DESIGN CROSS-SECTION, EXTENT OF R & R„ MEDIANS, AND OTHER
DETAIL DESIGN CONSIDERATIONS WILL BE DETERMINED DURING
FINAL DESIGN.
R/W
Engineer's Estimate
To be used as a basis for computation of State -Local Transportation Partnership Program funds.
Project Title: Bouquet Canyon Road from Plum Cyn Rd to North City Limits
Description of Work:. Street Overlay
Length: 5152 feet
Item Description
Unit
Quantit
Unit
Price
Extended
Amount
Asphalt -Rubber Hot Mix (ARID
TON
773
$ 55.00
$ 42,515
Cold Milling
SP
82,432
0.30
24,730
Adjust Manhole
EA
15
400.00
6,000
Adjust Pull/Meter Boxes
EA
10
250.00
2,500
Project Signs
EA
2
500.00
1,000
Traffic Control Plan
LS
100%
1,500.00
1,500
Traffic Loop Detectors
EA
10
350.00
3,500
Signing & Striping
LS
3,000
1.00
3,000
Construct Curb Ramps
EA
10
2,000.00
20,000
Subtotal Contract Items
a4nonkaLsltopkyrled est
sheet?
$ 104,745
EXHIBIT A (APP.05)
(PAGE 1 OF 2) STATE USE ONLY
PROJECT NO.
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUNDS
Part I: Information and Certification
Pursuant to California Streets and Highways Code, Division 3, Chapter 16, Section 2600 et seq.,
application for State -Local Transportation Partnership Program Funds is hereby made by:
Applicant:
CITY OF SANTA CLARITA -
Address: 23920 VALENCIA BLVD., SUITE 300
SANTA CLARITA, CA 91355
Contact Person: Anthony J. Nisich, City Engineer Phone: 805-255-4963
Expenditure Authorization (EA): Project Planning Number:
State Administered Project E]Yes ®No State Highway []Yes No
Transit Project []Yes [NNo Staged Project E]Yes ®No
Caltrans District: 7 County: LOS ANGELES
State Route: N/A Post Mile Limits: N/A to N/A
Project Location / Limits: Valley Street from Lyons Ave to 8th Street
Type of Work: STREET OVERLAY
Source of Local Share Funds: General Fund, Local Bonds and/or TDA Article 8
Justification of Project: To reestablish the integrity of the pavement that adversely affects the
quality of the ride. Extends the useful life of the roadway by ten years.
Part II: Project Costs
(A)
Contract Items
$
61,981
A
(B)
Less Ineligible Amount (Contract Items)
$ (
0
) B
(C)
Total Eligible Amount = A - B
$
61,981
C
(D)
Maximum State Share = 0.5 x (C)
$
30,991
D
c'%m \altPP\altPP'&pp
ahtttl
EXHIBIT A
(PAGE 2 OF 2)
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSFIIP PROGRAM FUNDS
Part III: Quarterly Expenditure Plan
SLTPP CYCLE NUMBER X= 8
Percent by Quarter of Total Eligible Local Agency Expenditures
(Do not adjust for early reimbursement procedures)
STATE F.Y.
QUARTER 1
(JUL-SEPT)
QUARTER 2
(OCT -DEC)
QUARTER 3
(JAN -MAR)
QUARTER 4
(APR -MAY)
TOTAL
199(X -1)/199X = 1997/1998
199X/199(X+1)= 1998/1999
50
50
100
199(X+1)/199(X+2) = 1999/2000
199(X+2)/199(X+3) = 2000/2001
GRAND TOTAL: 100%
CERTIFICATION: To the best, of my knowledge and belief, the data and information provided in this
application are true and correct, and I am authorized to file this application on behalf of the applicant.
Applicant acknowledges that it understands, and can comply with the time limits for award of contracts
and expenditure of funds.
Name and title:
Signature:
Attachments: Location Map, Typical, Cross -Section, Engineer's Estimate
c\mnnfm N.Uppkak"S..PP
I&W 2
909
2Q
(PVT.)
S
y
LYONS AVE
T
LIB
23200
DMV.
r -r
<
z
�� s
°' 9K
m
N m
r- TAZ
c CT
a
N o
WA
y
0C.
