HomeMy WebLinkAbout2001-07-10 - AGENDA REPORTS - CONGESTION MANAGE REPORT (2)PUBLIC HEARING
DATE:
SUBJECT:
DEPARTMENT:
CITY OF SANTA CLARITA
AGENDA REPORT
City Manager Approval:
Item to be presented by:
July 10, 2001
2001 CONGESTION MANAGEMENT PROGRAM LOCAL
IMPLEMENTATION REPORT
Transportation & Engineering Services
RECOMMENDED ACTION
City Council conduct a public hearing and adopt a resolution finding the City to be in
conformance with the Congestion Management Program; and direct staff to deliver the adopted
resolution and the 2001 Local Implementation Report to the Metropolitan Transportation
Authority on or before the September 1, 2001 deadline.
BACKGROUND
The Congestion Management Program (CMP) is a State -mandated program administered by
the Metropolitan Transportation Authority (MTA) to link land use, transportation, and air
quality decisions, and to address transportation needs on a regional basis. The City is required
to participate in this program in order to receive Proposition 111 Gas Tax funds. Participation
in the CMP in 2001 requires adoption of the proposed compliance resolution and a report to the
MTA on new development activity and new transportation improvements. This report either
credits or debits the bank established in the 1995 CMP reporting process. New development
activity is debited against the bank, and transportation improvements are granted additional
credits.
Last year, the City submitted 51,340 credit points and 21,274 debit points (+30,066 credits
total), yielding a total of 328,458 credits, the fourth highest credit balance in Los Angeles
County. This year, City staff is submitting a report to the MTA claiming 97,028 credit points
and 15,912 debit points (81,116 total additional credits), for a preliminary net balance of
409,574 credits.
The MTA requires that the City Council pass a resolution adopting the Local Implementation
Report through a public hearing process. A public notice was posted in The Signal on
June 25, 2001. City staff will deliver the adopted resolution and the 2001 Local Implementation
Report to MTA staff for consideration on or before the September 1, 2001 deadline.
Adopted: giy Agenda item:,
2001 CMP LOCAL IMPLEMENTATION REPORT
July 10, 2000 — Page 2
ALTERNATIVE ACTION
No alternative action identified by staff.
FISCAL IMPACT
None by this action.
ATTACHMENTS
Resolution Adopting the 2001 CMP Local Implementation Report
2001 CMP Local Implementation Report (available in City Clerk's Reading File)
MLY:twb
council\cmp 1ir01.dm
CITY OF SANTA CLARITA
NOTICE OF PUBLIC HEARING
NOTICE IS HEREBY GIVEN:
A Public Hearing will be held before the City Council of the City of Santa Clarita in the City
Hall Council Chambers, 23920 Valencia Blvd., 1st Floor, on the 10' day of July, at or after 6:00
p.m. regarding the adoption of the 2001 Congestion Management Plan Compliance Resolution
and Local Implementation Report. This resolution and report is an annually -performed action
which commits the City to comply with the state and federally -mandated Los Angeles County
Metropolitan Transportation Authority Congestion Management Program.
Proponents, opponents, and any interested persons may appear and be heard on this matter
at that time. Further information may be obtained by contacting Mark Yamarone,
Transportation Funding Coordinator (661) 255-4942, Santa Clarita City Hall, 23920 Valencia
Blvd., Santa Clarita, CA.
If you wish to challenge this action in court, you may be limited to raising only those issues you
or someone else raised at the public hearing described in this notice, or in written
correspondence delivered to the City Council, at or prior to the public hearing.
Dated: June 20, 2001
Sharon L. Dawson, CMC
City Clerk
Publish Date: June 25, 2001
Phcong.gb
City of Santa Clarita Date Prepared:
19 -Jun -01
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
Contact: Mark L. Yamarone
Phone Number: (661) 255-4931
CONGESTION MANAGEMENT PROGRAM
FOR LOS ANGELES COUNTY
2001 DEFICIENCY PLAN STATUS SUMMARY
1. Total Current Congestion Mitigation Goal
[from Section 1] ..................
(15,912)
Exempted Dwelling Units 0
Exempted Non-residential sq. ft. (in 1,OOOs) 0
2. Transportation Improvements Credit Claims
[from Section II] ..................
97,028
Land Use Strategy Claims 0
Capital Improvement Claims 67,739
Transit Claims 21,197
TDM Claims 8,092
Total Strategies Claimed 97,028
Subtotal Current Credit (Goal) ..................
81,116
3. Carryover Credit from Last Year's (B131997)
Local Implementation Report ..................
