HomeMy WebLinkAbout1997-05-13 - AGENDA REPORTS - PERFORMANCE REVIEW OF ATC CONT (2)AGENDA REPORT
City Manager Approval
Item to be presented by:
Ron Kilcoyne
UNFINISHED BUSINESS
DATE: May 13, 1997
SUBJECT: PERFORMANCE REVIEW OF ATC CONTRACT
DEPARTMENT: Public Works
BACKGROUND
At the April 1, 1997, City Council Study Session, Council indicated to ATC/Vancom, the City transit
contractor, and staff they expected immediate improvements made in resolving problems relating
to Commuter Express bus service and wishes to review contract status within 30 days. The Council
indicating it could be possible that they would direct staff to invoke contract cancellation or other
appropriate action against ATC/Vancom if service improvement was not satisfactory at this time.
Several actions have been taken to improve Commuter Express bus service. These actions and the
results of these actions are summarized in attachment A. Particularly noteworthy from this report
is that with additional buses available for service, problem buses have now been pulled out of service
for full service to repair all defects.
After reviewing the contractor performance over the past month, the Council has several options as
to how to proceed vis-a-vis the transit service contract. These options include canceling the contract
with ATC, selecting another contractor to operate the commuter express service, retaining ATC for
local and dial -a -ride services, or taking no action, thereby allowing ATC to continue operating all
services as per their contract. The pros and cons for each option are summarized in attachment B.
RECOMMENDATION
City Council provide direction to staff on how to proceed regarding the transit service contract with
ATC/Vancom.
Pt"X"•1I2"
Summary of actions taken to improve Commuter Express bus service and the results of these actions.
Summary of options available to City regarding future action pertaining to the service contract
between the City and ATC/Vancom and the pros and cons of each oppp{{{tion.
SXCAGV 4ENDAWGENDCMM.ATC j� ®nda lJ�,el. � n
APPROVED Y�
SUMMARY OF ACTIONS TAKEN BY ATCNANCOM TO
CORRECT DEFICIENCIES IN COMMUTER SERVICE
This summary is meant to only highlight the major areas where ATC placed its focus. It does not
capture the hundreds of additional hours or the thousands of dollars spent to make sure these
improvements take place.
Problems Identified:
Frequent Service Delays • Front Doors Opening
Buses not Clean • No Heat/AC
Actions Taken:
• Purchase of Spare Buses
Arrivals: 4/4/97, 4/10/97, 4/28/97 & 5/12/97
• Modifications to Fleet
1991 Neoplans to be re -tuned to reduce overheating 90% completed
1986 Neoplan Upgrading
Doors 60% completed Engine/Transmission 30% completed
AC/Heat 60% completed Seats (Only 3 Out of 10) 0% completed
• Cleaning Program Enhanced by
Increase of Personnel and Additional Training
Improvement to Cleaning Process
• Hired Two More Class "A" Mechanics
• Subcontract Some Commuter Service
Two Service Trips from the Lancaster Area to be Done by AVB (effective 5/5/97)
• Conducted two meetings with the Ambassadors to receive input and share ideas
• Sent out three (3) letters to our commuter customers keeping them informed as to our
plans and actions
• Provided weekly updates to Transit Staff on progress of our plan
Results to Date: (210 Commuter Trips Weekly)
• Week of 4/7
9 Delays or
4% of Trips
• Week of 4/4
3 Delays or
1.4% of Trips
• Week of 4/21
5 Delays or
2.3% of Trips
• Week of 4/28
2 Delays or
1.0% of Trips
With the arrival of four additional buses and subcontracting of two buses, major work on the
1986 Neoplans can be intensified. We will continue with the program until all items originally
identified are corrected, and we meet or exceed all requirements as outlined in the contract. It is
our goal to take this beyond the expectation so that this never occurs again.
SUMMARY OF OPTIONS AVAILABLE TO CITY
REGARDING TRANSIT SERVICE CONTRACT
OPTION
PRO
CON
1. Cancel contract with ATC/Vancom
Perceived attention to customer
Possible disruption to all transit
The City could either give ATC
needs.
services during the transition to new
30 days notice, without
contractors. This could be prolonged
explanation, or immediate
over several months since it is
notice, for breach of contract. In
possible that three different
order to avoid a disruption of
contractors could operate service (the
service, a 30 day notice would be
current contractor, the interim
advised. The City would select
contractor, and the new contractor) in
another contractor capable of
a period of less than one year.
taking over the contract on short
Delays to other transit projects, such
notice for an interim period
as the Newhall Metrolink Station and
while an RFP is issued and a
Town Center Transit Center, as
new permanent contractor is
considerable staff time is diverted to
selected
selecting an interim and permanent
contractor and dealing with transition
issues.
• Possible negative impact on recent
MOU with Hart School District.
• Added operating costs (from likely
higher rates), not reflected in
proposed budget for FY 1997/98.
• No guarantee that replacement
contractor(s) will provide better
service.
Page 1
OPTION
PRO
• CON
2. Cancel the Commuter/Express
No disruption to local and dial-a-ride
Possible disruption to
portion of the contractor, allow
service.
Commuter/Express service during the
ATC/Vancom to continue to provide
transition to new contractors. This
local and dial-a-ride services.
could be prolonged over several
As with option #1, the City
months since it is possible that three
would select an interim
different contractors could operate
contractor for
service (the current contractor, the
Commuter/Express service while
interim contractor, and the new
an RFP is issued to select a
contractor) in a period of less than
permanent contractor far this
one year.
service.
Delays to other transit projects, such
as the Newhall Metrolink Station and
Town Center Transit Center, as
considerable staff time is diverted to
selecting an interim and permanent
contractor and dealing with transition
issues.
• Once stability is reached, additional
staff time will need to be devoted to
administering two contracts instead of
one as at present.
• Loss of economy of scale and
operational flexibility that comes with
a single contractor. The higher costs
to the individual contractors will be
passed on to the City through the
hourly rate charged.
• No guarantee that replacement
contractor(s) will provide better
service.
Page 2
OPTION
PRO
CON
3. Take no action, allowing ATC to
& No disruption of service due to
May be perceived at satisfaction with
continue operating all services per
transition to new contractors.
status quo.
existing contract.
0 Staff and contractor time can be
This option reaffirms the current
devoted to continued service
contractual arrangement with
improvement and other priority
ATC.
projects.
• No loss of economy of scale or
operational flexibility resulting from
separate contractors.
SACCAGENDAW GENDATH.ATC
Page 3