CHERRY A ST
o
N��
OF C
SHADOW HE -;J
/
<G OAK LN
m
m HAPPY
D
0
APPYVALLEY
2
Y
~
VDARL LEY
m
AKRUN �N
m
c
QOj A
D Co
m
m
P �r1
o
z
g
D
ST
A
NEARGATE
STH
�E� titi
D R
AR1
3400
$
o
PROJECT PLHEATHER
m
O 0 TIMON
0
�P
Z
LOCATION - ®
R/W
COLD MILL
LIMITS
n I I
L_ - -
EXISTING
SURFACE
VARIES
VARIES
PAVING FABRIC OR S.A.M.I.
WHERE REQUIRED
1-1/2" TO 2" THICK
ASPHALT RUBBER HOT MIX
TYPICAL SECTION
COLD MILL
LIMITS
Jfl
N, T. S.
NOTE, THE ROADWAY CRDSS-SECTION AND EXTENT OF REPAIR AND
P,ECDNSTRUCTION IS PRELIMINARY IN NATURE. THE FINAL
DESIGN CROSS-SECTION, EXTENT OF R & R, MEDIANS, AND OTHER
DETAIL DESIGN CONSIDERATIONS WILL BE DETERMINED DURING
FINAL DESIGN_
R/W
Engineer's Estimate
To be used as a basis for computation of State -Local Transportation Partnership Program funds.
Project Title: Valley Street from Lyons Ave to 8th Street
Description of Work: Street Overlay
Length:
2341 feet
Item Description
Unit
Quantit
Unit
Price
Extended
Amount
Asphalt -Rubber Hot Mix (APJD
TON
348
$ 55.00
$ 19,140
Cold Milling
SF
37,136
0.30
11,141
Adjust Manhole
EA
8
400.00
3,200
Adjust Pull/Meter Boxes
EA
4
250.00
1,000
Project Signs
EA
2
500.00
11000
Traffic Control Plan
LS
100%
1,500.00
1,500
Traffic Loop Detectors
EA
10
350.00
3,500
Signing & Striping
LS
1,500
1.00
1,500
Construct Curb Ramps
EA
10
2,000.00
20,000
Subtotal Contract Items $ 61,981
c honlcelsttpplcycleaest
sheet 6
EXHIBIT A
(PAGE 1 OF 2)
(APP.05)
STATE USE ONLY
PROJECT NO.
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUNDS
Part I: Information and Certification
Pursuant to California Streets and Highways Code, Division 3, Chapter 16, Section 2600 et seq.,
application for State -Local Transportation Partnership Program Funds is hereby made by:
Applicant: CITY OF SANTA CLARITA
Address: 23920 VALENCIA BLVD., SUITE 300
SANTA CLARITA, CA 91355
Contact Person: Anthony J. Nisich, City Engineer
Expenditure Authorization (EA):
State Administered Project []Yes ®No
Transit Project []Yes [NNo
Caltrans District: 7
State Route: N/A
Phone: 805-255-4963
Project Planning Number:
State Highway
Staged Project
County:
E]Yes ®No
[]Yes ®No
LOS ANGELES
Post Mile Limits: N/A to N/A
Project Location / Limits: Calgrove from I-5 to 600'W/0 Wiley Canyon Road
Type of Work:
STREET OVERLAY
Source of Local Share Funds: General Fund, Local Bonds and/or TDA Article 8
Justification of Project: To reestablish the integrity of the pavement that adversely affects the
quality of the ride. Extends the useful life of the roadway by ten years.
Part II: Project Costs
(A)
Contract Items
$
45,457
A
(B)
Less Ineligible Amount (Contract Items)
$ (
0
) B
(C)
Total Eligible Amount = A - B
$
45,457
C
(D)
Maximum State Share = 0.5 x (C)
$
22,729
D
c\ma� \slfpp\�P➢4aPD
ehntl
EXHIBIT A
(PAGE 2 OF 2)
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUNDS
Part III: Quarterly Expenditure Plan
SLTPP CYCLE NUMBER X= 8
Percent by Quarter of Total Eligible Local Agency Expenditures
(Do not adjust for early reimbursement procedures)
STATE F.Y.
