SUBJECT: BOUQUET CANYON BRIDGE WIDENING — AWARD DESIGN
CONTRACT - PROJECT NO. S1035
DEPARTMENT: Transportation & Engineering Services
RECOMMENDED ACTION
City Council award the contract to Dokken Engineering for the engineering design services
for Bouquet Canyon Road Bridge Widening, Project No. S1035, in the amount of
$160,000.00 and authorize a 15 percent contingency expenditure in the amount of
$24,000.00. Appropriate $147,200.00 in Highway Bridge Replacement and Rehabilitation
(HBRR) Grant Funds to Account No. S1035453, and increase the estimated revenues in
Account No. 453-5212 by $147,200.00. Authorize an additional $16,000.00 for staff and
design review services; and authorize the City Manager or designee to execute all
documents, subject to City Attorney approval.
BACKGROUND
In September 1997, the City of Santa Clarita received approval by the HBRR program to
complete the widening of the Bouquet Canyon Road bridge and various other
improvements. The HBRR program has an 80 percent (federal) and 20 percent (City)
reimbursement clause attached to it, and is administered by Caltrans. Caltrans has
assigned grant designation code BHLS5450(007) to this project. Currently, the City has met
all of the grant issues and has received approval to complete the design requirements.
This project will provide the design requirements to widen the Bouquet Canyon Road
bridge over the Santa Clara River from the current layout of six lanes to an ultimate
configuration of eight lanes. Design improvements will include the eight -lane
configuration, stamped concrete median, Class I bike lane with an under -crossing beneath
the north end of the bridge, and decorative tiling associated with the vehicular barrier
railings.
Staff prepared a Request for Proposals (RFP) for the subject project. Included in the RFP is
the requirement to design the necessary improvements for the project. The RFP was sent
to firms on the City's Design Consultants List. Six firms submitted proposals (see
Exhibit "B"). Based on technical qualifications and methodology for the project, staff
recommends the firm of Dokken Engineering, the most qualified bidder.
A'71 ��R'
IR o: A.
BOUQUET CANYON BRIDGE WIDENING
AWARD DESIGN CONTRACT
March 14, 2000 — Page 2
ALTERNATIVE ACTION
Other action as determined by the City Council
FISCAL IMPACT
This project is funded by an HBRR grant in the amount of approximately $5 million. To
date, staff has received authorization from Caltrans to expend up to $350,000.000 in HBRR
funding. This request is to appropriate $147,200.00 in HBRR Grant Funds to Account
No. 51035453 and increase the estimated revenues in Account No. 453-5212 by
$147,200.00. HBRR Grant Funds provide 80 percent of the total funding for this project
and require the City to provide a 20 percent local match. Sufficient local match funding for
this project has been approved and appropriated by the Council for this project.
ATTACHMENTS
Exhibit "A!'— Project Location Map
Exhibit "B" — List of Consultants
RPN:tw
councihhbmdoc
EXHIBIT "A"
VICINITY MAP
BOUQUET CANYON ROAD OVER
THE SANTA CLARA RIVER
PROJECT SITE
EXHIBIT "B"
BOUQUET CANYON ROAD BRIDGE WIDENING
PROJECT NO. 51035
LIST OF CONSULTANTS
Daniel, Mann, Johnson, & Mendenhall
Dokken Engineering
HDR Engineering, Inc.
Tetra Tech
W.Koo & Associates
Willdan Associates
Los Angeles
Rancho Cordova
Orange
Orange
Orange
City of Industry