328,458
Net Deficiency Plan Credit Balance: ..................
409,574
Section I, Page 1
City of Santa Clarita Date Prepared:
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION I - NEW DEVELOPMENT ACTIVITY REPORT
•A- DEVELOPMENT
RESIDENTIAL DEVELOPMENT ACTIVITY
19 -Jun -01
Category
Dwelling
Units
Debit
Value/DU
Debits
Single Family Residential
x 6.80 -
2,632
Multi -Family Residential
x 4.76 -
2,190
Group Quarters
01
x 1.98 -
0
COMMERCIAL DEVELOPMENT ACTIVITY
Category 1000 Gross
Square Feet
Debit
Value/1000SF
Debits
Commercial less than 300,000 s .ft. 372.35
x 22.23 -
8,277
Commercial 300,000 s .ft. or more 0.00
x 17.80 -
0
Freestanding Eating & Drinking 17.43
x 66.99 -
1,167
NON -RETAIL DEVELOPMENT
ACTIVITY
Category 1000 Gross
Square Feet
Debit
Value/1000SF
Debits
Lodging 0.00
x 7.21 -
0
Industrial 152.52
x 6.08 -
927
Office less than 50,000 s .ft. 0.00
x 16.16 -
0
Office 50,000-299,999 s .ft. 0.00
x 10.50 -
0
Office 300,000 s .ft. or more 0.00
x 7.35 -
0
Medical 0.00
x 16.90 -
0
Government 0.00
x 20.95 -
0
Institutional/Educational 93.57
x 7.68 -
719
University 0.00
x 1.66 -
0
OTHER DEVELOPMENT ACTIVITY
Description Daily Trips
Attach additional sheets if necessary) Enter "0" if none
Debit
Value/rri
Debits
0.00
x 0.71 -
0
0.00
x 0.71 -
0
Subtotal New Development Activit -y
_
15,912
Adjustments (Optional) - Complete Part 2
0 -
0
Total Current Congestion Mitigation Goal Points
(15,912)
Section I, Page 2
City of Santa Clarita Date Prepared: 19 -dun -01
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION Il.b - CAPITAL IMPROVEMENT CREDIT CLAIMS
Total Cap. Imp. Projects: 22 Total Cap. Imp. Credit (Points): 67,739
1
2
2 3 General use lane on Other Major Arterial
212.2 4 Golden Valley Road Phase I
5. Scope 6. Units
4.8 lane -mile
7. Str. Name: Golden Valley Road
6. From/To: Sierra Highway to Via Princessa
9_ Intersection: 10, Map Page: 4551
11. Participants:
12. MTA Funding: 0%
13. Your share of local funding: 1 00%
14. Portion of Project within your jurisdiction: 1 00%
15. Other Info: Graded to "ultimate" six lane width with four lanes paved and striped
initially
16
18.
17 19 20 211 22
23
24
2900
13,920 2001 1 $7,842 100% 3 0
100%
13,9
1
3
2
212.2
3 General use lane on Other Major Arterial
5. Scope
1.0
6. Units
lane -mile
4 Golden Valley Road Phase II
1
232
Section Il.b, Page 1
City of Santa Clarita Date Prepared:
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION Il.b - CAPITAL IMPROVEMENT CREDIT CLAIMS
19 -Jun -01
Total Cap. Imp. Projects: 22 Total Cag. Im . Credit (Points):
1 2 3 General use lane on Other Major Arterial 5. Scope
4 212.2 4 Golden Valley Road Phase III 1.0
67,739
6. Unfts
lane -mile
7. Str. Name:
Golden Valley Road
8. From/To:
Redview to Soledad Cyn Rd.
9. Intersection:
1 10. Map Page:
4551
11. Participants:
12. MTA Funding:
13. Your share of local funding:
14. Portion of Project within your jurisdiction:
100%
t00%
15. other Info:
Adding 1 left turn & 1 right turn (n/s bounds).
16
17 18 19 20 21 22
23
24
2900
2,900 2002 $429 40% 1 0
232
N
1
5
2
244.2
3 Intersection Modification, Other Major Arterial
j20%
S. Scope
1.0
6. Units
intersection
4 Soledad Canyon Road at Golden Oak
7. Str. Name:
Soledad Canyon Road
8. From/To:
9. Intersection:
Soledad Canyon Road at Golden Oak 1 'OMap Page:
4551
11. Participants:
12. MTA Funding:
13. Your share of local funding: l00%
14. Portion of Project within your jurisdiction: 1 00%
15. Other Info:
Adding 1left turn and 1 right turn (n/s bounds).
