HomeMy WebLinkAbout1997-02-25 - AGENDA REPORTS - NEWHALL METROLINK STATION (2)141
UNFINISHED BUSINESS
DATE: February 25, 1997
City Manal
Item to be
Ken Pulskamp
SUBJECT: RAILROAD AVENUE IMPROVEMENT PROJECT NO. 95-065
NEWHALL METROLINK STATION
DEPARTMENT: Building and Engineering Services
On June 11, 1996, the City Council approved in concept the Newhall Downtown Revitalization
Plan. A major part of this program is the reconstruction of Railroad Avenue from San Fernando
Road south of 4th Street to San Fernando Road at 11th Street (see Railroad Avenue
Reconstruction Map, Attachment A). On July 9, 1996, Council awarded the design contract to
HDR Engineering, Inc.
Staff has held two community meetings with the business and property owners along Railroad
Avenue to inform the public about the proposed project and to gain input from the public
relating to mitigating the effects of construction. The meetings were held on September 18,
1996 and November 21, 1996.
An initial study and a traffic study have been prepared for the project and a finding of a
Negative Declaration for this project has been proposed. The plans and specifications are
substantially complete and will be ready for advertisement to obtain bids on March 11, 1997.
An Encroachment Permit Application has been filed with Caltrans and a permit is expected to
be received prior to the award of the construction contract.
ANALYSIS:
Railroad Avenue Improvement Project Only (75 -Foot Right -of -Way)
This project is proposed to realign and widen Railroad Avenue from an existing 60 -foot right-of-
way width to 75 feet. It would provide two travel lanes, one two-way left -turn lane, parking on
the east and west sides of the street, and sidewalks on the west side of the street.. Due to right-
of-way acquisition costs, this project would be over budget by an estimated $700,000. Two
larger partial property acquisitions would require substantial severance compensation, which
could be avoided if the entire parcels were acquired for the proposed Newhall Metrolink station.
Construction of this project must be completed by December 1997 and all funds expended,
including construction retention, by February 1998.
Confinued To: , - 1--9 Agenda item: C
RAILROAD AVENUE IMPROVEMENT PROJECT NO. 95-065
NEWHALL METROLINK STATION
February 25, 1997 - Page 2
It is important to note that the funding for the Railroad Avenue Improvement Project will expire
after February 1998. The Economic Development Administration (EDA) grant has been
submitted for final approval. The closing date to submit for final approval of an EDA grant has
passed, and the grant cannot be directed to another project. The EDA funds -would be lost
should the Railroad Avenue Improvement Project be canceled due to lack of time.
The Community Development Block Grant (CDBG) of $2,257,715 must also be expended by
February 1998. Should the Railroad Avenue Improvement Project be canceled, the CDBG grant
would be immediately reallocated to a different project.
Railroad Avenue Improvement Project. Newhall Metrolink Station Site Acquisition and Off -Site
Improvements (85 -Foot Right -of -Ways
This project would include the scope identified above plus the following: an additional 10 -foot
right-of-way, for an ultimate 85 -foot right-of-way. This would provide sidewalk, landscaping,
irrigation, and street lighting on the east side of Railroad Avenue, which would be required to
service the proposed Newhall Metrolink station. This project would also upgrade the Market
Street railroad crossing, interconnect the Market Street railroad crossing signals with the
intersection of San Fernando Road and Market Street, and relocate an existing spur track
adjacent to Railroad Avenue. The property acquisitions would include the acquisition of the
Newhall Metrolink site. (This acquisition would eliminate compensation of severance costs.)
The benefits of combining the two projects would be the cost savings of reduced engineering,
design, construction administration, and construction engineering expenses, and the elimination
of severance compensation for the acquisition of two parcels. These cost savings will provide
the landscaping, irrigation, sidewalks, and street lighting on the east side of the street
($500,000 value). Should these two projects be constructed separately, funds would not be
available in either project to provide these improvements.
Other benefits would include reduced disruption to the adjacent business and property owners
during construction, as the improvements to Railroad Avenue would be constructed at one time
and construction time would be reduced.
The investment opportunities noted above are planned to be financed with funding from a
variety of sources. Each of these sources is considered to be secured, with the exception of a
portion of the Newhall Metrolink station. Should that portion ($1,975,010) of the Metrolink
station source fail to materialize, the current Transit budget contains sufficient funds that can
be reallocated over the next two fiscal years to cover the cost. It is important to note, however,
that such use of these funds could delay some expansion of Transit services, the scope of the
planned Transit Center near the mall, and other future capital projects.
