HomeMy WebLinkAbout1998-08-25 - AGENDA REPORTS - INFRASTRUCTURE PROJ RESULTS (2)CITY OF SANTA CLARITA
AGENDA REPORT
CONSENT CALENDAR City Manager Approv 1
Item to be presented by: Kerry Breyer
DATE: August 25, 1998
SUBJECT: 1997-98 & 1998-99 ANNUAL INFRASTRUCTURE PROJECTS — BID
RESULTS
DEPARTMENT: Transportation & Engineering Services
RECOMMENDED ACTION
The City Council ratify the contract entered into by the City Manager with Excel Paving
Company under the authority granted by Council on July 14, 1998.
Project Name Proiect No. Account Nos.
1997-98 Annual Overlay Program M0002 - M0002205, M0002455
1997-98 Annual Slurry Program M0003 M0003103, M0003201,
M0003455
1997-98 Annual Access Ramp Construction
T0006
T0006103
1997-98 Annual Curb & Gutter Repair .
M0004
M0004052
1997-98 Annual New Sidewalk Program
T0007
T0007103
1998-99 Annual Sidewalk Repair
PWS -5
5211-8061
1997-98 Annual Median Modifications
C0013
C0013455
North Oaks Park — Parking Lot Pavement Rehab.
N/A
5100-8001/8110
Santa Clarita Park — Parking Lot Pavement Rehab.
N/A
5100-8001/8110
1998-99 Annual Overlay Program
M0027
M0027001, M0027205
1998-99 Annual Slurry Program
M0028
M0028001
1998-99 Annual Access Ramp Construction
T0011
T0011201
1998-99 Annual Curb & Gutter Repair
M0026
M0026456
1998-99 Annual New Sidewalk Program
T0012
T0012201
1998-99 Annual Sidewalk Repair
PWS -6
5211-8061
Orchard Village Traffic Signal Interconnect
C2014
C2014001
16th Street Sidewalk Installation
LMD177
7515-8001
BACKGROUND
Bids were received -by the City Clerk's office on July 23, 1998. Ordinarily after a bid
opening, staff prepares a bid summary and verifies ,the following: licensing of the low
bidder; financial condition of the surety company; bid bond; and references on past projects.
Staff then prepares an agenda report recommending that Council award a contract to the
lowest responsible bidder. However, the schedule of this project conflicted with Council's
1997-98 & 1998-99 ANNUAL INFRASTRUCTURE PROJECTS — BID RESULTS
August 25, 1998 — Page 2
summer recess. In an effort to keep this project.on schedule, Council granted authority on
July 14, 1998 to the City Manager to sign the contract with the lowest responsible bidder.
This report is an update of the bid results.
The Engineer's Estimate for construction of this project was $4,285,000.00. The low bid
was $4,092,472.70 by Excel Paving Company. The results of the bids are attached as
Exhibit "A."
Excel Paving Company of Long Beach possesses a State Contractor's License and is in good
standing with the State.Contractors' License Board. References and past projects with the
City have indicated satisfactory work performance by this contractor.
The above projects were combined and bid as one project. By doing this, the City expected
to receive lower construction bids and reduce inconvenience to the public. For comparison
purposes, Exhibit `B" includes a summary of unit prices bid on this project versus past
annual projects where the projects were bid and constructed separately: As anticipated,
lower bid prices were received by combining the projects.
ALTERNATIVE ACTIONS
Other action as determined by Council.
FISCAL IMPACT
The total combined budget of these projects is $4,591,522.00. The Engineer's Estimate for
construction was $4,285,000.00 and the low bid is $4,092,472.70. Sufficient funds are
available in the designated accounts.
ATTACHMENTS
Bid Results, Exhibit "A"
Bid Comparison, Exhibit "B"
KB:mrr
s:\tes\wunci1\m0003\award1.doc
,!,
1997-98 & 1998-99 ANNUAL INFRASTRUCTURE PROJECTS
BID RESULTS
Comnanv Location Bid
Excel Paving Company
Granite Construction Company
R.C. Becker & Son, Inc.
KB:mrr
s:\tes\council\m0003\awa dLdoc
Long Beach, CA
Watsonville, CA
Newhall, CA
$ 4,092,472.70
$ 4,130,289.00
$ 4,967,842.49
Item
Cold Mill
Conventional Asphalt
Rubberized Asphalt
Type II Slurry
Chip Seal
Adjust Manhole to Grade
Install Traffic Loop Detectors
Construct Access Ramp
Construct New Sidewalk
Remove & Replace Sidewalk
Remove & Replace Curb & Gutter
Remove & Replace Driveway Apron
Item
Cold Mill
Conventional Asphalt
Rubberized Asphalt
Type II Slurry
Chip Seal
Adjust Manhole to Grade
Install Traffic Loop Detectors
Construct Access Ramp
Construct New Sidewalk
Remove & Replace Sidewalk
Remove & Replace Curb & Gutter
Remove & Replace Driveway Apron
s-.VeMeng-civsm0003Xb1dcampl.xls
1997-98 & 1998.99 Annual
Infrastructure Projects
Quantity
70,450 SY
18,282 TON
17,250 TON
1297 ELT
852,535 SF
180 EA
181 EA
107 EA
40,570 SF
27,514 SF
7629 LF
9017 SF
Bid Price
$1.00
$31.70
$49.80
$100.00
$0.28
$184.00
$290.00
$500.00
$2.50
$2.60
$16.00
$3.10
1997.98 & 1998.99 Annual
Infrastructure Projects
Ouantity
70,450 SY
18,282 TON
17,250 TON
1297 ELT
852,535 SF
180 EA
181 EA
107 EA
40,570 SF
27,514 SF
7629 LF
9017 SF
Bid Price
$1.00
$31.70
$49.80
$100.00
$0.28
$184.00
$290.00
$500.00
$2.60
$2.60
$16.00
$3.10
EXHIBIT B
BID COMPARISON
Annual Overlay
1996-97
Quantity
Bid Price
88,833 SY
$1.44
7885 TON
$35.00
20,875 TON
$45.00
42 EA
$300.00
70 EA
$320.00
56 EA
$1,400.00
1130 SF
$5.00
1735 LF
$30.00
536 SF
$4.00
Annual Sidewalk, C&
1996.97
Quantity id Price
1 EA $700.00
21,962 SF $4.60
684 LF $25.00
2615 SF $4.60
1995-96
QuantitV
Bid Price
24,068 SY
$1.08
8088 TON
$48.00
29 EA
$200.00
46 EA
$250.00
20 EA
$1,200.00
3 & Access Ramps
1995.96
Quantity Bid Price
11 EA $550.00 .
9092 SF $3.50
20 LF $25.00
1487 SF $4.50
Annual Slurry
1996.97 1995-96
Quantity Bid Price Quantity Bid Pric
1829 TON $88.84 1502 TON $78.00
?40,546 SF $0.36 1000,447 SF $0.46
v Sidewalk
1994-95
Quantity id Price
7 EA $700.00
40,810 SF $2.50
z
Annual Ne
1996.97
Quantity
Bid Price
2 EA
$400.00
2 EA
$500.00
1790 SF
$2.50
v Sidewalk
1994-95
Quantity id Price
7 EA $700.00
40,810 SF $2.50
z