16
17 18 19 20 21 22
23
24
144
144 2002 $270 40% 1 0
20%
12
1
6
2
244.2
3 Intersection Modification, Other Major Arterial
S. Scope
1.0
6. Units
intersection
4 Soledad Canyon & Rainbow Glen
7. Str. Name:
8. From To:
9. Intersection:
Soledad Canyon & Rainbow Glen 1 10. Map Page:
4551
11. Participants:
12. MTA Funding:
0% 1 13. Your share of local funding:
14. Portion of Project within our jurisdiction:
100%
100%
15. Other Info:
Installed one lane for each direction.
16
17 18 1 19 1 20 1 21 1 22 1 23
24
144
144 2002 1 $331 1 40% 1 1 1 0 1 20% 1
12
Section II.b, Page 2
112. MTA Funding: 1 - _ 13. Your share of local fundina: 1000
144 144 2002 $270 1 40% 1 0 20% 12
1 2 3 General use lane on Other Major Arterial 5. Scope 6. Units
s 1212.21 4 Haskell Canyon Road Bridge Widening 4.8 lane -mile
11. Participants:
12. MTA Funding: 0% 13. Your share of local funding: 100%
14. Portion of Project within your jurisdiction: 1 00%
9,744
1 2 3 Multi -modal trans. centers. Click on "MMTC Claims" tab for 5. Scope 6. Units
9 223.0 4 McBean Transfer Station 1,885.0 Varies
12. MTA Funding: 30% 13. Your share of local funding: 100%
14. Portion of Project within vour'urisdlotion: 100%
15. other Info: 1,414 Local Boardings per day & 471 Express Boardings per day.
16 17 118 19 20 21 221 23 24
_ILNTEFq#VALUE!l 2001 1 $2,274 1 100% 2 0 1 70% 293
Section Il.b, Page 3
(City of Santa Clarita Date Prepared: 19 -Jun -01
2001 CMP Local Implementation Report
I to 1 212.21 4
[f7
"lane-mile
(12. MTA Funding: 0% 13. Your share of local funding: 100%
14. Portion of Project within your jurisdiction: 100%
115. Other Info:
11. Participants:
12. MTA Funding: 0% 13. Your share of local funding: 100%
14. Portion of Project within your jurisdiction: 100%
15. Other Info: Widen the Bouquet Canyon Rd. bridge from six to eioht lanes.
LUUU
120,300 1 2005 1 $500 100% 11 0
1 20%
1 4,060
1
11
2
212.2
3 General use lane on Other Major Arterial
1
12
2
212.2
5. Scope
1.0
6. Units
lane -mile
4 Golden Valley Road over the Santa Clara River
11. Participants:
12. MTA Funding: 0% 13. Your share of local funding: 100%
14. Portion of Project within your jurisdiction: 100%
15. Other Info: Widen the Bouquet Canyon Rd. bridge from six to eioht lanes.
17 16 1 19 1 20 1 21 1 2223
13,920 2002 $299 100% 1 0 20°
Section Il.b, Page 4
Zbpuu
Z,e00 ZUUb $5UU 100% 1
0
20%
580
1
12
2
212.2
3 General use lane on Other Major Arterial
5. Scope
4.8
6. Units
lane -mile
4 Via Princessa Cla bourne to Magic Mtn.
7. Str. Name:
Via Princessa
8.
From/To:
San Fernando Road to Magic Mountain Pkwy.
9.
Intersection:
10. Map Page:
4550
11.
Participants:
12.
MTA Funding:
0%
1 13. Your share of local funding:
100%
17 16 1 19 1 20 1 21 1 2223
13,920 2002 $299 100% 1 0 20°
Section Il.b, Page 4
(City of Santa Clarita Date Prepared: 19 -Jun -01
1 13 1 215.2
1: 67,739
EMEEM
Scope 6. Units
1 1 lane -mile
12. MTA Funding:0%
13. Your share of local funding: 100%
14. Portion of Project within your jurisdiction: 100%
15. Other Info: Aesthetic im rovements: Installation of side panels, medians and landscaping.
16 17 18 19 20 21 22 1 23 24
145 145 2003 1 $300 100% 1 0 1 20% 29
1 2 3 Intersection Modification, Other Major Arterial 5. Scope 6. Units
14 244.2 4 1999-2000 New Traffic Signal 1.0 intersection
11. Participants:
12. MTA Funding: 0% 1 13. Your share of local funding: too-/.
14. Portion of Project within your jurisdiction: l00%
15. Other Info: iof 2
144 144 2001 $239 100% 3 101 100% 43
1 2 1 3 Intersection Modification, Other Major Arterial 5. Scope 6. Units
15 244.21 4 1999-2000 New Traffic Signal 1.0 intersection
7. Str. Name: Plum Canyon
8. From/To:
9. Intersection: Plum Canyon & Rodgers Dr. 10. Map Page: 4461
11. Particioants:
115. Other
17
144
100%
100%
20 1 21 1 22 1 23 1 24
00% 1 3 101 1 100% 431
Section Il.b, Page 5
near
112. MTA Funding: 0% L _ 13. Your share of local funding: 1o0%
14. Portion of Project within your jurisdiction: 100% i
15. Other Info:
575 2001
3 Intersection
1 17 1 244.2
11. Part
12. MT/
Arterial
Flk1
1.0 1 intersection
100%
16 17 18 19 20 _ 21 1 22 1 23 24
144 144 1 2002 1 $150 100% 3 0 100% 144
1 23 Intersection Mod'Aication, Other Major Arterial 5. Scope 6. Units
1e 244.2 4 Soledad Canyon Road & Oak S ring Canyon Rd. 1.0 intersection
115. Other
17
144
100%
23 24
100% 144
Section II.b, Page 6
City of Santa Clarita
Date Prepared:
19 -Jun -01
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION Il.b - CAPITAL IMPROVEMENT CREDIT CLAIMS
Total Cap. Imp. Pro ects: 22 Total Cae. Im . Credit
(Points):
67,739
1
2 3 Intersection Modification, Other Major Arterial
5. Scope
6. Units
19
244.2
4 Soledad Canyon Road & Poppy Meadow St.
1.0
intersection
7. Sir. Name: Soledad Canyon Road
8. From/To:
9. Intersection: Soledad Canvon Road & Ponnv Meadow St I
in Man Pnnn•
drr9
100%
115. Otho
144 144 2001 $500 100% 3 0 100% 744
1 2 3 Intersection Modification, Other Major Arterial 5. Scope 6. Units
20 244.2 4 Soledad Canyon & Flower Park 1.0 intersection
7. Str. Name: Soledad Canvon Road
100%
16 17 181 1920 21 1 22 23 - 24
144 1 144 1 2001 $500 100% 3 0 100% 144
1 2 3 Arterial Center Medians, Other Major Arterial 5. Scope 6. Units
21 215.2 4 San Fernando Road New Median 1.0 lane -mile
112. MTA Funding: 0% I 13. Your share of local fundina: 100%
rw meaian, norm or the new via Princessa extension at Wiley Canyon Rd.
17 18 19 1 20 1 21 1 2223 24
145 2002 $145 100% 1 0 20% 29
Section Il.b, Page 7
City of Santa Clarita Date Prepared: 1s -jun -o1
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION Il.b - CAPITAL IMPROVEMENT CREDIT CLAIMS
Total Cap. Imp. Projects: 22 Total Can. Imo. Cradit (Pninta
1 12 I 3
2 215.2 4
67,739
6. Units
lane -mile
11. Participants:
12. MTA Funding:
0%
13. Your share of local funding:
l00%
14. Portion of Project within your jurisdiction:
10o%
15. Other Info:
417
18 19 20
21 22
23
24
1
23
2
244.1
145
3
2002 $354 100%
Intersection Modification, CMP Arterial
3 102
100%
5. Scope
1.0
43
6. Units
intersection
4 New Traffic Signal 00-01
7. Str. Name:
Sierra Highway
8. From/To:
s. Intersection:
Sierra Highway & American Beauty
10. Ma Pa e:
4551
11. Participants:
12. MTA Funding:
0%
_
13. Your share of local funding:
1 00%
575 1 575 1 2001 $320 100% 2 0 70% 403
1 2 3 Intersection Modification, Other Major Arterial 5. Scope 6. Units
24 244.2 4 New Traffic Signal 00-01 1.0 intersection
7. Str. Name: Bouquet Canvon Road
12. MT
144
100%
101
Section Il.b, Page 8
Section Il.b, Page 9
City of Santa Clarita Date Prepared:
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION Il.b - CAPITAL IMPROVEMENT CREDIT CLAIMS
19 -Jun -01
Total Cap. Imp. Pro'ects: 22 Total Cag. Im . Credit (Points):
1 2 3 General use lane on Other Major Arterial 5. Scope
28 212.2 4 Ave Scott Road Widening 2.5
67,739
6. Untts
lane -mile
7. Str. Name:
Ave Scoff
a. From/To:
McBean Parkway to Tibbitts
9. Intersection:
110. Map Page:
4550
11. Participants:
12. MTA Funding:
13. Your share of local funding:
1 00%
14. Portion of Project within your jurisdiction:
l00%
15. Other Info:
Installed 4 lanes along Ave Scott.