QUARTER 1
(JUL-SEPT)
QUARTER 2
(OCT -DEC)
QUARTER 3
(JAN -MAR)
QUARTER 4
(APR -MAY)
TOTAL
199(X -1)/199X = 1997/1998
199X/199(X+1) = 1998/1999
50
50
100
199(X+1)/199(X+2) = 1999/2000
199(X+2)/199(X+3) = 2000/2001
GRAND TOTAL: 100%
CERTIFICATION: To the best of my knowledge and belief, the data and information provided in this
application are true and correct, and I am authorized to file this application on behalf of the applicant.
Applicant acknowledges that it understands, and can comply with the time limits for award of contracts
and expenditure of funds.
Name and title: /_ b ear ' JPE nv/fl /t/(�r L`t�ly L
Signature:
t
Uk,
Attachments: Location Map, Typical Cross -Section, Engineer's Estimate
c.\moven %,U,,\'U'P4.."
sheet 2
Date:
co aT CANER�WELL S
r
0
�PM580RO
P Q w i Q ST
N STA
DA15
gR� DR
CPLGROVE
73 LEY OAK DR
a <9 CT Wy�cOqK. LVD
T
o 0 RITgO£
k
2 r cT
c�
J
Q
U
PROJECT
LOCATION -
R/W
VARIES
VARIES
COLD MILL -
LIMITS
COLD MILL
LIMITS
11_1L I _
L
EXISTING
SURFACE PAVING FABRIC OR S.A.M.I.
WHERE REQUIRED
1-1/2" TO 2" THICK
ASPHALT RUBBER HOT MIX
TYPICAL SECTION
N. T_ S.
NOTE; THE ROADWAY CROSS-SECTION AND EXTENT OF REPAIR AND
RECONSTRUCTION IS PRELIMINARY IN NATURE. THE FINAL
DESIGN CROSS-SECTION, EXTENT OF R & R, MEDIANS, AND OTHER
DETAIL DESIGN CONSIDERATIONS WILL BE DETERMINED DURING
FINAL DESIGN,
R/W
Engineer's Estimate
To be used as a basis for computation of State -Local Transportation Partnership Program funds.
Project Title: Calgrove from 1-5 to 600' W/O Wiley Cyn Rd
Description of Work: Street Overlay
Length:
686 feet
Item Description
Unit
Quantit
Unit
Price
Extended
Amount
Asphalt -Rubber Hot Mix (ARHD
TON
373
$ 55.00
$ 20,515
Cold Milling
SF
25,308
0.30
7,592
Adjust Manhole
EA
4
400.00
1,600
Adjust Pull/Meter Boxes
EA
4
250.00
1,000
Project Signs
EA
2
500.00
1,000
Traffic Control Plan
LS
100%
1,500.00
1,500
Traffic Loop Detectors
EA
5
350.00
1,750
Signing & Striping
LS
2,500
1.00
2,500
Construct Curb Ramps
EA
4
2,000.00
8,000
Subtotal Contract Items $ 45,457
a lmonicalshpplcycle& est
sheet 5
EXHIBIT A
(PAGE 1 OF 2)
(APP.05)
STATE USE ONLY
PROJECT NO.
PLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUND
Part I: Information and Certification
Pursuant to California Streets and Highways Code, Division 3, Chapter 16, Section 2600 et seq.,
application for State -Local Transportation Partnership Program Funds is hereby made by:
Applicant: CITY OF SANTA CLARITA
Address: 23920 VALENCIA BLVD., SUITE 300
SANTA CLARITA, CA 91355
Contact Person: Anthony J. Nisich, City Engineer
Expenditure Authorization (EA):
State Administered Project
Transit Project
Caltrans District: 7
State Route: N/A
[]Yes [NNo
E]Yes [NNo
Phone: 805-255-4963
Project Planning Number:.
State Highway
Staged Project
County:
E]Yes ®No
E]Yes ®No
LOS ANGELES
Post Mile Limits: N/A to N/A
Project Location / Limits: Soledad Canyon Road from Miss Grace to Sand Canyon Road
Type of Work:
STREET OVERLAY
Source of Local Share Funds: General Fund, Local Bonds and/or TDA Article 8
Justification of Project: To reestablish the integrity of the pavement that adversely affects the
quality of the ride. Extends the useful life of the roadway by ten years.
