HomeMy WebLinkAbout2009-06-23 - AGENDA REPORTS - CONCRETE REHAB PGM PROJ ACCEPT (2)CONSENT CALENDAR DATE: SUBJECT: DEPARTMENT Agenda Item: CITY OF SANTA CLARITA AGENDA REPORT City Manager Approval Item to be presented by: June 23, 2009 V V Curtis Nay /C. 2008-09 ANNUAL CONCRETE REHABILITATION PROGRAM, PROJECTS M0064, M0065, AND T0027 - PROJECT ACCEPTANCE Public Works RECOMMENDED ACTION City Council accept the completion of the construction contract executed by Toro Enterprises Inc. for the 2008-09 Annual Concrete Rehabilitation Program, Projects M0064, M0065, and T0027. 2. Direct the City Clerk to file the attached Notice of Completion. 3. Direct staff to release the retention amount 35 days after the Notice of Completion is recorded, provided no stop notices have been filed, as provided by law. BACKGROUND On November 25, 2008, the City Council awarded a construction contract to Toro Enterprises Inc. for the 2008-09 Annual Concrete Rehabilitation Program, Projects M0064, M0065, and T0027. The purpose of these projects is to improve and upgrade sidewalks and drainage systems Citywide by removing and replacing the existing damaged concrete sidewalks and curb and gutter systems. Damage is typically due to uplifting caused by tree root infiltration and/or pavement settlement. The construction of these projects (M0064, M0065, and T0027) was combined under one contract to ensure the most efficient use of the available budget. By combining these projects, the City was able to remove and replace 38,237 square feet of sidewalk, 5,156 square feet of driveway approaches, 2,509 linear feet of curb and gutter, and install 33 new curb ramps at various intersections Citywide. APPROVED The City took advantage of the construction contract's low unit costs and used the project's contingency savings to repair additional curb, gutter, and sidewalks Citywide. Twenty-one additional access ramps were also installed to help satisfy Americans with Disabilities Act requirements and benefit the residents of the City of Santa Clarita. Construction was completed on time and within budget on May 6, 2009, to the satisfaction of the City Engineer. ALTERNATIVE ACTIONS Other action as determined by the City Council. FISCAL IMPACT Funds totaling $651,338 were approved and budgeted in the current fiscal year. These funds adequately provided for all three construction projects. ATTACHMENTS Notice of Completion Locations List RECORDING REQUESTED BY: City of Santa Clarita Public Works Department WHEN RECORDED MAIL TO: Sharon L. Dawson, MMC, City Clerk City of Santa Clarita 23920 Valencia Boulevard, Suite 304 Santa Clarita, CA 91355-2196 RECORDING FEES EXEMPTED G.C. § 6103 and 27383 NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN: The City of Santa Clarita, a municipal corporation, is the owner in fee, except for the right-of-way upon which it has been constructed, of a certain public improvement known as 2008-09 Annual Concrete Rehabilitation Program, projects M0064, M0065, and T0027. The City's address is 23920 Valencia Boulevard, Suite 300, Santa Clarita, California 91355-2196 The general location of said public improvements is Citywide. 4. On November 25, 2008, a contract to construct said public improvement was awarded to Toro Enterprises Inc. Work under said contract was completed on May 6, 2009, to the satisfaction of the City Engineer, and was accepted by the City on June 23, 2009. Sharon L. Dawson, MMC, City Clerk City of Santa Clarita STATE OF CALIFORNIA ) COUNTY OF LOS ANGELES ) ss. CITY OF SANTA CLARITA ) I have read the foregoing Notice of Completion and know its contents. I am the City Clerk of the City of Santa Clarita and am authorized to make this verification for and on its behalf, and I make this verification for that reason. I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and was duly and regularly ordered to be recorded in the office of the Los Angeles County Recorder. Sharon L. Dawson, MMC, City Clerk City of Santa Clarita Date 3 FISCAL YEAR 2008-09 ANNUAL CONCRETE REHABILITATION PROGRAM PROJECTS M0064, M0065, AND T0027 LOCATIONS LIST Abelia Road Adamsboro Drive Altamere Avenue Avenue Stanford Bakerton Avenue Bellerive Drive Calvello Drive Camp Plenty Road Carla Court Crossglade Avenue Decoro Drive Delight Street Delight Street at Felbridge Street Felbridge Street Florabunda Road Foxlane Drive Guadilamar Drive Haxton Drive La Veda Avenue Lyons Avenue Mendoza Drive Nearbrook Street North Oaks Park Old Course Way Parklane Estates Parkvale Drive Plumwood Avenue Royal Vista Court Rye Canyon Road Santa Clarita Road Seco Canyon Road Sierra Highway Shine Drive Soledad Canyon Road Soledad Canyon Road at Honby Street Stillmore Street T-2 Old Orchard Paseo T-3 Valencia Hills Paseo T-4 Valencia Meadows Paseo T-46 North Bridge Paseo T-5 Valencia Glen Paseo T-7Central North Valley Paseo T-6South Valley Paseo Tamarack Lane Tambora Drive Valencia Summit Park Valley Street Via Barra Via Pacifica Via Princessa Vicci Street Walnut Springs Avenue Wellhaven Street Zone 18 Valencia Mall Paseo