18 19 20 21 22
23
24
0 2001 "''"'"" `" 100% 3 0
100%
7,250
MM
1
29
+212.2
3 General use lane on Other Major Arterial
4 McBean Parkway Road Widening
5. Scope
3.5
6. Units
lane -mile
7. Str. Name:
McBean Parkwa
8. From/To:
Magic Mountain to Decoro Dr.
9. Intersection:
10. Map Page:
4460/4550
11. Participants:
12. MTA Funding:
13. Your share of local funding:
1 00%
14. Portion of Project within your jurisdiction:
t00%
15. Other Info:
Added 2 lanes on McBean Par ay (4 to 6 lanes).
16
17 18 19 20 21 22
23
24
2900
2
1244.2
10,150 2001 100% 3 0
3 Intersection Modification, Other Major Arterial
4 Wiley Canyon New Traffic Signal
100%
10,150
1
30
5. Scope
1.0
6. Untts
intersection
7. Str. Name:
Wiley Canyon
8. From/To:
9. Intersection:
Wiley Canyon & Tournament 10. Map Page:
4550/4640
11. Participants:
12. MTA Funding:
1
13. Your share of local funding:
1 00%
14. Portion of Project within your jurisdiction:
t00%
115. Other Info:
16
17 18 19 20 21 22 23
24
144
144 2001 $75 1 100% 3 1 0 1 100% 1
144
Section Il.b, Page 10
(City of Santa Clarita Date Prepared: 19 -Jun -01
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION Il.b - CAPITAL IMPROVEMENT CREDIT CLAIMS
1
12. MTA Funding: 1 -- 13. Your share of local funding: 1 00%
14. Portion of Project within your iurisdiction: l00% 1
15. Other Info:
144 144 2001 $75 1000% 3 0 100% 144
1 2 3 Intersection Modification, Other Major Arterial 5. Scope 6. Units
32 244.2 4 McBean ParkwayNew Traffic Si nal 1.0 intersection
7. Str. Name: McBean Parkwav
12. MTAFunding: 13. Your share of local funding: 1 00%
14. Portion of Project within your jurisdiction: 1 000/
15. Other Info.
1
33
144
2
244.2
144 2001 $90 100% 2 0
3 Intersection Modification, Other Major Arterial
70%
101
5. Scope
1.0
6. Unfts
intersection
4 Whites Canyon New Traffic Signal
7. Str. Name:
Whites Canyon
8. From/To:
'.9. Intersection:
Whites Canyon & Stillmore 10. Map Page:
4551
11. Participants:
12. MTA Funding:
13. Your share of local funding:
1 00%
14. Portion of Project within your jurisdiction:
1 00%
15. Other Info:
Enter
16 1
17 1 18 1 19 1 20 1 21 22 23
24
144 1
144 1 2001 1 5k 100% 1 3 0 1000/6
144
Section II.b, Page 11
City of Santa Clarita Date Prepared:
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION Il.b - CAPITAL IMPROVEMENT CREDIT CLAIMS
19 -Jun -01
Total Cap. Imp. Pro Iects: 22 Total CaR. Im . Credit (Points):
1 1 2 1 3 Intersection Modification, CMP Arterial 5. Scope
34 1244.1 1 4 Seco CanyWCo per Hill New Traffic Signal 1.0
67,739
6. Units
intersection
7. Str. Name:
8. From/To:
9. Intersection:
Seco Canyon & Copper Hill 10. Map Page:
4460
11. Participants:
12. MTA Funding:
13. Your share of local funding:
l00%
14. Portion of Project within your jurisdiction:
100%
15. Other Info:
Enter
16
17 18 19 20 21 22 23
24
1
36
575
MM
2
244.1
575 2001 1 $250 100% 3 0 100%
3 Intersection Modification, CMP Arterial 5. Scope
4 Lyons Ave & Wiley Canyon Intersection Modification 1.0
575
6. Units
intersection
7. Str. Name:
I-onsAve
8. From/To:
9. Intersection:
Lyons Ave & Wiley Canyon 10. Ma Page:
4640
11. Participants:
12. MTA Funding:
13. Your share of local funding: 1 00%
14. Portion of Project within your jurisdiction: 100°
15. Other Info:
Added two protected left turns.