RAILROAD AVENUE IMPROVEMENT PROJECT NO.. 95-065
NEWHALL METROLINK STATION
February 25, 1997 - Page 3
Railroad Avenue Improvement Project Newhall Metrolink Station Off -Site and On -Site
Improvements (85 -Foot Right -of -Way)
This project includes all the improvements of the previously discussed project and also includes
the construction of the on-site station improvements. The total cost of these combined
improvements is $7,132,750.
No Project
Should the Railroad Avenue Improvement Project not be constructed, the City would lose an
EDA grant up to $601,975. The CDBG grant in the amount of $2,257,715 would be reallocated
to an overlay project in another area of the City. Additionally, the City has already incurred
approximately $400,000 in design costs, which would not be reimbursed.
The Newhall Metrolink station grant applications did not include expenses related to improving
Railroad Avenue. For the station to be constructed, the City would have to identify resources
for the additional $2,859,690 required to improve Railroad Avenue. Should these resources not
be identified, the Newhall Metrolink Station Project would also be canceled.
The loss of the Railroad Avenue Improvement Project and the Newhall Metrolink station would
greatly affect the revitalization of downtown Newhall, as this would be a loss of a $7,132,750
investment in the area.
Due to the complexity of this project, staff would like to brief Council in detail regarding the
proposed recommendation below. See the attached March 11, 1997 City Council Meeting
Recommendation Summary.
RECOMMENDATION
1. - City Council accept, review, and discuss the report on the Railroad Avenue Improvement
Project No. 95-065, and the siting of the proposed Newhall Metrolink station.
2. City Council direct staff to return with recommendations for the Railroad Avenue
Improvement Project and Newhall Metrolink station off-site improvements to the March 11,
1997 City Council Meeting.
Proposed Recommended Actions for the Railroad Avenue Improvement Project and Newhall
Metrolink Off -Site Improvements at the March 11 1997 City Council Meeting
1. City Council approve the location of the Newhall Metrolink site.
2. City Council adopt a Negative Declaration pursuant to Section 15070 of CEQA.
3. City Council adopt a Resolution of Necessity for Immediate Possession of the two (2)
parcels required for the Newhall Metrolink site and the widening and reconstruction
of Railroad Avenue.
RAILROAD AVENUE IMPROVEMENT PROJECT NO. 95-065
NEWHALL METROLINK STATION
February 25, 1997 - Page 4
4. City Council adopt a Resolution of Necessity for Immediate Possession of the eight
partial -takes required for the widening and reconstruction of Railroad Avenue.
5. City Council authorize the advertisement for bids for the Railroad Avenue Improvement
Project.
6. City Council approve a change order to the existing design contract with HDR
Engineering, Inc. in the amount of $85,000.
March 11, 1997 City Council Meeting Recommendation Summary
Railroad Avenue Improvement Vicinity Map
List of Acquisitions (full- and partial -takes)
Eminent Domain Summary
Project Schedule
EIS and Traffic Study in Reading File in City Clerk's Office
BEJ:lkl
mun5H\.-95065.b6
MARCH 11, 1997 CITY COUNCIL MEETING
RECOMMENDATION SUMMARY
ACTION ITEMS NECESSARY AT MARCH 11, 1997 CITY COUNCIL MEETING:
.. .>isiH"tta�[d'.+llflii�i'I3�iQ;f;z.`I�Il:T1T: •:
Staff has identified a site for the construction of the Newhall Metrolink station. The site
is located on the east side of Railroad Avenue, north and south of Market Street. The north
parcel is currently occupied by Newhall Hardware's Garden Center. Staff has met with
MTA and SCRRA, and they have indicated that this location is the preferable site for the
platform and station. The Railroad Avenue and Market Street location was identified in
the Downtown Newhall Improvement Program as the preferred location for the Metrolink
station. On February 3, 1997, the Newhall Redevelopment Committee voted (15-1) to
recommend that the City Council authorize site acquisition and construction of the Newhall
Metrolink station.
If the site proposed for the Newhall Metrolink station is not approved by the City Council,
staff would request that. the Council approve the partial acquisition of the site necessary
for the widening of Railroad Avenue. Additional funds would be necessary for the right-of-
way acquisition required for Railroad Avenue, as these two parcels would have been
acquired by Transit funds for the station.
RECOMMENDATION: Staff will request that the City Council approve the Newhall
Metrolink site location.
2. Adoption of Negative Declaration
An Environmental Assessment and Initial Study has been prepared for the Railroad Avenue
Improvement Project. A proposed Negative Declaration has been prepared that indicates
the project will not have a significant effect upon the environment.
Further project continuation is contingent upon this approval.
RECOMMENDATION. Staff will request that City Council adopt a Negative Declaration
pursuant to Section 15070 of CEQA.
