HomeMy WebLinkAbout2006-08-22 - AGENDA REPORTS - DESIGN CONTR AWARD NEWHALL (2)Agenda Item:
CITY OF SANTA CLARITA
REDEVELOPMENT AGENCY
AGENDA REPORT
City Manager Approval:
CONSENT CALENDAR Item to be presented by: Christopher Price
DATE: August 22, 2006
SUBJECT: AWARD OF DESIGN CONTRACT FOR DOWNTOWN
NEWHALL RESTRIPE PROJECT
DEPARTMENT: Community Development
RECOMMENDED ACTION
Redevelopment Agency award the design contract change order to Advantec Consulting
Engineers, Inc. for the preparation of Plans, Specifications, and Estimate (PS & E) for the
Downtown Newhall Restripe Project; Transfer funds from Account No. 3610-8001 to
Downtown Restripe Project Number S2016901-8001, in the amount of $50,000 and authorize a
10 percent contingency expenditure in the amount of $10,000 (no contingency was added to the
original contract of $49,500) for a total of $109,500 and authorize the City Manager or designee
to execute all documents, subject to City Attorney approval.
BACKGROUND
The City of Santa Clarita Redevelopment Agency's (RDA) approval and adoption of the
Downtown Newhall Specific Plan (Plan) became effective on December 22, 2005. The Plan
creates the framework and development code necessary to revitalize what was once the "Old
Town" of Newhall into a thriving pedestrian oriented shopping, dining, and entertainment
district. One of the first physical changes to be made under the Plan is aimed at creating a
calmer, pedestrian friendly environment along the stretch of San Fernando Road that will plant
the seed that will eventually grow into the City's new "Main Street." This will be accomplished
by removing a traffic lane from San Fernando Road in the downtown area and replacing it with
angled parking . In order to remove that lane provisions must be made to accomodate the
existing commuter traffic through the area.
While the Architects of the Plan (Moule & Polyzoides) continue to work with City staff and
APPROVED
sub -consultants on the design of the permanent Streetscape improvements, Advantec Consulting
Engineers has already begun the preliminary analysis and design of improvements to Railroad
Avenue. The award of this change order will provide for the complete design of all remaining
aspects of the restripe project, enabling staff to shift the majority of "commuter" traffic from San
Fernando Road onto Railroad Avenue through the downtown area. The work under way,
together with this change order will allow these specialized traffic engineers to prepare plans
that will remove a lane of traffic from San Fernando Road and replace it with striped angled
parking for the benefit of patrons and businesses. Modifications to signals, median islands, and
some curb and gutter will be necessary to accomplish this, and parking along the East side of
Railroad Avenue will likely need to be eliminated once these plan are executed. All of these
changes and impacts were identified and discussed during the public participation process that
created the Plan, however additional public meetings will be held as the process moves forward.
The design of this complex Public Works project will take approximately four months from the
award of this contract. Staff anticipates that an agenda item to award the construction contract
would be brought before the agency board during one of the first meetings of 2007. Construction
is anticipated to take three to five months after the award of that contract.
On Friday July 7, 2006, City staff received proposals from the following consultants:
Katz, Okistu & Associates Tustin, CA
Advantec Consulting Engineers Diamond Bar, CA
Staff interviewed both responding consultants during the weeks of the 10th and the 17th and
recommended that the City Manager award a contract to Advantec Consulting Engineers Inc. for
the initial stages of work. Staff now recommends that Advantec Consulting Engineers, Inc. be
awarded a change order for this project in order to complete the entire traffic re -configuration
project for Downtown Newhall. This firm has delivered several significant projects for the City
and other agencies in Southern California. The references indicated high marks on their
performance and quality of work. Their proposal cost was well within the range of staffs
estimate.
As the implementation process continues and begins to include more investment from the private
sector, the then complete streetscape plans will be incrementally constructed. Much like a
graphic novel artist begins with the lines that define his subject matter and follows up later with
the colorful art that brings life to his work, this striping project will remodel the vehicular
patterns of the project area so that the streetscape will then be able to help bring new life to
Downtown Newhall.
ALTERNATIVE ACTIONS
Other actions as determined by the Redevelopment Agency.
FISCAL IMPACT
Funds for this project will be located in Project No. 52016901-8001 in the amount of $109,500.
Funds for the eventual construction of these improvements have been earmarked by the RDA for
this specific purpose and should be adequate to provide for the completion of this entire project.