Part II: Project Costs
(A)
Contract Items
$
238,270
A
(B)
Less Ineligible Amount (Contract Items)
$ (
0
) B
(C)
Total Eligible Amount = A - B
$
238,270
C
(D)
Maximum State Share = 0.5 x (C)
$
119,135
D
& \ monim N slfpp %aUpplopp
sheet I
EXHIBIT A
(PAGE 2 OF 2)
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUNDS
Part III: Quarterly Expenditure Plan
SLTPP CYCLE NUMBER X= 8
Percent by Quarter of Total Eligible Local Agency Expenditures
(Do not adjust for early reimbursement procedures)
STATE F.Y.
QUARTER 1
(JUL-SEPT)
QUARTER 2
(OCT -DEC)
QUARTER 3
(JAN -MAR)
QUARTER 4
(APR -MAY)
TOTAL
199(X -1)/199X = 1997/1998
199X/199(X+l) = 1998/1999
50
50
100
199(X+1)/199(X+2) = 1999/2000
199(X+2)/199(X+3) = 2000/2001
GRAND TOTAL: 100%
CERTIFICATION: To the best of my knowledge and belief, the data and information provided in this
application are true and correct, and I am authorized to file this application on behalf of the applicant.
Applicant acknowledges that it understands, and can comply with the time limits for award of contracts
and expenditure of funds.
Name and title:.
Signature: Date:
Attachments: Location Map, Typical Cross -Section,, Engineer's Estimate
v%mo w. We" IdtPP3.."
sheet 2
Q
r
Q 441
a
ZI FAIRGLADE
LA
VEDA p ¢ / p ST o
Q 11
9LF co
Lu �2 a G� Z
Qc` N , ( w
P�
x
N tiF BAINBUR' R
GPS P��s o <�I`N�E� o y�
MISS GRACE DR
�R
Sr c` op SCF
v O
o `4� FOPS
SAN L!
14 �—O
PROJECT
LOCATION -
R/W
COLD MILL -
LIMITS
Ip I I
IL
L
EXISTING
SURFACE
VARIES
VARIES
COLD MILL
LIMITS
_ - I
PAVING FABRIC OR S.A.M.I,
WHERE REQUIRED
1-1/2 TO 2" THICK
ASPHALT RUBBER HOT MIX
TYPICAL SECTION
N. T. S.
NOTE: THE ROADWAY CROSS-SECTION AND EXTENT OF REPAIR AND
RECONSTRUCTION IS PRELIMINARY IN NATURE:. THE FINAL
DESIGN CROSS-SECTION, EXTENT OF R & R, MEDIANS, AND OTHER
DETAIL DESIGN CONSIDERATIONS WILL BE DETERMINED DURING
FINAL DESIGN..
R/W
Engineer's Estimate
To be used as a basis for computation of State -Local Transportation Partnership Program funds.
Project Title: Soledad Canyon Road from Miss Grace to Sand Cyn Rd
Description of Work: Street Overlay
Length: 3170 feet
Item Description
Unit
Quantit
Unit
Price
Extended
Amount
Asphalt -Rubber Hot Mix (ARH3
TON
2,378
$ 55.00
$ 130,790
Cold Milling
SF
253,600
0.30
76,080
Adjust Manhole
EA
6
400.00
2,400
Adjust Pull/Meter Boxes
EA
8
250.00
2,000
Project Signs
EA
2
500.00
1,000
Traffic Control Plan
LS
100%
1,500.00
1,500
Traffic Loop Detectors
EA
10
350.00
3,500
Signing & Striping
LS
5,000
1.00
5,000
Construct Curb Ramps
EA
8
2,000.00
16,000
Subtotal Contract Items
c:lmonicaWtpp1cyc1e8.est
sheet4
$ 238,270
EXHIBIT A
(PAGE 1 OF 2)
(APP.05)
STATE USE ONLY
PROJECT NO,
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUNDS
Part I: Information and Certification
Pursuant to California Streets and Highways Code, Division 3, Chapter 16, Section 2600 et seq.,
application for State -Local Transportation Partnership Program Funds is hereby made by:
Applicant: CITY OF SANTA CLARITA
Address: 23920 VALENCIA BLVD., SUITE 300
SANTA CLARITA, CA 91355
Contact Person: Anthony J. Nisich, City Engineer Phone: 805-255-4963
Expenditure Authorization (EA): Project Planning Number:
State Administered Project
Transit Project
Caltrans District:
State Route: N/A
[]Yes ®No State Highway []Yes ®No
ElYes ®No Staged Project []Yes ®No
7 County: LOS ANGELES
Post Mile Limits: N/A to N/A
Project Location / Limits: Orchard Village from McBean Parkway to Lyons Avenue
Type of Work:
STREET OVERLAY
Source of Local Share Funds: General Fund, Local Bonds and/or TDA Article 8
Justification of Project: To reestablish the integrity of the pavement that adversely affects the
quality of the ride. Extends the useful life of the roadway by ten years.