3. After Conductina_a
PublicProposed
that
the CityCouncilAdopt
a Resolution
Necessity
for the Order
of Immediate Possession
- Two Parcels
for Proposed
Newhal
Metrolinkof
I
Acquisition of the Newhall Metrolink site involves the relocation of an existing business.
A portion of the Metrolink site will be designated for Railroad Avenue road widening. In
order to reduce the costs of acquisition and eliminate costs due to severance compensation,
it would be in the City's interest to acquire the site as a whole rather than acquiring a
portion of the site needed for the widening of Railroad Avenue, and then later acquiring the
remainder of the site for the. Metrolink station.
As relocation of the existing business needs to be addressed in this acquisition, the City is
required to give a 90 -day notice to vacate the property. This can only happen after an
Order of Immediate Possession is issued by the court. The federal grants received for the
Railroad Avenue Improvement Project require that the City expend all funds by
February 1998. To accomplish this, construction must begin by June 1997. The City will
need to obtain an Order of Immediate Possession on March 11, 1997 to start the business
relocation process and complete it in time for construction to begin.
If the acquisition and site proposed for the Newhall Metrolink station is not approved and
the Resolution of Necessity is not adopted by the City Council, staff would request that the
Council approve the partial acquisition of the site necessary for the widening of Railroad
Avenue. Additional funds (in excess of the CDBG and EDA grants) would be necessary for
the right-of-way acquisition required for Railroad Avenue, as these two parcels would have
been acquired by Transit funds should this be the location acquired for the station. Should
the City fail to meet the demands of this schedule, it puts the project at risk for cancellation
due to the time limitations of the funding.
RECOMMENDATION: Staff will request that after a public hearing, the City Council
adopt a Resolution of Necessity for Immediate Possession of the two parcels required for
the Newhall Metrolink site and the widening and reconstruction of Railroad Avenue.
Due to the partial realignment of Railroad Avenue in order to reduce the existing curves
near 6th Street and 8th Street, and in order to conform with ADA (Americans with
Disabilities Act) requirements, staff will request that Council authorize the acquisition of
eight partial -takes along Railroad Avenue.
A total of ten (10) partial -takes, two of which would be included in the acquisition of the
Metrolink site, need to be acquired for the additional right-of-way necessary to construct
the Railroad Avenue Reconstruction Project. The City is currently negotiating with the
owners of the properties. Staff is requesting that Council adopt the Resolution of Necessity
so that, in the event that negotiations stall, the City will be able to obtain immediate
possession of the property prior to the start of construction.
Should Council not adopt the Resolution of Necessity .for the Order of Immediate
Possession, the project would be canceled, as it cannot be constructed without obtaining the
required right-of-way.
RECOMMENDATION: Staff will request that after a Public Hearing, the City Council
adopt a Resolution of Necessity for. Immediate Possession of the eight partial -takes
required for the widening and reconstruction of Railroad Avenue.
5. Authorize the Advertisement for Bids
The plans and specifications will be ready for advertisement to obtain bids for construction.
The federal grants require that we have a bid advertisement period of at least 30 days.
Due to the timing constraints of this project, staff will need to. advertise and award a
contract for construction within the next three months. This process will take at least three
months and will require a decision at the Council meeting of March 11, 1997.
RECOMMENDATION: Staff will request that the City Council authorize the
advertisement forbids for the Railroad Avenue Reconstruction Project.
"Mme TWU•e7=874 - 3 • 2 1 •• 1- a•
Staff has incorporated the necessary off-site public improvements that will be required for
the Newhall Metrolink Station into the construction documents for the Railroad Avenue
Improvement Project in order to expedite and reduce construction costs for the Metrolink
station. Due to this additional scope of work being added to the design of the Railroad
Avenue Improvement Project, staff recommends to increase the design contract from
$300,000 to $385,000.
RECOMMENDATION: Staff will request that Council approve a change order to the
existing design contract with HDR Engineering, Inc. in the amount of $85,000.
BEJ:1k1
m calk rv95065.bej
VICINITY MAP
N, T. S.
