HomeMy WebLinkAbout1996-02-27 - AGENDA REPORTS - LAKEMORE DEWATERING IMPROV (2)AGENDA REPORT
City Manager Approval
Item to be presented by:
Robert G. Newman
CONSENT CALENDAR
DATE: February 27, 1996
SUBJECT: LAKEMORE'DEWATERING IMPROVEMENTS
PROJECT NO. 96-084 - PROJECT ACCEPTANCE
DEPARTMENT: Building and Engineering Services
On June 27, 1995, Council awarded a contract for the subject project to Padilla Paving Co., Inc.
This contract work was completed to the satisfaction of the Director of Building and Engineering
Services on December 1, 1995 for a total construction cost of $198,431.11
This project includes the construction of 12 -inch HDPE (High Density Polyethylene) perforated
pipe to lower the groundwater level. The work also includes slurry seal and overlay for the; full
width along the entire project.
This project is a FEMA- (Federal Emergency Management Agency) funded project as a result
of the 1993 storm, which caused high groundwater damage to the area described and to the Four
Oaks area.
RECOMMENDATION
1, That Council accept the work performed by Padilla Paving Co., Inc.
2. That Council direct the City Clerk to file the attached Notice of Completion for the project.
3. That staff be directed to release the 10% retention 35 days after the Notice of Completion
is recorded, provided no stop notices, as provided by law, have been filed.
ATTACHMENT
Notice of Completion
MC:hds
C0=m1\p96-0M'MC
E