16
1 17 18 19 20 21 22
23
24
1
36
575
2
244.1 1
575 2001 $90 1o0% 3 0
3 Intersection Modification, CMP Arterial
100%
575
5. Scope
1.0
6. Units
intersection
4 Lyons Ave & Orchard Vill. Intersection Modification
7. Str. Name:
B. From/To:
9. Intersection:
Lyons Ave & Orchard Village 10. Ma Page:
4640
11. Participants:
12. MTA Funding:
1 13. Your share of local funding:
14. Portion of Project within your jurisdiction:
loo
100%
15. Other Info:
Added leftturn on Lyons Ave,
16
17 18 19 20 21 22 23
24
575
575 2001 9: 100%1. 0
Section Il.b, Page 12
City of Santa Clarita Date Prepared:
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION Il.b - CAPITAL IMPROVEMENT CREDIT CLAIMS
19 -Jun -01
Total Cap. Imp. Projects: 22 Total Cag. Im . Credit (Points):
1 2 3 Intersection Modification, CMP Arterial 5. Scope
37 244.1 1 4 McBean Pkwy. & Valencia Blvd. 1.0
67,739
6. Units
intersection
7. Str. Name:
8. From/To:
s. Intersection:
McBean Parkway & Valencia Blvd. 10. Map Page:
4550
11. Participants:
12. MTA Funding:
13. Your share of local funding:
100%<
14. Portion of Project within your jurisdiction:
100%
15. Other Info:
Change stripping to dual right turn on McBean Pkwy-
kw .16
16
17 18 19 1 20 1 21 1 22
23
24
575
575 2001 i'•,<;1 100% 3 0
100%
575
1
38
2
244.1
3 Intersection Modification, CMP Arterial
5. Scope
...........................
j<'ajjs?"t
6. Units
intersection
4 Soledad & Bouquet Intersection Modification
7. Str. Name:
Soledad Canyon
8. From/To:
s. Intersection:
Soledad Cyn. & Bouquet Cyn. 1 10. Map Page:
4550
11. Participants:
12. MTA Funding:
13. Your share of local funding:
100%
14. Portion of Project within your jurisdiction:
100%
15. other Info:
Changed stripping
to dual right turns, west bound on Bouquet Can on.
16
17 18 1 19 20 1 21 1 22
23
24
575
575 2001 $150 100% 3 1 0
100%
575
1
3s
2
244.1
3 Intersection Modification, CMP Arterial
5. Scope
1.0
6. Units
intersection
a McBean Pkwy. &Rockwell Intersection Mod'rfication
7. Str. Name:
McBean Parkway
8. From/To:
9. Intersection:
McBean Parkway & Rockwell Canyon 10. Map Page: 4550
11. Participants:
12. MTA Funding:
13. Your share of local funding:
1 00%
14. Portion of Project within your jurisdiction:
100%
15. other Info:
Left turns in all directions.
16 1
17 18 1 19 1 20 1 21 1 22 1 23
24
575 1
575 2001 1 $75 1 100% 1 2 1 0 1 70% 1
403
Section II.b, Page 13
City of Santa Clarita Date Prepared:
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION Il.b - CAPITAL IMPROVEMENT CREDIT CLAIMS
19 -Jun -01
Total Cap. Imp. Pro'ects: 22 Total Cag. Imp. Credit lftintsL
1 2 1 3 General use lane on Other Major Arterial 5. Scope
40 212.2 1 4 Wiley Canyon Road Widening 2.0
67,739
6. Units
lane -mile
7. Sir. Name:
Wiley Canyon
8. From/To:
Via Pacifica to Oak RA; Dr.
9. Intersection:
10. Map Page:
4550
11. Participants:
12. MTA Funding:
13. Your share of local funding:
100%
14. Portion of Project within your jurisdiction:
1 00%
15. Other Info:
Road widen ng, 0-4) lanes.
