HomeMy WebLinkAbout1996-09-03 - AGENDA REPORTS - ENVIRON GP CIRCULATION ELEMENT (2)City Manager ApproN
Item to be presented
Jeffrey Lambert
NEW BUSINESS
DATE: September 3, 1996
SUBJECT: ENVIRONMENTAL REVIEW FOR THE AMENDMENTS TO UPDATE
THE GENERAL PLAN CIRCULATION ELEMENT
DEPARTMENT: Community Development
The current Circulation Element was approved by the City Council along with the General Plan
in June of 1991. As detailed more fully in the attached timeline, ever since the City Council
rejected the north and south alignments of State Route 126 in October 1992, the City has been
engaged in a planning process aimed at developing an amended Circulation Element which:
addresses the impacts of the removal of Route 126;
incorporates amendments to the General Plan resulting from such projects as the
Porta Bella project, and;
is based on an evaluation of circulation alternatives.
The City Council's direction to remove State Route 126 from the Circulation Element of the
General Plan removed the capacity for 100,000 daily trips through the city. This action and
direction to amend the Circulation Element meets the definition of a "project" which may have
a significant impact; as defined by the California Environmental Quality Act (CEQA). Because
of the potentially significant impacts of these amendments to the Circulation Element, an
Environmental Impact Report (EIR) is required. Although the EBR is required, it is also an
important full public disclosure document and procedure which will ensure a proactive public
participation process.
Completion of the environmental process will require the City to enter into a contractual
arrangement with (1) an environmental consultant to prepare the EIR, and conduct the
associated public participation process and (2) Meyer, Mohaddes Associates, Inc. to provide the
traffic analysis for the alternatives, at alevel of detail which is appropriate for the EIR:
On May 29, 1996, the City issued a Request for Proposals (RFP) to assist in the preparation of
the Environmental Impact Report (EBR) for the Circulation Element. Potential consultants were
PPR 11k ED Agenda Item.
told that the EIR process and EIR document:
1. Would be used as a way to inform the decision -makers, responsible agencies, and the
public about the various alternatives for the circulation system and to provide
information regarding the trade-offs among the alternatives;
2. Would analyze up to five alternatives, at an equal level of detail, in order to provide
information about the trade-offs among alternatives. These alternatives would include
refined versions of three of the roadway network options addressed in the Center City
Traffic and Modeling Study, a land use alternative designed to clarify trade-off questions,
and a fifth alternative which would be identified through the public scoping meeting for
the EIR;
3. That the traffic analysis for the EIR would be prepared by Meyer, Mohaddes Associates,
Inc., and would constitute a final stage of the analysis already performed by this traffic
consulting firm;
4, Should include an extensive public information and participation component, and;
5. Should help the City to arrive at a consensus regarding the choice of a roadway network
for inclusion in the Amended Circulation Element.
Consultants were asked to address a list of public involvement options in their proposals. They
were also asked to include a recommended public involvement program, which in their
professional opinion, would help the City to meet its objectives.
Proposals were received from five environmental consulting firms. Staff conducted interviews
with all five firms and has identified the firm staff feels is best qualified to provide both a legally
adequate EIR and a quality public participation process. The recommended firm is Rincon.
Environmental Consultant
Rincon has provided the City with a choice of three levels of public participation in the
environmental process, which are detailed more fully in the attached Scope of Work. The three
levels are as follows:
1. Tier 1 - Rincon's Scope of Work would include: preparation of the Initial Study;
conducting a public scoping meeting for the EIR.; preparation of the EIR and associated
Mitigation Monitoring Program, Findings and Statement of Overriding Considerations;
attendance at three public hearings on the EIR; and, meetings with an EIR Steering
Committee.
The EIR Steering Committee would consist of key staff, two City Councilmembers and
two Planning Commissioners. The purpose of the EIR Steering Committee would be to
assist with making two key decisions during the EIR process: the choice of a fifth
alternative for analysis and, once the EIR is completed and ready for certification, the
formulation of a recommendation regarding the choice of roadway network to include in
the Circulation Element Amendment. EIR Steering Committee members would also
assist in reviewing the preliminary draft of the EIR, in order to ensure that it provides
information about the alternatives in a way which clarifies the trade-offs.
Tier 1 thus provides only the standard level of public involvement in the EIR process
The fee for the Tier 1 Scope of Work is $120,677.
2, Tier 2 - This is Rincon's recommended public participation level. In addition to the Tier
1 Scope elements, this tier would include: preparation of an EIR newsletter which would
serve as an "at -a -glance" guide to the EIR and EIR process, at two key points in the
process; conducting three open house informational workshops on the Draft EIR; and
preparation of a graphic display which would be used in the workshops and which can
be set-up at City Hall or the local library to further inform citizens about the process and
the choice of roadway alternatives.
The Tier 2 public participation component would be run by the public participation
specialty firm of Moore Iacofano Goltsman (MIG). This firm is included on the Rincon
team.
The fee for including the Tier 2 public participation program in the approved Scope of
Work would be an additional $48,740, for a total cost of $169,417.
3. Tier 3 - Rincon has also provided costs for the other elements mentioned by the
community as desired components of a public participation program.. The additional
components, along with their associated fee, are as follows:
• Development of an EIR Home Page - $4,195
• A series of three video educations programs suitable for broadcast - $26,820
• Ad Hoc Community Meetings - $2,630 per meeting
• Slide presentation - $4,880 (fee for the slide presentation would be reduced 50%
if both slide presentation and video program components are selected)
• Press Packet- $2,980
• Additional Newsletters - $5,570 each
On December 12, 1995, Council appropriated $100,000 to begin the environmental process.
