HomeMy WebLinkAbout2007-11-13 - AGENDA REPORTS - AIR CONDITIONING PROJ F1014 (2)Agenda Item: 4 CITY OF SANTA CLARITA AGENDA REPORT CONSENT CALENDAR City Manager Approval: Item to be presented by: Peter Henne DATE: November 13, 2007 SUBJECT: CITY HALL AIR CONDITIONING UNIT REPLACEMENT, PROJECT NO. F 1014 - PROJECT ACCEPTANCE DEPARTMENT: Public Works RECOMMENDED ACTION 1. City Council approve and accept the work performed by JCT Mechanical, Inc. on the City Hall Air Conditioning Unit Replacement, Project No. F1014. 2: Direct the City Clerk to file the attached Notice of Completion. 3. Direct staff to release the 10 percent retention 35 days after the Notice of Completion is recorded, provided no stop notices have been filed, as provided by law. J BACKGROUND The City Hall building air conditioning equipment, originally installed in 1986, was over 20 years old. A competitive bid was advertised on April 25, April -29, and May 2, 2007, and awarded to JCT Mechanical, Inc. on June 12, 2007. Five air conditioning package units were installed on September 29, 2007 and October 6, 2007. The installation was performed to the City's satisfaction, and all of the new air conditioning units are now in full operation. The new equipment is much more energy efficient and will result in an undetermined energy savings for the City. ALTERNATIVE ACTIONS Other action as determined by the City Council. FISCAL IMPACT There is no fiscal impact created by the approval of the recommended action. Adequate funding has been budgeted in Account No. F1014601-5161.001 to provide for project costs. ATTACHMENTS Notice of Completion RECORDING REQUESTED BY: City of Santa Clarita Public Works Department WHEN RECORDED MAIL TO: Sharon L. Dawson, CMC, City Clerk City of Santa Clarita 23920 Valencia Boulevard, Suite 304 Santa Clarita, CA 91355-2196 RECORDING FEES EXEMPTED G.C. § 6103 and 27383 pace Above This Line For Recorders Use NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN: 1. The City of Santa Clarita, a municipal corporation, is the owner of the property upon which it has been constructed, of a certain public improvement known as the City Hall Air Conditioning Unit Replacement Project, Project No F1014. 2. The City's address is 23920 Valencia Boulevard, Suite 300, Santa Clarita, California 91355-2196. 3. The general location of said public improvements is 23920 Valencia Boulevard, Santa Clarita California 91355-2196. 4. On June 12, 2007, a contract to construct said public improvement was awarded to JCT Mechanical, Inc.. 5. Work under said contract was completed on October 6, 2007 to the satisfaction of the City Engineer, and was accepted by the City on November 13, 2007. STATE OF CALIFORNIA ) COUNTY OF LOS ANGELES ) ss. CITY OF SANTA CLARITA ) I have read the foregoing Notice of Completion and know its contents. I am the City Clerk of the City of Santa Clarita and am authorized to make this verification for and on its behalf, and I make this verification for that reason. I am informed and believe, and on that ground, allege that the matters stated in the foregoing document are true. I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct. Sharon L. Dawson, CMC, City Clerk Date City of Santa Clarita C200 1 \closeout\ notice of completion.doc