AGENDA REPORT
UNFINISHED BUSINESS
DATE: December 14, 1999
City Manager Approi
Item to be presented
SUBJECT: GOLDEN VALLEY ROAD PHASE I AND HIGH SCHOOL SITE -
PROJECT NO. 53016 - AGREEMENTS BETWEEN 1) THE CITY OF
SANTA CLARITA AND WILLIAM S. HART UNION SCHOOL
DISTRICT; AND 2) THE CITY OF SANTA CLARITA AND THE
SANTA CLARITA VALLEY FACILITIES FOUNDATION
DEPARTMENT: Transportation & Engineering Services
RECOMMENDED ACTION
City Council authorize the City Manager or designee, subject to City Attorney approval, to
approve the agreements between 1) the City of Santa Clarita and William S. Hart Union
School District; and 2) the City of Santa Clarita and the Santa Clarita Valley Facilities
Foundation.
BACKGROUND
The Santa Clarita Valley Facilities Foundation, in conjunction with the William S. Hart
Union School District, is developing approximately 130 acres of land in the Friendly Valley
area of the City. Of this, approximately 48 acres will be used as a high school site. The
remaining 82 acres consists mostly of road right-of-way, slopes, and several potentially
developable parcels (zoned for Business Park, Medium to High Density Residential, and
Neighborhood Commercial.)
The plans for the new school facility increased the urgency to begin construction of
Golden Valley Road to access the school site. To meet the construction schedule dictated by
the needs of the school district, it was necessary for the City to proceed as quickly as
possible with the construction of Golden Valley Road Phase I, which extends from
Sierra Highway to the future extension of Via Princessa. The construction schedule of both
projects is very time -critical in order to obtain state bond funding for the school
development and open the school in September 2001.
To take advantage of the economies of scale and to eliminate potential conflicts if the City
road project and the school site grading were done by separate contractors and
administered separately, staff proposed that the two projects be combined. The combined
project would be administered by the City and paid for jointly by the City and the
Education Foundation.
APPRO
u` Agenda
e,`
GOLDEN VALLEY ROAD/SCHOOL SITE AGREEMENTS
December 14, 1999 — Page 2
On June 22, 1999, City Council approved a Memorandum of Understanding (Exhibit A)
between the William S. Hart Union High School District, the Santa Clarita Valley Facilities
Foundation, and the City, for the City to administer a combined Golden Valley Road
Phase I and Golden Valley High School site grading project. Staff was directed to prepare a
more comprehensive agreement for the administration and cost sharing between the
entities for the joint project.
On August 4, 1999, City Council approved an Interim Funding Agreement between the
William S. Hart Union High School District, the Santa Clarita Valley Facilities Foundation,
and the City, to provide for the funding of preliminary project expenses (through study,
design, and bidding phases) for the joint project, until a Final Funding Agreement was
approved.
Separate Funding Agreements between the City of Santa Clarita and the Santa Clarita
Valley Facilities Foundation, and the City of Santa Clarita and the William S. Hart Union
High School District, have been prepared and are now ready for execution.
The Funding Agreements are scheduled for approval by the Board of Directors of the
Foundation and the School District on December 7, 1999.
The project was advertised for construction bids on November 10, 1999, and the bid opening
is scheduled for December 29, 1999. A construction contract is scheduled to be awarded to
the lowest bidder at the January 11, 2000 Council Meeting. Construction is anticipated to
begin in late January 2000, contingent upon receipt of funds from the Foundation and the
School District.
ALTERNATIVE ACTIONS
Other action as determined by the City Council.
FISCAL IMPACT
At this time, the total joint project construction costs are estimated to be $20 million. This
figure includes a 15 percent contingency. Of the total construction costs, the portion for
Golden Valley Road construction will be funded by the Eastside Bridge and Thoroughfare
District fund, County B&T fees, and a loan from the General Fund Balance to be repaid
with future B&T payments. The construction cost for the Golden Valley High School site
will be funded by the Santa Clarita Valley Facilities Foundation and William S. Hart Union
High School District.
GOLDEN VALLEY ROAD/SCHOOL SITE AGREEMENTS
December 14, 1999 — Page 3
ATTACHMENTS
Funding Agreement - City of Santa Clarita and Santa Clarita Valley Facilities Foundation
City of Santa Clarita and Santa Clarita Valley Facilities Foundation Interim Agreement
City of Santa Clarita and William S. Hart Union High School District Agreement
KB:RGN:twb
m cl\goldm\agrement.doc
NOTICE OF ADJOURNMENT
CITY OF SANTA CLARITA
CITY COUNCIL
NOTICE IS HEREBY GIVEN that the regular meeting of the City Council of
the City of Santa Clarita held December 14, 1999 was adjourned to Tuesday, December 21,
1999 at 12:45 p.m. in the Main Conference Room, 3rd floor of City Hall, 23920 Valencia
Blvd., Santa Clarita, CA, for the purpose of attending a field trip with the Hart School
District regarding the Golden Valley Road/High School site.
Dated this 15d' day of December, 1999.
SHARON L. DAWSON, CITY CLERK
STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES ) ss. AFFIDAVIT OF POSTING
CITY OF SANTA CLARITA )
SHARON L. DAWSON, being fust duly sworn, deposes and says that she is
the duly appointed and qualified City Clerk of the City of Santa Clarita and that on
December 15, 1999, she caused the above Notice to be posted at the door of the Council
Chamber located at 23920 Valencia Blvd., Santa Clarita, CA.