CITY OF SANTA CLARITA
AGENDA REPORT
CONSENT CALENDAR City Manager Approval:
Item to be presented by: Curtis Nay
DATE: July 10, 2007
SUBJECT: 2005-06 COMMUNITY MEDIAN LANDSCAPE PROJECT - SAN
FERNANDO ROAD, PROJECT NO. 130002 - AWARD
CONSTRUCTION CONTRACT
DEPARTMENT: Public Works
RECOMMENDED ACTION
1. City Council approve the plans and specifications, and award the construction contract for the
2005-06 Community Median Landscape Project - San Fernando Road, Project No. B0002, to
R.C. Becker & Son in the amount of $693,525.45, and authorize a 10 percent contingency in
the amount of $69,353.00.
2. Authorize the City Manager or designee to execute all documents, subject to City Attorney
approval.
BACKGROUND
The 2005-06 Community Median Landscape - San Fernando Road project will provide
construction of a raised landscape median from Oak Ridge Drive to Drayton Street. The median
will be constructed with decorative stamped concrete. The stamped concrete design integrates
into the Landscape Maintenance District's standards, and will have the same pattern and color as
the segment of Newhall Ranch Road from Copper Hill Drive to Interstate 5. The median and
landscaping will provide traffic flow improvements and enhance the aesthetics of this heavily
traveled corridor.
A future construction effort to continue the beautification of the corridor from Drayton Street to
the Valencia Boulevard/Soledad Canyon Road intersection will be submitted for funding
consideration at a future date.
Q'PROVED
The property has been annexed into the Landscape Maintenance District to provide for ongoing
maintenance for the median.
On June 21, 2007, the City's Purchasing Division received the following bids for the project:
COMPANY
G. Coast Construction
Environmental Construction
C.S. Legacy Construction
Camarillo Eng. Inc.
Genesis Paving & Landscaping
R.C. Becker & Son
LOCATION BID AMOUNT
Encino, CA
$1,225,286.00
Woodland Hills, CA
$957,595.00
Chino, CA
$794,067.00
Somis, CA
$837,082.00
Sylmar, CA
$785,884.76
Santa Clarita, CA
$693,525.45
The Engineer's Estimate for the construction of this project is $800,000.00. The lowest bid was
submitted by R.C. Becker & Son in the amount of $693,525.45. After reviewing the bid
summary, staff verified the apparent low bidder's contract license, surety companies, and project
references. Based on the investigation, staff recommends awarding the construction contract to
R.C. Becker & Son, the lowest responsive bidder, in the amount of $693,525.45.
ALTERNATIVE ACTIONS
Other action as determined by the City Council.
FISCAL IMPACT
Funds to cover the design and construction costs of the 2005-06 Community Median Landscape
San Fernando Road project have been appropriated to Account No. B0002001-8001. These funds
will adequately provide for construction, along with design, survey, inspection, and material
testing costs.
ATTACHMENTS
Exhibit A - Location Map