RAILROAD AVENUE PROPERTY ACQUISITION LIST
PROJECT NO. 95-065
The following properties will be reviewed for partial right-of-way acquisition for construction of
the Railroad Avenue Improvement Project:
1) APN 2831-007-019
NW Corner of 9th Street and Railroad Avenue
2) APN 2831-010-038
SW Corner of 9th Street and Railroad Avenue
3) APN 2831-018-015
NW Comer of 5th Street and Railroad Avenue
4) APN 2831-014-005
SW Comer of Market Street and Railroad Avenue
5) APN 2831-010-011
NW Corner of 8th Street and Railroad Avenue
6) APN 2831-026-900, 901, 904-913
MTA Right of Way East of Railroad Avenue between 4th Street and 11th Street
7) APN 2831-026-001
East side of Railroad Avenue between 6th Street and 8th Street
(Nursery and vacant lot)
8) APN 2831-019-021
SW Comer of 5th Street and Railroad Avenue
9) APN 2831-018-009
SW Corner of 6th Street and Railroad Avenue
10) APN 2831-010-043
West side of Railroad Avenue approx. 50' North of 8th Street
BEI:
engtivA95-065Sncq.1ist.bej
EMINENT DOMAIN SUMMARY
PROJECT NO. 95-065
oiect Des12n/ProDerty Acauisition Reauirements
The improvements to Railroad Avenue intend to realign the existing centerline at 6th and 8th
Streets to provide a smoother transition for traffic as currently a right angle jog must be negotiated
at these two intersections. As the Newhall Metrolink Station is proposed to be constructed in this
area, realigning Railroad Avenue to provide a smoother transition will make the station accessible
to buses, and vehicle and pedestrian friendly. Other improvements include the widening of Railroad
Avenue from an existing 60 -foot width to an 85 -foot width. This new right-of-way will provide an
additional 15 feet of roadway and 10 feet of parkway to provide sidewalks, street lighting,
landscaping, and irrigation for the proposed Newhall Metrolink Station.
Property Acquisition Procedures
Due to the realignment and widening of Railroad Avenue, additional right-of-way must be obtained.
In order to accomplish this, the City, as a public agency, must exercise its right to use eminent
domain. This procedure involves notifying each affected property owner of the City's intent to
appraise the property. Then an appraisal is performed to establish the "fair market value" of the
property to be acquired. The appraisal also determines whether severance damages exist. Any
relocations that may be required as a part of the acquisition of the property are also identified. An
offer to purchase property is prepared and submitted to the property owner and. negotiations begin.
As the City is a public agency an offer cannot be made for less than the fair market value of the
property.
If timing is not an issue, the negotiation process can go on indefinitely, but as timing is usually a
factor due to funding constraints the City usually proceeds with the next phase of the eminent
domain process, which is to adopt the Negative Declaration finding for the project, hold a public
hearing, and then adopt a Resolution of Necessity including authorization to seek an Order of
Immediate Possession of the properties. The City then files an action and seeks an Order from the
court. A deposit of the amount of the established fair market value must be made in court to obtain
an order as to each property sought.
In this case negotiations are proceeding in a "friendly" manner and the staff is meeting individually
with the affected property owners concerned, but because the relocation of a business will be
required due to this project and the future construction of a metrolink station, the Order of
Immediate Possession must be filed and the Order to Vacate must be delivered to the business
and\or property owner 90 days prior to the City's possession of the property. The Railroad Avenue
construction project is scheduled to start construction in June 1997 in order to have construction
completed, project acceptance recorded and the retention released by February 1998. Should Council
adopt the Resolution of Necessity at its March 11, 1997 Council Meeting, the earliest date that the
City could take possession of the property would be in late June 1997.
In general, property owners prefer the use of eminent domain. Eminent domain provides a tax
benefit to the property owner as the condemnation process allows the property owner three years
to reinvest the settlement amount received by the City in order to avoid capital gains tax.
Negotiations would continue throughout this process. If a settlement is reached, an agreement
would be drawn up and payment would be made for the acquisition. If a settlement is reached after
the action is filed, a stipulation for judgement would be signed and filed with the court. It is
necessary for the City to obtain an Order of Immediate Possession from the court to ensure that the
City would have possession of the property in time for construction of the project should negotiations
deteriorate.
BEJ:lkl
eng-drik9s-mNemi" t.w
RAILROAD AVENUE STREET IMPROVEMENTS
PROJECT SCHEDULE
10
Taak Noma
0 s
Sferl
Flnish
Otrt 1937 0121937 Ob01991
Jen Feb Mar A Ma Jun JW
Qtra 1991
Ob1 1998
OV21988
0" 1998
Oct Nov Dee
Jan Feb Mar
A Ma Jun
JW
1
GA
CETROUNKAPPR
MERiOLINKAPPflOVAL
ROW ACQUISITION
I711L3TY RELOCNERMRS
DEMGNRIDIAWARD
CONSTRUCTION
PROJECTCLOSEOUT
88tl 112357
29d xlLB7
1043 1121197
118E 1m191
780 MUST
M18E 511497
aBA /x12xS7
MOS
MINT
3N1S]
&1497
71997
511387
1012497
xFJM
'
6
10
18
25
37
u
proj�.
Data:2/IW97
Task
progress
milaskme ♦ RoNed Up Task
Summery ^ RoneSUp MIWMone Q
Rgled Up Progress
GmunOSmaWag -k
211fl97
Page l