Council previously authorized the City Manager to execute an agreement with Willdan
Associates to oversee the General Plan Amendment process for an amount not to exceed
$30,000. Thus, $70,000 of the appropriation remains which can be applied to preparation of the
EIR.
INKINJUT DI10�: •�
Staff recommends that the City Council:
1. Authorize the City Manager to execute an agreement with Rincon for an amount not to
exceed $169,417, to prepare the EIR for the Circulation Element Update ($120,677) and
conduct the Tier 2 public participation process for the update ($48,740) and authorize
a contingency of $17,583 (10%) for a total amount of $187,000.
2. Authorize the City Manager to execute an agreement with Meyer Mohaddes Associates,
Inc., for an amount not to exceed $18,235, to prepare the traffic analysis and authorize
a contingency of $4,765 (26%) for a total amount of $23,000,
Appropriate $140,000 to Account No. 01-5422-227 from General Fund Contingency
Account No. 01-4101-290; and;
4. Designate two City Councilmembers and two Planning Commissioners to serve on a
Steering Committee for the amendment process.
ATTACHMENTS
Timeline of Events related to the Circulation Element Update
Contract for Rincon, with attached Scope, Schedule and Fee (Available for review in the City
Clerk's Reading File)
Scope of Work for Meyer, Mohaddes Associates, Inc., with attached Schedule and Fee (Available
for review in the City Clerk's Reading File)
JL`.LHS:Iep
munciAgpcircl.rpt
TIMELINE OF EVENTS
CIRCULATION ELEMENT UPDATE
6/25/91
City's first General Plan Circulation Element Adopted.
11/10/92
City Council adopted General Plan Amendment 92-02 (Master Case 92-154)
which amended the Circulation Element for clarity and to identify the Lyons
Avenue Extension,
10/92
Council passed a motion to reject the north and south alignments of State
Route 126 as they were proposed in the Caltrans' Draft EIR.
City Council made a referral to the newly formed Citizens Transportation
Advisory Committee (CTAC) to receive further community input regarding an
alternative east/west roadway network in the City.
7/93
CTAC recommendations were presented to the Planning Commission. The
Planning Commission conducted public hearings on this topic, made
refinements in the alternative roadway patterns to be studied, and
forwarded its recommendation to the City Council.
12/21/93
Planning Commission recommended a network that the City Council should
consider in studying an amendment to the Circulation Element.
9/13/94
Council awarded a contract to Meyer Mohaddes Associates, Inc. to conduct a
traffic study (the Center City Traffic and Modeling Study) for the purpose of
examining the existing circulation system and four alternative road networks
in an effort to recommend a superior and acceptable highway system which
would eliminate "the super truck" State Route 126 from the City's General
Plan, while providing a suitable alternative east/west connector with a
network of supporting arterial highways, essential to mobility in the Clarita
Valley.
1/3/95
At the City Council Study Session, staff presented the preliminary findings of
the Center City Traffic and Modeling Study to be used in the environmental
document for the proposed aniendments to the Circulation Element of the
General Plan. The presentation included highlights of the traffic study for
the four alternative circulation networks recommended or endorsed by the
CTAC, the Planning Commission, and the City Council. The study at that
time concluded that neither the current Circulation Element nor any of the
four potential circulation plans would meet the City's General Plan minimum
level of service goal (LOS -D). The City Council directed staff to prepare
additional analysis and try to develop a network that best meets the future
circulation goals of the Valley. Two additional alternatives were ultimately
analyzed as part of an iterative process to develop a superior alternative. The
scenarios and the conclusions of the traffic study are described in the Draft
Final Center City Circulation FlMnantBlUdy (June 1995).
THAELINE OF EVENTS
CIRCULATION ELEMENT UPDATE
Cont'd
10/10/95
Council authorized staff to proceed with recruiting an EIR consultant. At
that time, it was anticipated that Scenario 5 from the Center City Circulation
Element Study would be treated as the preferred alternative for purposes of
environmental analysis.
11/13/95
At City Council request, staff held a community meeting to discuss the
adoption of a new circulation system. The purpose of the meeting was to
present the City's proposed circulation system amendment to the General
Plan to citizens and to ask their assistance in identifying the most
appropriate way to involve the community in the adoption of a new citywide
circulation system which would help to solve the on-going problem of traffic.
congestion. Two things became clear through this process: (1) that it was
premature to consider Scenario 5 as the preferred alternative, and (2) that
there was a need to keep the community informed and involved in all
activities, studies, input opportunities and recommended actions relating to
altering the City's future circulation system.
12/12/95
City Council appropriated $100,000 for the public participation process and
preparation of the legally required environmental impact report and
authorized an agreement with Willdan Associates to oversee the General Plan
Amendment process for an amount not to exceed $30,000.00.
5/29/96
The City issued a Request for Proposal (RFP) to prepare the EIR and to
conduct an expanded public participation process.
6/26/96
The City received bids from five firms: Rincon, Ultrasystems, LSA, P&D `
Environmental Services and Cotton/Beland.
7/18/96
Staff conducted interviews with the five firms following a comprehensive
review and ranking of the written proposals. Based on the written proposals
and interviews, staff determined that 2 of the firms were qualified to preform
the requested work effort anA entered into negotiation with Rincon, which
was chosen as the #1 ranked firm by staff participating in the interview
process.
S: \ed\advance \gprdchrt.lhs