Part II: Project Costs
(A) Contract Items
$ 416,173 A
(B)
Less Ineligible Amount (Contract Items)
$ (
0
) B
(C)
Total Eligible Amount = A - B
$
416,173
C
(D)
Maximum State Share = 0.5 x (C)
$
208,087
D
c \ m nim \skpp\sGpplapp
sdsel I
EXHIBIT A
(PAGE 2 OF 2)
APPLICATION FOR STATE -LOCAL TRANSPORTATION PARTNERSHIP PROGRAM FUNDS
Part III: Quarterly Expenditure Plan
SLTPP CYCLE NUMBER X=
Percent by Quarter of Total Eligible Local Agency Expenditures
(Do not adjust for early reimbursement procedures)
STATE F.Y.
QUARTER 1
(JUL-SEPT)
QUARTER 2
(OCT -DEC)
QUARTER 3
(JAN -MAR)
QUARTER 4
(APR -MAY)
TOTAL
199(X -1)/199X = 1997/1998
199X/199(X+1) = 1998/1999
50
50
100
199(X+1)/199(X+2) = 1999/2000
199(X+2)/199(X+3) = 2000/2001
GRAND TOTAL: 100%
CERTIFICATION: To the best of my knowledge and belief, the data and information provided in this
application are true and correct, and I am authorized to file this application on behalf of the applicant.
Applicant acknowledges that it understands, and can comply with the time limits for award of contracts
and expenditure of funds.
�E2-i �fccJM 4nl �/PE/LciS�cu�� (ill,,- � /N�l`�
Name and title:. �
Signature: Date:
Attachments: Location Map, Typical Cross -Section, Engineer's Estimate
c.lmoaim \altpp Wfppl app
,hmt2
PROJECT R•
LOCATION -
LYONS
HEEN�RY MAYO /J
MEM: �P/
MIENSai;l
PLACERITA
3L HIGH SCH,
H.M. NEWHALL
MEMORIAL
\ CITY PARK
WM. S HART
HIGH SCHOOL
i AVE
R/'w R/W
VARIES I
VARIES
8' 8'
COLD MILL COLD MILL
LIMITS LIMITS
n
'L J'
EXISTING
SURFACE PAVING FABRIC OR S. A. M.I.
WHERE REQUIRED
1-1/2" TO 2" THICK
ASPHALT RUBBER ::HOT MIX
TYPICAL SECTION
N. L S.
NOTE THE ROADWAY CROSS-SECTION AND EXTENT OF REPAIR AND
RECONSTRUCTION IS PRELIMINARY IN NATURE. THE FINAL
DESIGN CROSS-SECTION, EXTENT OF R 8, R, MEDIANS. AND OTHER
DETAIL DESIGN CONSIDERATIONS WILL BE DETERMINED DURING
FINAL DESIGN.
Engineer's Estimate
To be used as a basis for computation of State -Local Transportation Partnership Program funds.
