HomeMy WebLinkAbout1997-06-24 - AGENDA REPORTS - SANTA CLARA RIVER TRAIL PH III (2)AGENDA REPORT
City Manager Approval
Item to be presented by:
Rick Putnam
CONSENT CALENDAR
DATE: June 24, 1997
SUBJECT: SANTA CLARA RIVER TRAIL - PHASE III
PROJECT NO. 99-047-02 - BID AWARD
DEPARTMENT: Parks, Recreation, and Community Services
On April 8, 1997, City Council authorized the advertisement of Project 99-047-02. This project
consists of the construction of a Class I (off-road) bicycle trail adjacent to the north side of
Soledad Canyon Road and Valencia Boulevard, between the Metrolink Station and the South
Fork of the Santa Clara River (see attached project map).
The Engineers Estimate for this project was $1,299,691. The following bids were received by
the City Clerk on June 12; 1997:
Gueno Development Company
Los Angeles
$ 988,614.00
Valley Crest Landscape
San Fernando
$1,079,261.00
Nye & Nelson
Ventura
$1,090,749.50
R -Help Construction
Newbury Park
$1,138,597.10
Terra -Cal Construction
Baldwin Park
$1,142,531.02
R. C. Becker & Son, Inc.
Newhall
$1,169,135.28
Excel Paving
Long Beach
$1,249,877.00
Pima Corporation
Santa Monica
$1,258,847.50
Ecology Construction
Canoga Park
$1,327,652.50
C.A. Rasmussen
Lancaster
$1,405,641.83
This project (as well as the adjacent bridge Project No. 99-047-01) are being made
possible through a combination of PFA, Proposition 116, Proposition C, and Developer
funds. Appropriate accounts have been established for both this project and the bridge
project under master account no. 80001. Sufficient budget, including a 15% contingency
for unforseen conditions, is available in the project account to award construction of this
project.
Assend Item: 3
That Council award a contract to the low bidder, Gueno Development Company, Inc., in
the amount of $988,614.00 and authorize a contingency expenditure of 15% for unforseen
conditions. Authorize the City Manager or his designee to approve all documents
relating to this contract, and to execute all licenses, agreements, and easements related
to this project. Authorize entering into inspection and testing services with Lundgren
Management and Almanza Consulting for a total construction. management amount not
to exceed $45,000.
Project Map
REP:KDN:ltk
prlpfa devO9047-024Zq_cc.02
MOTE; BICYCLE BRIDGE OVER SOUTH FORK