NEWHALL PARK AQUATIC BUILDING REHABILTTATON,
PROJECT NO. M2001 - PROJECT ACCEPTANCE
Public Works
RECOMMENDED ACTION
City Council accept the completion of the Newhall Park Aquatic Building Rehabilitation, Project
No. M2001; direct the City Clerk to file the attached Notice of Completion; direct staff to release
the 5 percent retention 35 days after the Notice of Completion is recorded, provided no stop
notices have been filed, as provided by law; and authorize the City Manager or designee to
execute all documents, subject to City Attorney approval.
BACKGROUND
On February 28, 2006, the City Council awarded the contract for the rehabilitation of the
Newhall Park Aquatics Building to Hanes and Associates in the amount of $807,000.
Construction commenced on March 6, 2006, and was substantially completed
September 6, 2006. The work included demolishing and renovating the interior of the building,
and installing new HVAC, plumbing, and electrical systems. The significant improvements done
to the interior of the building provide a new, safe, and easily accessible facility to the Newhall
community.
The total construction cost was $868,892.87. The construction contract was completed to the
satisfaction of the City Engineer on November 7, 2006. Parks staff moved into the building the
second week in November, and it has been available for public use since that time.
ALTERNATIVE ACTIONS
Other action as determined by the City Council.
FISCAL IMPACT
There is no fiscal impact created by the approval of the recommended action. Adequate funding
has been budgeted in Account Nos. M2001001-8001 and M2001450-8001 to provide for project
costs.