16
17 18 1 19 20 1 21 22
23
24
2900
5,800 2001 100% 3 0
100%
5,800
1
41
2
244.2
3 Intersection Modification, Other Major Arterial
4 Via Princessa & Oak Ridge New Traffic Signal
MM
5. Scope
1.0
6. Units
intersection
7. Sir. Name:
8. From/To:
9. Intersection:
Via Princessa & Oak Ridge Dr. 10. Map Page:
4550
11. Participants:
12. MTA Funding:
13. Your share of local funding: 1 00%
14. Portion of Project within your jurisdiction: 100%
15. Other Info:
16
17 1 18 19 20 21 22
23
24
144
144 2001 $90 40% 3 0
100%
58
1
42
2
244.2
3 Intersection Modification, Other Major Arterial
5. Scope
1.0
6. Units
intersection
4 Wiley New Traffic Signal
7. Sir. Name:
8. From/To:
9. Intersection:
Wiley Canyon & Via Pacifica 10. Map Page:
4550
11. Participants:
12. MTA Funding:
13. Your share of local funding:
100%
14. Portion of Project within your jurisdiction:
100%
15. Other Info:
16
17 18 19 20 21 22 23
24
144
144 2001 $75 100% 3 0 100%
144
Section Il.b, Page 14
City of Santa Clarita Date Prepared:
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION Il.b - CAPITAL IMPROVEMENT CREDIT CLAIMS
19-dun-01
Total Cap. Imp. Projects: 22 Total Cag. 1mg. Credit (Points):
1 2 3 Intersection Modification, CMP Arterial 5. Scope
43 244.1 _4_Wiley Cyn. & Orchard Vill. Intersection Modification 1.0
67,739
6. Units
intersection
7. Sir. Name:
8. From/To:
9. Intersection:
Wiley Canyon & Orchard Village 1 10. Map Page:
4550
11. Participants:
12. MTA Funding:
13. Your share of local funding:
l00%
14. Portion of Project within your jurisdiction:
100%
15. Other Info:
Enter
16
17 18 1 19 1 20 1 21 22
1 23
24
575
575 1 2001 1 $50 100% 3 1 0
1 100%
575
1
44
2
244.1
3 Intersection Modification, CMP Arterial
4 San Fernando & Oakridge Intersection Modification
5. Scope
1.0
6. Units
intersection
7. Str. Name:
8. From/To:
9. Intersection:
San Fernando Rd. & Oakridge Dr. 10. Map Page:
4550
11. Participants:
12. MTA Funding:
13. Your share of local funding:
100%
14. Portion of Project within your jurisdiction:
1 00%
15. Other Info:
Protected all traffic lights (all directions).
16
17 18 19 20 1 21 1 22
23
1 24
575
575 2001 $50 100% 3 0
100%
575
1
45
2
212.2
3 General use lane on Other Major Arterial
5. Scope
1.0
6. Units
lane-mile
4 Oak Ridge Dr. Road Widening
7. Str. Name:
Oak Ridge Dr.
8. From/To:
Between San Fernando & Via Princessa
9. Intersection:
10. Map Page:
4550
11. Participants:
12. MTA Funding:
0 1
13. Your share of local funding:
1 00%
14. Portion of Project within your jurisdiction:
l00%
15. Other Info:
Road widening from 2 lanes to 5 lanes.
16
17 18 19 20 21 22 23
24
2900
2,900 2001 100% 1 3 1 0 1 100% 1
2,900
Section Il.b, Page 15
City of Santa Clarita Date Prepared:
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION Il.b - CAPITAL IMPROVEMENT CREDIT CLAIMS
19.1un-01
Total Cap. Imp. Projects: 22 Total Cag. im . CreditPoints :
1 2 3 Intersection Modification, CMP Arterial 5. scope
46 244.1 4 Valencia & Rockwell Cyn. Intersection Modification 1.0
67,739
6. Units
intersection
7. Sir. Name:
8. From/To:
9. Intersection: Valencia Blvd. & Rockwell Cyn. 10. Map Page:
4550
11. Participants:
12. MTA Funding:
13. Your share of local funding:
1 00%
14. Portion of Project within your jurisdiction:
100%
15. Other Info: Add protected left tum on west bound.
16
17 18 19 20 21 1 22
575
575 2001 $50 100% <>„>+''` 0
1
a7
2
2!j
fii
3 Other Major Bikeway
4 Copper Hill Dr. Bike Lane
7. Str. Name: Copper Hill Dr.
8. Fromlro: Seco Canyon to Haskell Canyon
9. Intersection: 10. Map Page: 4460 &4461
11. Participants: L.A . County Dept. of Public Works
12. MTA Funding:
13. Your share of local funding:
1 00%
14. Portion of Project within your jurisdiction:
25%
15. Other Info: Enter
16 1 17 18 19 20 1 21 22 23
24
560 1 1,400 . 2001 85% 3 0I 100% 1
1,190
Section II.b, Page 16
=actor (avg. miles per i
Avg. Daily
11. First Year of Servio
12. Prior credits for rldi
13. Milestone Reached:
14. Milestone Percent F
15. Annual Operating C
16. Percent Funded Lo(
17. If commuter rail fee
18. If urban rail feeder i
19. Prior credits for rail
2
1 361.