Project Title: Orchard Village from McBean Pkwy to Lyons Ave
Description of Work: Street Overlay
Length: 7134 feet
Item Description
Unit
Quantit
Unit
Price
Extended
Amount
Asphalt -Rubber Hot Mix (ARHb
TON
4,280
$ 55.00
$ 235,400
Cold Milling
SF
456,576
0.30
136,973
Adjust Manhole
EA
12
400.00
4,800
Adjust Pull/Meter Boxes
EA
10
250.00
2,500
Project Signs
EA
2
500.00
1,000
Traffic Control Plan
LS
100%
2,500.00
2,500
Traffic Loop Detectors
EA
20
350.00
7,000
Signing & Striping
LS
6,000
1.00
6,000
Construct Curb Ramps
EA
10
2,000.00
20,000
Subtotal Contract Items
c:lmon/cals/fppl cycfe8.est
sheet
$ 416,173
EXHIBIT A (APP•05)
(PAGE 1 OF 2) STATE USE ONLY
PROJECT NO._
rari l: tntuIII)au�,I
Pursuant to California Streets and Highways Code. Division 3, Chapter 16, Section 2606 et seq.,
application for State -Local Transportation Partnership Program Funds is hereby made by:
Applicant: City of Santa Clarita
Address: 23920 Valencia Blvd., Suite 300
Santa Clarita, CA 91355
Contact Person: Wayne Weber Phone: (805) 286-4000
Expenditure Authorization (EA):
State Administered Project ❑ Yes 0 Ao
Transit Project ❑ Yes ❑ No
Caltrans District: 07
Project Planning Number:
State Highway ❑ Yes x❑ No
Staged Project ❑ Yes E No
County: Los Angeles
State Route: N/A Post Mile Limits: N/A to N/A
Project Location/Limits: Valencia Boulevard and Soledad Canyon Road between
Creekside Drive and Commuter Way.
Type of Work: Class I bikeway to connect the regional trail system to the intermodal
4Y r.n t.,
Source of Local Share Funds: Local Public Financing Bonds
Justification of Project: This project replaces bike lanes on Soledad Canyon Road allowing
Soledad Canyon Road to be restriped to six lanes of traffic increasing roadway capacity.
Part il: Project Costs
(A)
Contract Payments
g
1,500,000 A
(B)
Less Ineligible Amount (Contract Payments)
S(
0 ) B
(C)
Total Eligible Amount = A - B
$
1,500,000 C
(D)
Maximum State Share= 0.5 X (C)
$
750,000 D
12
EXHIBIT A
(Page 2 of 2)
Part III: Quarterly Expenditure Plan
SLTPP CYCLE NUMBER X 8
(For example:,' for Cycle 6. X=6)
Percent by Quarter of Total Eligible Local Agency Expenditures
(Do not adjust for early reimbursement procedures)
STATE F. Y. QUARTER'1 QUARTER 2 QUARTER 3 QUARTER 4 TOTAL
1.(JUL-SEPT) (OCT- DEC) (JAN -MAR) (APR -JUNE)
139(X-1) / 199X = 1996/1997
I
I 25. I- 25 I 50 I 100
i 99X / 199(X+1) = I -
199(X+1) / 199(X+2) =
1199(X+2) / 199(X+3) =
jrui =xampie: [or i,ycte o, 199(X-1) / 199X = 1995 / 1996)
GRAND TOTAL: 100%
CERTIFICATION: To the best of my knowledge and belief, the data and information provided
in this application are true and correct, and I am authorized to file this application on behalf of
Me applicant. Applicant acknowledges that it understands, and can comply with the time limits
for award of contracts and expenditure of funds.
Name and title: Joseph Inch, Bikeway Coordinator
Signatu
Date: 56_/7 —9Ce-,
Attachments: Location Map, Typical Cross -Section, Engineer's Estimate
13
CITY BOl1N0ARY
t
�E /
SOLEOAO CANYON RD
PROJECT
LOCATION
P{ / L
�P{ I
{
JP
SANTA CLARITA
LOCATION MAP
N TS.
Cross Section
Not Applicable
To be used as a basis for computation of State -Local Transportation Partnership Program Funds.
Project Title: Santa Clara River Trail Phase III
Description of Work: Replace the existing on -street bicycle lanes on Soledad Canyon Road and
Valencia Boulevard, between Commuter Way and the existing South Fork
Trail at Creekside Drive, with an off-street bicycle lane in order to
accommodate six lanes of travel on Soledad Canyon Road and Valencia
Boulevard.
1= Description Amount
001 Earthwork $450,000
002 Bridge Overcrossing $325,000
003 Ramp Undercrossing $475,000
004 Asphalt Bikeway $150,000
005 Fence $100,000
Total: $1,500,000
plandevlengesb5.jmi