CITY OF SANTA CLARITA
AGENDA REPORT
UNFINISHED BUSINESS City Manager Approval:
Item to be presented by: Robert Newman
DATE: June 24, 2008
SUBJECT: INTERSTATE 5/MAGIC MOUNTAIN PARKWAY
INTERCHANGE PHASE 2 IMPROVEMENTS, PROJECT S 1003 -
EXECUTION OF AGREEMENTS WITH SOUTHERN
CALIFORNIA EDISON (SCE) AND CALIFORNIA
DEPARTMENT OF TRANSPORTATION (CALTRANS), AND
AUTHORIZE INCREASE IN SPENDING AUTHORITY
DEPARTMENT: Public Works
RECOMMENDED ACTION
1. City Council authorize an increase of $10,400,000 to the existing contract for general
contractor Security Paving, Inc. resulting in a total contract price of $36,751,592.
2. Authorize an increase totaling $1,400,000 for the following existing contracts:
• Construction design support services to Willdan in the amount of $650,000, resulting in a
total contract price of $975,000.
• Construction management and inspection services to MNS Engineers, Inc. in the amount
of $550,000, resulting in a total contract price of $650,000.
• Construction survey staking services to Psomas & Associates in the amount of $150,000,
resulting in a total contract price of $450,000.
• Materials testing and soil/asphalt inspection services to Fugro West, Inc. in the amount of
$50,000, resulting in a total contract price of $450,000.
Approve the streetlight installation agreement with Southern California Edison (SCE) in the
amount of $600,000 for the lighting system to be installed on Magic Mountain Parkway and
The Old Road.
4. Authorize the execution of a landscape maintenance agreement with the California
Department of Transportation (Caltrans) to maintain the decorative treatment on the recently
constructed retaining walls at the northbound Magic Mountain Parkway off -ramp.
AP .. PRO
�
5. Authorize the City Manager or designee to execute all documents, subject to City Attorney
approval.
BACKGROUND
The construction of the proposed Interstate 5/Magic Mountain Parkway Interchange
Improvements and the realignment of The Old Road commenced in July 2006, with an adjusted
completion date of fall 2009.
Newhall Land was the lead in regards to the design phase of the project that started in early 2002.
In order to meet the MTA deadline and secure $10,435,000 in MTA funds, the City Council
awarded the construction contract on October 25, 2005, to Security Paving, Inc. During the next
eight months, the plans were finalized by Newhall Land in coordination with Caltrans, Los
Angeles County Department of Public Works (LACDPW), Los Angeles County Sanitation
Districts (LACSD), and the City. These modifications and unanticipated utility conflicts resulted
in a $10,400,000 increase to the construction contract budget with a breakdown as follows:
Work Description
Increased Amount
Reason for Increase
Percentage
Complete
1. Quantity changes from plan
$3,800,000
Plan revisions by approving
revisions after award and delay
agencies after award and
10%
impacts from unanticipated utility
unanticipated utility conflicts.
conflicts.
2. Sewer lining and bypass
$2,200,000
LACSD requirement due to
operations of the existing
design change after award.
100%
30 -inch LACSD main trunk line.
3 Construction of Portland
$1,300,000
LACDPW requirement due to
Cement Concrete pavement at the
design change after award.
50%
intersection of The Old Road and
Magic Mountain Parkway in lieu
of asphalt concrete.
4. Construction of outlet
$1,200,000
LACDPW requirement due to
structure and various other
plancheck comments after award.
80%
stormdrain changes along The
Old Road realignment.
6 Installation of decorative wall
$1,000,000
Newhall Land requested after
treatment on retaining walls along
award
0%
northbound off -ramp and Magic
Mountain Parkway.
7. Construction of landscape
$500,000
Newhall Land requested after
enhancement on The Old Road
award.
0%
and Magic Mountain Parkway.
8. Construction of new sewer
$400,000
Newhall Land requested after
lines on The Old Road and Magic
award
90%
Mountain Parkway
Due to increases in the project from utility conflicts, support services which includes
construction design, field testing, inspection services, and construction management are also
extended by one calendar year, resulting in an increased cost of $1,400,000.
In addition, the streetlight installation on Magic Mountain Parkway and The Old Road requires
the current SCE streetlight system be removed and relocated with SCE installing the lights. This
item authorizes an agreement with SCE to facilitate the work.
All additional costs of the Phase 2 improvements incurred by the City will be reimbursed by
Newhall Land as illustrated in the fiscal impact statement pursuant to the October 25, 2005,
funding agreement between the City and Newhall Land. Subsequent to this agreement, Newhall
Land filed bankruptcy on June 8, 2008, with the court approving an interim order for financing
on June 10. The City has been advised by Newhall Land that the post petition financing will fund
Newhall Land's obligation on this project.
ALTERNATIVE ACTIONS
Other action as determined by the City Council.
FISCAL IMPACT
The amount of approved additional construction costs requested at midyear budget adjustment
was $15,604,227, which increased the City Council approved project costs to $47,700,000. The
October 2005 funding agreement between Newhall Land and the City obligates Newhall Land to
form the Westside Bridge and Thoroughfare District, and to pre -pay its agreed to fair -share
project costs into the District.
Fair -share allocation of project costs have been agreed to as being shared between the City, the
Valencia Bridge and Thoroughfare District, and the Westside Bridge and Thoroughfare District
and are respectively identified as:
All project costs in excess of the City's agreed to fair share of $10,435,000, including but not
limited to $30,138,556, will be borne by the Valencia Bridge and Thoroughfare District and
Westside Bridge and Thoroughfare District, or Newhall Land, per the executed funding
agreement. Adequate funds have been budgeted in Expenditure Account S1003260-5161.001 and
S1003303-5161.001.
ATTACHMENTS
Exhibit "A" - Location Map
CITY
VALENCIA B&T
WESTSIDE B&T
DISTRICT
DISTRICT
First $30,138,556
34% - $10,435,000
22% - $6,502,173
44% - $13,201,383
(percentage share/total)
Over $30,138,556
$0
50%
50%
All project costs in excess of the City's agreed to fair share of $10,435,000, including but not
limited to $30,138,556, will be borne by the Valencia Bridge and Thoroughfare District and
Westside Bridge and Thoroughfare District, or Newhall Land, per the executed funding
agreement. Adequate funds have been budgeted in Expenditure Account S1003260-5161.001 and
S1003303-5161.001.
ATTACHMENTS
Exhibit "A" - Location Map