HomeMy WebLinkAbout2012-04-24 - AGENDA REPORTS - NEWHALL AVE IMPROV PROJ T2003 (2)CONSENT CALENDAR
DATE:
SUBJECT:
DEPARTMENT
Agenda Item: 5
CITY OF SANTA CLARITA
AGENDA REPORT
City Manager Approval
Item to be presented by:
April 24, 2012
Curtis Nay
NEWHALL AVENUE PEDESTRIAN IMPROVEMENTS,
PROJECT T2003 - PROJECT ACCEPTANCE
Public Works
RECOMMENDED ACTION
1. City Council accept the completion of the Newhall Avenue Pedestrian Improvements, Project .
T2003.
2. Direct the City Clerk to file the attached Notice of Completion.
3. Direct staff to release the 10 percent retention balance 35 days after the Notice of Completion
is recorded, provided no stop notices have been filed, as provided by law.
4. Authorize an expenditure in the amount of $85,000 to Southern California Regional Rail
Authority for the design of the pedestrian railroad signal as part of Phase II of this project.
BACKGROUND
On August 23, 2011, City Council awarded a contract to construct the Newhall Avenue
Pedestrian Improvements, Project T2003, to Hondo Engineering, Inc. Construction began on
October 17, 2011. The project "consisted of construction of pedestrian improvements on the east
side of Newhall Avenue from Sierra Highway to 2nd Street. The goal of the project was to
enhance pedestrian safety and beautification to this heavily used pedestrian corridor.
Work included construction of sidewalk, access ramps, and driveways complying with the
Americans with Disabilities Act and the construction of curb and gutters. The project scope also
included the installation of landscaped parkway, trees, and irrigation. These improvements
provide a separation from the sidewalk and traffic in addition to providing beautification to this
heavily used pedestrian corridor along Newhall Avenue.
PPR�VED
The construction contract was completed within budget to the satisfaction of the City Engineer
on March 5, 2012.
The expenditure amount of $85,000 to Southern California Regional Rail Authority (SCRRA) is
to fund the design of Phase I1 of this project. This amount has been appropriated in Expenditure
Account T2003302-5161.001. Phase II will construct a signalized pedestrian crossing over the
railroad tracks at Railroad Avenue and Newhall Avenue to 3rd Street. Staff continues to work
with SCRRA on approval for the proposed improvements in SCRRA's right-of-way. Upon
completion of Phase II, the project will provide a continuous sidewalk from Sierra Highway to
Railroad Avenue.
ALTERNATIVE ACTIONS
Other action as determined by the City Council.
FISCAL IMPACT
Adequate funds for Phase I from Via Princessa Bridge and Thoroughfare Fund 302, Landscape
Maintenance District Fund 357, and Proposition C Local Return Fund 260 were appropriated in
Expenditure Accounts T2003302-5161.001, T2003357-5161.001, and T2003260-5161.001. The
project's budget adequately provided for all project costs, including construction management,
inspection, and administration. The final contract cost for Hondo Engineering, Inc. is $408,850,
which is within the original City Council authorized contract spending authority of $471,977.
Adequate funds for design of Phase Il have been appropriated in Expenditure Account
T2003302-5161.001.
ATTACHMENTS
Notice of Completion
Location Map
SCRRA Letter
2
RECORDING REQUESTED BY:
City of Santa Clarita
Public Works Department
WHEN RECORDED MAIL TO:
Sarah P. Gorman, City Clerk
City of Santa Clarita
23920 Valencia Boulevard, Suite 304
Santa Clarita, CA 91355-2196
RECORDING FEES EXEMPTED
G.C.§6103 and 27383
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN:
The City of Santa Clarita, a municipal corporation, is the owner in fee, except for the right-of-way
upon which it has been constructed, of a certain public improvement known as Newhall Avenue
Pedestrian Improvements, Project T2003.
2. The City's address is 23920 Valencia Boulevard, Suite 300, Santa Clarita, California 91355-2196.
The general locations of said public improvements are the east side of Newhall Avenue from Sierra
Highway to 2nd Street.
4. On August 23, 2011, a contract to construct said public improvement was awarded to Hondo
Engineering, Inc., 42443 27th Street West, Lancaster, CA 93536.
Work under said contract was completed on March 5, 2012, to the satisfaction of the City Engineer,
and was accepted by the City on April 24, 2012.
Sarah P. Gorman, Esquire, City Clerk
City of Santa Clarita
STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES ) ss.
CITY OF SANTA CLARITA )
I have read the foregoing Notice of Completion and know its contents. I am the City Clerk of the City of
Santa Clarita and am authorized to make this verification for and on its behalf, and I make this verification
for that reason. I declare under penalty of perjury under the laws of the State of California that the foregoing
is true and correct and was duly and regularly ordered to be recorded in the office of the Los Angeles County
Recorder.
Sarah P. Gorman, Esquire, City Clerk Date
City of Santa Clarita
3
r
METROLINK
October 24,• 2011
Kris Markarian
City of Santa Clarita Senior Engineer
23920 Valencia Blvd., Suite 300
Santa Clarita, CA 91355
Southern California Regional Rail Authority
File: #S0000469
Project: #860538
Reference: Newhall Avenue Railroad Pedestrian Crossing Gap Closure
Subject: Request for Second Deposit for Engineering Services
Dear Ms. Markarian:
This letter is to request for a second deposit in the amount of $85,000 to continue the support and
involvement of SCRRA in Santa Clarita's Newhall Avenue Pedestrian Crossing Gap Closure
Project.
Per your authorization via attached email sent on June 2, 2011 from Mr. John Spalione, SCRRA
has procured the consulting services of Xorail to provide a railroad signal design for this project.
The design has reached a milestone of sixty percent completion. As a result, we have exhausted
the initial deposit of $15,000 received in February 2011 and are requesting a second deposit of
$85,000 to complete the design work and to support the development of Construction and
Maintenance Agreement that will enable the construction of the project.
The. deposit should be in the form of a check made payable to the Southern California Regional
Rail Authority.
If you have any questions, please contact Ms. Kim Chan by phone at (213) 435-1827 or via e-
mail at chank(i�scrra.net.
Sincerely,
Patricia Watkins
Assistant Director, Public Projects
Encl: Email from Spalione authorizing design services
Cc: Edward Enriquez, SCRRA
John Spalione, Santa Clarita
51