HomeMy WebLinkAbout1998-08-25 - AGENDA REPORTS - WILEY CYN ROAD PROJ S2020 (2)CITY OF SANTA CLARITA
AGENDA REPORT
CONSENT CALENDAR
DATE: August 25, 1998
r
Item .. <. .•/
SUBJECT: WILEY CANYON ROAD REALIGNMENT BID AWARD - PROJECT
NO. 52020
DEPARTMENT: Transportation and Engineering Services
RECOMMENDED ACTION
City Council award the contract for the Wiley. Canyon Road Realignment, Project No. 52020,
to Gueno Development in the amount of $1,399,802.55 and authorize a 15 percent contingency
should any change orders to the contract become necessary. Authorize budget transfers in the
amounts shown below to adjust funding sources necessary to complete the project under the
proper program guidelines. Authorize the City Manager or designee to execute and sign all
documents, subject to City Attorney approval.
Appropriate $80,343.00 from 50005201 fund balance to Account No. 52020201-8001 and
$119,823.00 from 50005205 fund balance to account No. 520202058001, for a total increase of
$200,343.00 from the Magic Mountain Parkway/Via Princessa project. Appropriate $250,000.00
from 53013201 fund balance to Account No. 52020201-8001 for a total increase of $250,000.00
from the Scherzinger Lane project. Staff anticipates that the Magic Mountain Parkway/Via
Princessa project will not need as much money in this fiscal year as originally estimated. The
Scherzinger Lane project will still proceed through the design phase through this year, but will
have to be reexamined at mid -year and next fiscal year to determine the best time to fund and
start construction.
BACKGROUND
On July 14, 1998, Council authorized the advertisement of Project No. 52020. This project will
include construction of two travel lanes using the eastern portion of right-of-way, curb, gutter,
and a seven -foot sidewalk on the eastern side of the road, a five-foot paved shoulder lane
adjacent to the curb for bicycle use, an asphalt walk area on the western side from Powell
Street to Wabuska Road, and a concrete retaining wall to relieve the existing slope grade
impacts on the roadway. The counterfort retaining wall is stepped back into the hillside
slightly to allow for irrigation and planting of certain "cells" of the wall. The Planning
Commission chose this more aesthetic design, and street trees were also included along the
alignment to soften the appearance of the finished wall.
ROVED Agenda Item: >`�
WILEY CANYON ROAD REALIGNMENT BID AWARD
August 25, 1998 — Page 2
On Tuesday, August 18, 1998, the following bids were received by the City Clerk's office:
Company
Gueno Development
Granite Construction
Pima dba Advanced Construction
Location Bid Amount
Los Angeles, CA
$1,399,802.55
Watsonville, CA
$1,542,125.00
Santa Monica, CA
$1,654,727.00
The Engineer's Estimate for this project was $1,000,000.00. However, due to a number of
factors, the lowest bidder is nearly $400,000.00 higher than the estimate. Staff believes that
the following circumstances contributed significantly to the higher than expected bid prices:
The nature of the project, specifically, the complexities of the counterfort retaining wall
system;
• The low number of bidders, creating less competition;
The booming construction atmosphere in Southern California, allowing contractors to be
much more selective in their choice of projects.
Staff recommends that the project be awarded to'the lowest bidder, Gueno Development. Gueno
Development possesses a State Contractor's License and is in good standing with the State
Contractors' License Board. The bid of $1,399,802.55 was reviewed for accuracy and
conformance to the contract documents and was found to be complete. This contractor
previously constructed a phase of the Santa Clara River Trail and has just completed the
Railroad Avenue Realignment project to the City's satisfaction. Other references have
indicated that this contractor has performed work that has met their goals.
Staff recommends that the City Council assign additional funds from the Magic Mountain
ParkwayNia Princessa project and from the Scherzinger Lane project as shown in the above
recommendation. The projects will then need additional funds at a later date to make up for the
shortages created by moving money to the Wiley Canyon Road Realignment project.
Based on recent information from State funding source administrators, staff also recommends
that the City Council authorize further funding source transfers between this project and the
Magic Mountain ParkwayNia Princessa project as well. These transfers result in no net
funding change, but will maximize the City's protection against potential loss of funding.
I£ the City Council should decide to award the contract, staff will continue to work to save
money in as many places as possible. Staff will work with the contractor to find areas where
cost savings may be found. Previous experience with this contractor on City jobs leads staff to
believe. that he will cooperate in making changes that will complete the job as economically as
possible.
WILEY CANYON ROAD REALIGNMENT BID AWARD
August 25, 1998 — Page 3
ALTERNATIVE ACTIONS
There are several alternative actions that the City Council may take regarding this matter:
1. Reject all bids and readvertise the project.
Staff can delay the project, return to a design allowing for a vertical wall, and search for
other methods of reducing the cost of the project. This will allow for additional bidding
time and more competition. However, the project will be delayed significantly, which could
result in additional costs due to rising material prices, performing construction during the
rainy season, and potential increases in the price of contractor services due to even higher
demand.
Award the contract to the low bidder and appropriate some or all of the additional funding
needed from the City Council Contingency Fund.
3. Reject all bids and delay the project to a future time in which adequate funds are available.
If an alternative action is chosen, staff recommends that the City Council authorize budget
transfers in the amounts shown below to adjust funding sources necessary to complete the
project under the proper program guidelines. The below transfers effect no net change to the
project budgets.
FISCAL IMPACT
Funding in the amount of $1,532,773.00 has been budgeted, and $1,171,068.00 is currently
available in fiscal year 1998/99 budget for construction of the project as follows:
Account No. Funding Source
S2020201
Gas Tax
S2020204
TDA (Article 8)
52020205
Proposition C
S2020103
STP -L
Total Budeet Available Balance
$ 200,000.00 $ 72,279.00
$ 257,773.00 $ 23,789.00
$ 500,000.00 $ 500,000.00
$ 575.000.00 $ 575.000.00
$1,532,773.00 $1,171,068.00
Staff recommends that funds from the following accounts be transferred in order to satisfy
requirements of expenditure placed on them by the funding sources.
WILEY CANYON ROAD REALIGNMENT BID AWARD
August 25, 1998 — Page 4
Wiley Canyon Road Realignment:
Account No. Funding Source
S2020201
Gas Tax
S2020205
Proposition C
S2020204
TDA (Article 8)
S2020001
General Fund
S2020103
STP -L
Magic Mountain Parkway/Via Princessa:
Account No. Funding Source
50005201
S0005205
S0005204
S0005001
S0005108
ATTACHMENTS
Realignment Plan View
MC:Ikl:mrr
counciMagnwileyAm
Gas Tax
Proposition C
TDA (Article 8)
General Fund
STP -L
98/99 Budget
$ 120,942.00
$ 500,000.00
$ 25,000.00
$ 0.00
$ 575 000.00
$1,220,942.00
Amount
$ 230,520.00
$ 119,823.00
$ 150,000.00
$ 275,000.00
$ 404,312.00
$1,179,655.00
Chan e
$ 150,000.00
$ 0.00
$ 150,000.00
$ 275,000.00
$ (575,000.00)
$0.00
Change
$ (150,000.00)
$ 0.00
$ (150,000.00)
$ (275,000.00)
$ 575.000.00
$0.00
GRAPHC SCALES
0 10 40 60 70
• SCALE M METERS 1:3000 j
100 100 700
SCALE, IN FEET .
,
LEGM
Tn.
RECOMMENDED ALIGNMENT
WILEY CANYON ROAD
RECONSTRUCTION
CITYOF SANTA CLARITA
BDVCE er)GVE6Rina caRPCV2F non