Item to be presented
Andrew Yi
CONSENT CALENDAR
DATE: August 26, 1997
SUBJECT: TRAFFIC SIGNAL INSTALLATION AT WILEY CANYON ROAD/
LA GLORITA CIRCLE-EVANS AVENUE - PROJECT ACCEPTANCE
(PROJECT NO. 20002)
DEPARTMENT: Transportation and Engineering Services
On March 27, 1997, the City Council awarded a contract for the subject project to TDS
Engineering. This project consisted of the installation of a traffic signal at the intersection of
Wiley Canyon Road/La Glorita Circle -Evans Avenue.
This project was completed to the satisfaction of the City Engineer as of August 5, 1997. The
project was completed on time and within the budget. The .total budget of $140,000 was
allocated for this project, including design, construction, inspection, and administration. The
actual cost for this project is estimated at $112,000.
ImpLkehHUT ►l�� •►
1. City Council accept the work performed by TDS Engineering on the traffic signal installation
project at the intersection of Wiley Canyon Road and La Glorita Circle -Evans Avenue;
2. City Council direct the City Clerk to file the attached Notice of Completion for the project;
and
3. City Council direct staff to release the 10 percent retention 35 days after the Notice of
Completion is recorded, provided no Stop Notices, as provided by law, have been filed.
Notice of Completion
AY:lkl
mwallwlegdaay
Ag
A PROVED enda Iten,
V
RECORDING REQUESTED BY:
City of Santa Clarita
Transportation and Engineering Services Department
WHEN RECORDED, MAIL TO:
Sharon L. Dawson, CMC, City Clerk
City of Santa Clarita
23920 Valencia Boulevard, Suite 301
Santa Clarita, CA 91355-2196
RECORDLNG FEES EXEMPTED
G.C. $ 6103 AND 27383 Space Above This Line For Recorder's Use
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN:
1. The City of Santa Clarita, a municipal corporation, is the owner in fee, except for the right-
of-way upon which it has been constructed, of a certain public improvement known as:
Traffic Signal Installation at the intersection of Wiley Canyon Road and La Glorita Circle -
Evans Avenue, Project No. 20002.
2. The CiWs address is: 23920 Valencia Boulevard, Suite 300, Santa Clarita, CA 91355-2196.
3. The general location of said public improvement is: at the intersection of Wiley Canyon
Road and La Glorita Circle -Evans Avenue.
4. On March 27, 1997, a contract to construct said public improvement was awarded to: TDS
Engineering, 2899 Agoura Road, Suite 171, Westlake Village, CA 91361-3200.
5. Work under said contract was completed on August 5, 1997, to the satisfaction of the City
Engineer, and was accepted by the City on X997. atgwaJ Z6, 1,7f7
State of California
County of Los Angeles
City of Santa Clarita
I have read the foregoing Notice of Completion and know its contents. I am the City Clerk of
the City of Santa Clarita and am authorized to make this verification for and on its behalf, and
I make this verification for that reason. I am informed and believe and on that ground allege
that the matters stated in the foregoing document are true. 'I declare under penalty of perjury
under the laws of the State of California that the foregoing is true and correct.
Sharon L. Dawson, CMC, City Clerk Date
City of Santa Clarita
AY:lk1
wunct\.i.ea,..r