HomeMy WebLinkAbout2001-05-08 - AGENDA REPORTS - SIDEWALK REPAIRS PROJECT (2)CITY OF SANTA CLARITA
AGENDA REPORT
CONSENT CALENDAR City Manager Approval:
Ro
Item to be presented by: bert G. Newman
DATE: May 8, 2001
SUBJECT: FISCAL YEARS 1999-2000 AND 2000-2001 NEW SIDEWALK AND
SIDEWALK REPAIR PROJECTS, BOUQUET CANYON ROAD/
ESPUELLA DRIVE RIGHT -TURN POCKET, AND 2000-2001 ACCESS
RAMP PROGRAM, PROJECT NOS. T0005, M0001, T0013, M0018,
C4003, AND T0008 — PROJECT ACCEPTANCE
DEPARTMENT: Transportation & Engineering Services
RECOMMENDED ACTION
City Council accept the work performed by Kalban, Inc. on the 1999-2000 and 2000-2001 New
Sidewalk and Sidewalk Repair Projects, Bouquet Canyon Road/Espuella Drive Right -Turn
Pocket, and 2000-2001 Access Ramp Program; direct the City Clerk to file the attached
Notice of Completion; and direct staff to release the 10 percent retention 35 days after the
Notice of Completion is recorded, provided no stop notices, as provided by law, have been filed.
BACKGROUND
On October 10, 2000, the City Council awarded a contract for the 1999-2000 and 2000-2001
New Sidewalk and Sidewalk Repair Projects, Bouquet Canyon Road/Espuella Drive Right -Turn
Pocket, and 2000-2001 Access Ramp Program to Kalban, Inc. This project involved the concrete
rehabilitation program at various locations in the City and right -turn pocket widening on
Bouquet Canyon Road/Espuella Drive.
This project was completed to the satisfaction of the City Engineer on April 6, 2001. The project
was completed under budget and on time. The total cost for construction was $412,752.00,
which came under the allocated budget amount of $420,164.00.
ALTERNATIVE ACTION
Other action as determined by the City Council.
Agenda Item :_1tL
APPROVED
NEW SIDEWALK AND SIDEWALK REPAIR PROJECTS, BOUQUET CANYON/ESPUELLA
RIGHT -TURN POCKET, AND ACCESS RAMP PROGRAM
May 8, 2001— Page 2
FISCAL IMPACT
The total cost for the project is $412,752.00. The total budget of $420,164.00 from the
General Fund, Proposition C, Gas Tax was allocated in the budget for Fiscal Years 1999-2000
and 2000-2001.
ATTACHMENT
Notice of Completion
JKT:lkl
W=61\MO8Ac Pt.050801.doc
RECORDING REQUESTED BY:
City of Santa Clarita
Transportation and Engineering Services Department
WHEN RECORDED, MAIL TO:
Sharon L. Dawson, CMC, City Clerk
City of Santa Clarita
23920 Valencia Boulevard, Suite 304
Santa Clarita, CA 91355-2196
RECORDING FEES EXEMPTED
G.C. • 6103 and 27383
Space Above This Line For Recorder's Use
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN:
1. The City of Santa Clarita, a municipal corporation, is the owner in fee, except for the
right-of-way upon which it has been constructed, of a certain public improvement known as
1999-2000 and 2000-2001 New Sidewalk and Sidewalk Repair Projects, Bouquet Canyon
Road/Espuella Drive Right -Turn Pocket and 2000-2001 Access Ramp Program 1999-2000,
Project Nos. T0005, M0001, T0013, M0018, C4003, and T0008.
2. The City's address is 23920 Valencia Boulevard, Suite 300, Santa Clarita,
California 91355-2196.
3. The general location of said public improvement is at various locations within City jurisdiction.
4. On October 10, 2000, a contract to construct said public improvement was awarded to
Kalban, Inc., 10950 Tuxford Street, Sun Valley, California 91352.
5. Work under said contract was completed on April 6, 2001, to the satisfaction of the
City Engineer, and was accepted by the City on May 8, 2001.
STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES ) as.
CITY OF SANTA CLARITA )
I have read the foregoing Notice of Completion and know its contents. I am the City Clerk of the
City of Santa Clarita and am authorized to make this verification for and on its behalf, and I make
this verification for that reason. I am informed and believe and on that ground allege that the
matters stated in the foregoing document are true. I declare under penalty of perjury under the
laws of the State of California that the foregoing is true and correct.
Sharon L. Dawson, CMC, City Clerk
City of Santa Clarita
JKT:lkl
I cil\t000BMcepW6M1.dm
Date