HomeMy WebLinkAbout2008-02-26 - AGENDA REPORTS - ANNUAL OVERLAY SLURRY CONTR (2)Agenda Item: CITY OF SANTA CLARITA AGENDA REPORT CONSENT CALENDAR City Manager Approval: Item to be presented by:. Curtis Nay DATE: February 26, 2008 SUBJECT: ANNUAL OVERLAY AND SLURRY SEAL PROGRAM, PROJECTS M0046,, M0049, AND M0052 - PROJECT ACCEPTANCE DEPARTMENT: Public Works RECOMMENDED ACTION 1. City Council accept the completion of the Annual Overlay and,Slurry Seal Program, Projects M0046, M0049, and M0052. 2. Direct the City Clerk to file the attached Notices of Completion. 3. Direct staff to release the remaining retention 35 days after the Notices of Completion are recorded, provided no stop notices as provided by law have been filed. 4. Authorize the City Manager or designee to execute all documents, subject to City Attorney approval. BACKGROUND The Annual Overlay and Slurry Seal project is an integral part of the City's pavement management program. Each year, streets are evaluated and identified for the need for asphalt overlay and slurry seal maintenance treatments. The project resurfaces streets in various areas of the City to provide a smoother ride for traffic, enhance the' appearance of the roadway and surrounding area, and extend the life of the roadway. These projects included the overlay of Soledad Canyon Road, 8th Street, Valley Street, Sand Canyon Road, Rainbow Glen Drive, Shangri-La Drive, Wiley Canyon Road; and several streets in the Valencia Industrial Center. Slurry seal and cape seal for residential areas within the City were also completed. P ED City Council awarded the construction contract to Security Paving Company, Inc. for Projects M0046 and M0049, and to Excel Paving Company for Project M0052. Both of these projects were completed within budget and on schedule to the satisfaction of the City Engineer by December 10, 2007. These projects included the pavement preparation and dig outs, followed by the asphalt rubberized hot mix (ARHM) overlay on the streets. ALTERNATIVE ACTIONS Other action as determined by the City Council. FISCAL IMPACT These projects were completed within budget. Contract costs totaled $7,473,434 for Security Paving Company, Inc., with overhead, construction management, inspection, and administration costs of $303,890. Contract costs totaled $5,513,823 for Excel Paving Company, with overhead, construction management, inspection, and administration costs of $402,562. ATTACHMENTS Notice of Completion M0046 and M0049 Notice of Completion M0052 J RECORDING REQUESTED BY: City of Santa Clarita Public Works Department WHEN RECORDED MAIL TO: Sharon L. Dawson, CMC, City Clerk City of Santa Clarita 23920 Valencia Boulevard, Suite 304 Santa Clarita, CA 91355-2196 RECORDING FEES EXEMPTED G.C. § 6103 and 27383 Space Above This Line For Recorder's Use NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN: 1. The. City of Santa Clarita, a municipal corporation, is the owner in fee, except for the right-of- way upon which it has been constructed, . of a certain public improvement known as the FY 05-06 Annual Overlay and Slurry Seal Program, Projects M0046 and M0049. 2. The City's address is 23920 Valencia Boulevard, Suite 300, Santa Clarita, California 91355-2196. 3. The general location of said public improvements is the Valencia Industrial Center, and various residential areas within the City. 4. On June 13, 2006, a contract to construct said public improvement was awarded to Security Paving Company, Inc. 5. Work under said contract was completed on December 10, 2007 to the satisfaction of the City Engineer, and was accepted by the City on February 26, 2008. STATE OF CALIFORNIA ) COUNTY OF LOS ANGELES ) ss. CITY OF SANTA CLARITA ) I have read the ,foregoing Notice of Completion and know its contents. 1 am the City Clerk of the City of Santa Clarita and am authorized to make this verification for and on its behalf, and I make this verification for that reason. I am informed and believe, and on that ground, allege that the matters stated in the foregoing document are true. I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct. Sharon L. Dawson, CMC, City Clerk Date City of Santa Clarita 05 06 annual overlay\notice of completion 05-06 annual overlay.doc RECORDING REQUESTED BY: City of Santa Clarita Public Works Department WHEN RECORDED MAIL TO: Sharon L. Dawson, CMC, City Clerk City of Santa Clarita 23920 Valencia Boulevard, Suite 304 Santa Clarita, CA 91355-2196 RECORDING FEES EXEMPTED G.C. § 6103 and 27383 Space Above, This Line For Recorder's Use NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN: 1. The City of Santa Clarita, a municipal corporation, is the owner in fee, except for the right-of- way upon which it has been constructed, of a certain public improvement known as the FY 06-07 Annual Overlay and Slurry Seal Program, Project M0052. 2. The City's address is 23920 Valencia Boulevard, Suite 300, Santa Clarita, California 91355-2196. 3. The general location of said public improvements is the Valencia Industrial Center, Sand Canyon Road, and various residential areas within the City. 4. On May 22, 2007, a contract to construct said public improvement was awarded to Excel Paving Company. 5. Work under said contract was completed on November 16, 2007 to the satisfaction of the City Engineer, and was accepted by the City on February 26, 2008. STATE OF CALIFORNIA ) COUNTY OF LOS ANGELES ) ss. CITY OF SANTA CLARITA ) I have read the foregoing Notice of Completion and know its contents. I am the City Clerk of the City of Santa Clarita and am authorized to make this verification for and on its behalf,' and I make this verification for that reason. I am informed and believe, and on that ground, allege that the matters stated in the foregoing document are.true. I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct. Sharon L. Dawson, CMC, City Clerk Date City of Santa Clarita 06 07 annual overlay\notice of completion 06-07 annual overlay.doc