HomeMy WebLinkAbout1997-04-08 - AGENDA REPORTS - SANTA CLARA RIVER TRAIL PHASE (2)AGENDA REPORT
City Manager Approval
Item to be presented by:
Rick Putnam
CONSENT CALENDAR
DATE: April 8, 1997
SUBJECT: SANTA CLARA RIVER TRAIL - PHASE III
PROJECT NO. 99-047-02 - ADVERTISE FOR BIDS
DEPARTMENT: Parks,.Recreation, and Community Services
Project 99-047-02 consists of the construction of a Class I (off-road) bicycle trail adjacent to the
north side of Soledad Canyon Road and Valencia Boulevard, between the Metrolink Station and
the South Fork of the Santa Clara River near Creekside Road (see attached project map).
Due to design and construction constraints, staff proposes that improvements be constructed
under two separate design packages. Project No. 99-047-01 has been identified for the bicycle
bridge across the South Fork, and Project No. 99-047-02 has been identified for the remainder
of the trail. Project No. 99-047-02, which is currently under final design review, incorporates
design features similar to those of the adjacent Commuter Rail Trail, except that landscaping
will not be provided due to space restrictions along the river.
Budget in the amount of $805,390 (PFA Funds); $573,000 (Developer Funds); $473,762.86
(Proposition 116 Funds); and $300,000 (Proposition C Funds) were previously authorized by City
Council for the entire project. Appropriate fund accounts to track these costs have been
established by staff under Account No. 80001.
City Council authorize staff to issue a Notice Inviting Bids for Project No. 99-047-02, the "trail'
portion of the project, subject to incorporation of final design review comments. Council
adoption of the plans and specifications to be made at the time of contract award.
Project Map
REP:KDN:Itk