SUBJECT: EL NIIVO 1998 - EMERGENCY STORM REPAIRS UPDATE
DEPARTMENT: Transportation and Engineering Services
RECOMMENDED ACTION
City Council appropriate additional budget to provide for El Nino 1998 storm repairs in the
amount of $269,800.83 from City Council Fiscal Year 1997-98 Contingency Account
No. 1240-7401. Accept the work performed by Oberg Contracting Corporation for emergency
repairs relative to the El Nifio 1998 Storm season. Direct the City Clerk to file the attached
Notice of Completion.
On February 24, 1998, the City Council appropriated $650,000.00 from the Contingency
Account, based on a preliminary estimate of the storm damages. The final costs for the
emergency repairs contract with Oberg are $493,179.49. Additionally, the Los Angeles County
Public Works Department completed emergency repairs to the Bouquet Canyon Bridge in the
amount of $168,945.55. The additional funds requested are the net result of some projects
costing less than estimated and some costing more than estimated (please refer to the attached
chart of projects).
Emergency repairs for both the Bouquet Canyon Bridge and the Santa Clara River across from
the Saugus Speedway were approved after the Federal Highway Administration (FHWA) and
Caltrans representatives conducted a field review on April 29, 1998. A subsequent Caltrans
field review on June 16, 1998 resulted in the approval of six additional sites. These approvals
provide for full reimbursement of the cost incurred to complete the emergency repairs. Caltrans
did not approve five sites that are not a part of the Federal Aid Highway system, but these will
be submitted to the Federal Emergency Management Administration (FEMA) for possible
funding. The United States Department of Argriculture (USDA) will provide 86 percent
reimbursement on the Pine Street project. Upon successful approval and obligation of funding
from the Federal agencies, approximately $823,324.00 will be reimbursed, resulting in a local
match of approximately $96,477.00. This liability includes a portion of construction
engineering costs in excess of the allowable 8% for FEMA and 15% for FHWA. The attached
chart reflects cost estimates the City Council approved on February 24, 1998, the final costs to
complete the repairs, and the requested additional appropriations for each project location.
This project was completed to the satisfaction of the City Engineer on April 15, 1998.
p�p�Ood�D A�encla item: -Q
EL NANO 1998 — EMERGENCY REPAIRS
July 14, 1998 —Page 2
ALTERNATIVE ACTIONS
Other action as determined by the City Council
FISCAL IMPACT
Appropriations of $650,000.00 have been approved for El Nino Emergency Response
Expenditures. Additional funding is required in the amount of $269,800.83.
ATTACHMENTS
Notice of Completion
1998 El Nino Storm Update
CCP:DMK:vjj
C..61NAR-STRM2.d.0
RECORDING REQUESTED BY:
City of Santa Clarita
Transportation and Engineering Services Department
WHEN RECORDED, MAIL TO:
Sharon L. Dawson, CMC, City Clerk
City of Santa Clarita
23920 Valencia Boulevard, Suite 301
Santa Clarita, CA 91355-2196
RECORDING FEES EXEMPTED
G.C. § 6103 AND 27383
NOTICE IS HEREBY GIVEN:
Space Above This Line For Recorder's Use
NOTICE OF COMPLETION
1. The City of Santa Clarita, a municipal corporation, is the owner in fee of a certain public
improvement known as: El Nifio 1998 Emergency Storm Repairs.
2. The City's address is: 23920 Valencia Boulevard, Suite 300, Santa Clarita, CA 91355-
2196.
3. The general location of said public improvement is: Santa Clarita - Various Locations
Citywide.
4. On March 24, 1998, a contract to construct said public improvement was awarded to:
Oberg Contracting Corporation, 2132 Winifred Street, Simi Valley, CA 93062.
5. Work under said contract was completed on April 15, 1998, to the satisfaction of the City
Engineer, and was accepted by the City on July 14, 1998.
STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES ) ss.
CITY OF SANTA CLARITA )
I have read the foregoing Notice of Completion and know its contents. I am the City Clerk of
the City of Santa Clarita and am authorized to make this verification for and on its behalf, and
I make this verification for that reason. I am informed and believe and on that ground allege
that the matters stated in the foregoing document are true. I declare under penalty of perjury
under the laws of the State of California that the foregoing is true and correct.
Sharon L. Dawson, CMC, City Clerk
City of Santa Clarita
Date
1998 EL NINO STORM UPDATE
engcivMlo,m\uptlaie2ab 7/8/98
Account
Council Approved
Additional
Funding
Project Location
Number
Emergency Fund
Actuals
Appropriations
PA
Santa Clara Rvr@Speedway
E4302001
$65,000
$236,955.54
$171,955.54
FHWA
Santa Clara Rvr @ Luther
E3208001
$50,000
$16,564.50
-$33,435.50
FEMA pending
Creekview Park
E2205001
$40,000
$18,501.42
-$21,498.58
FEMA pending
Bouquet Cyn RdBgtCreek
E4305001
$25,000
$17,824.54
-$7,175.46
FHWA
Santa Clara Rvr e/o Mint Cyn
E3209001
$20,000
$6,928.39
-$13,071.61
FEMA pending
Towsley Canyon Park
E2601001
- $10,000
$1,987.47
-$8,012.53
FEMA pending
Soledad Cyn Rd/Sta.Clara Rvr
E3503001
$3,084
$6,090.12
$3,006.47
FHWA
Sierra Hwy s/o San Fernando
E3304001
$20,000
$68,741.20
$48,741.20
FHWA
Soledad Cyn Rd @ CC Park
E3501001
$5,000
$8,725.17
$3,725.17
FHWA
Sand Canyon over Iron Cyn
E3206001
$20,000
$60,401.23
$40,401.23
FHWA
Pine Street s/o San Fernando
E2204001
$50,000
$95,238.59
$45,238.59
USDA
Sierra Hwy @ Cemetery
E3303001
$20,000
$54,702.65
$34,702.85
FHWA
Bouquet Cyn over S.Clara Rvr
E4207001
$242,646
$223,009.49"`
-$19,636.85
FHWA
' This amount Includes $170K for LACPW repairs
Debris Removal and
E0101001 8
Emergency Protection -Citywide
E0201001
$39,000
$92,493.47 *
$53,493.47
FEMA
This amount Includes staff overtime
Calgrove Barricade
E2202001
$13,000
$0.00
-$13,000.00
no project
Canyon Country Roof
E3502001
$10,000
$0.00
-$10,000.00
FEMA
Corporate Yard Roof
E1503001
$7,000
$0.00
-$7,000.00
FEMA
South Fork Trail
E2203001
$6,000
$3,894.80
-$2,105.20
FEMA
Trail under Bouquet Cyn Bridge
E4211001
14m
$7,742.05
$3,472-04
FEMA pending
Reimbursement costs pending approval
$650.000
from FHWA, USDA, or FEMA:
$919.800.83
$823,324.00
$269.800.83
Local Match..................................................................................
$96,476.8a
engcivMlo,m\uptlaie2ab 7/8/98