11. First Year of
12. Prior credits
13. Milestone Re
14. Milestone Pr
15. Annual Oper
16. Percent Fun;
17. If commuter
18. If urban rail 1
3 New Local or
0 2,150
7.7 3.3
0 7,095
1996
3,700
2
1001A
s): 420
on
7. Ext)reselfl. Local
lershi : 0
2,418
r rider): 32.8
4.4
y PMT: 0
1 c
ce:
0
dership:
0
d:
2
Factor:
100%
Cost:
$ 4,70f
ocal ly:
75%
ederservice:
0
service:
0
Total
0
1998 Credit
ervice (btwn. FY 00 & 1 7,979
>huttle 10. DialaRlde Total
0 0
1.0 8.0
0 0 10,63
6. Unit
PMT
Section Il.d, Page 1
City of Santa Clarita
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION Il.d - TRANSIT CREDIT CLAIMS
Date Prepared:
19-.Jun-01
Total Transit Pro'ects: 3 Total Transit Credit (Points):
21,127
1
1
19. Prior credits for rail boardings: 0
7,979
20. Net 2001 Credit
2 3 New Local or Commuter Bus Service
361.00 4 Increase in Avg. Wkdy. Ridership on Commuter Service (btwn. FY
Value:
5. Scope:
13,111
6. Units:
PMT
7. Ex res 8. Local
19. Shuttle 10. DlalaRlde Total
0 0
1.0 8.0
0 01 16,597
inter a zercx { U )%C
dll bill@ tS7C1t 611tC138
if thB Quggtlp(f 3S E3At
applicable lathe
is 11t1iGrl0Yyn
20. Net 2001 Credit Value:
Credits
13,111
Current Avg Weekday Ridership: 506 1 0
Credit Factor (avg. miles per rider): 32.8 1 4.4
Avg. Daily PMT: 16,597 0
11. First Year of Service: 0
12. Prior credits for ridership: 0
13. Milestone Reached: 2
14. Milestone Percent Factor: 100°/,
15. Annual Operating Cost: $ 1,812,290
16. Percent Funded Locally: 79%
17. If commuter rail feeder service: psyve
18. If urban rail feeder service: 0
19. Prior credits for rail boardings: 0
Section Il.d, Page 2
City of Santa Clarita Date Prepared: 19 -Jun -01
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION Il.d - TRANSIT CREDIT CLAIMS
Total Transit Projects: 3 Total Transit Credit (Points): 21,127
1I 2 3 New Local or
1 361.00 4 Increase in A,
nt mvg vveeKcjay mice rsni 0 0
actor (avg. miles per rider): 32.8 4.,
Avg. Daily PMT:f o
1. First Year of Service: 0
2. Prior credits for ridership: 0
3. Milestone Reached: 9
1
commuter rail feeder service: 0
urban rail feeder service: 0
Ior credits for rail boardings: 0
on
■illlllllll�o
oiiiiilllllllllll��
20.
scope: 6. Unit
36 1 PMT
Total
Section 11A, Page 3
City of Santa Clarita Date Prepared:
2001 CMP Local Implementation Report
Report Period: JUNE 1, 2000 - MAY 31, 2001
SECTION 11.e - TDM CREDIT CLAIMS
19 -Jun -01
Total TDM Projects: z ITotal TDMCredit Points):
8,095
1 321.0 CMP TDM Ordinance 635.871000 =gsf
Non -Residential building permits issued, as reported In Section I
No other description/entries required for this strategy. This is already done for you.
1
2
16
0.30
2
354.00
17 18 19 20 21 22
191 n/a n/a 100% 3 n/a
3 Remote Access to Gov't Info/Transactions
23
100%
24
191
5. Scope:
5,646
6. Units:
daily log -in
4 City of Santa Clarita Web She/City Services On -Line
Enterzero
fI'01B uestiondoes,nota ..
7. Total employees In program: 0
8. Total employers: 0
9. Operator of Transit Service: 0
10. Percent of Total Fare Subsidized: 0%
11. Net Gain avg monthly participants: 0
12. Facility/Center Address: 23920 Valencia Blvd. (City Hall)
13. Dally Parking Rate: $0.00
14. Fee Increase: $0.00
15. Other Info:
16
1.40
17
7,904
18
1999
19
$51,500
20
100%
21
3
22
0
23
100%
24
7,904
Section Il.e, Page 1