RECOMMENDED ACTION
City Council:
1. Direct staff to execute a Participant Agreement with Los Angeles County (County) and award
contract to Los Angeles County for an amount not to exceed $83,200 for the purchase of
high-quality aerial imagery and elevation datasets.
2. Authorize the City Manager or designee to execute all contracts and associated documents,
contingent upon the appropriation of funds by the City Council in the annual budget for such
Fiscal Year, and execute all documents subject to City Attorney approval.
BACKGROUND
In May 2008, the City Council authorized staff to enter into an agreement with Los Angeles
County to participate in the Los Angeles Region hnagery Acquisition Consortium (LAR -IAC).
This program, organized by the County of Los Angeles Chief Information Office, provided the
City with high-quality and accurate aerial imagery and elevation data products, and was formed
with the purpose of making these aerial images available at a cost that would be far less if
acquired through independent acquisition. If the City were to independently contract for data
comparable to what is provided through the County's program, the cost to the City would be
almost 80% more.
Staff is recommending the City continue to participate in the LAR -IAC Program to obtain
updated aerial imagery of the Santa Clarita Valley. Participants in the Consortium include the
��
County of Los Angeles, more than 25 additional cities (such as Glendale, Pasadena, Los Angeles,
and Torrance), and public -sector organizations (including Caltrans).
As in 2008, the project will capture digital aerial imagery data and related photogrammetric
services for the 4,100 -square -mile Los Angeles County area. Consortium members will be
provided with highly accurate digital aerial imagery and other data with Geographic Information
System (GIS), web -mapping systems, computer-aided design (CAD), and engineering design
applications. Delivery includes near -infrared imagery, oblique imagery, elevation data, and
topography line data. Staff expects to receive this data prior to the end of calendar year 2014.
ALTERNATIVE ACTIONS
1. Do not approve the award of this contract.
2. Other alternatives as identified by Council.
FISCAL IMPACT
Sufficient funds for this expenditure were anticipated and appropriated by the City Council as
part of the Fiscal Year 2014-15 budget adoption process.
ATTACHMENTS
LAR-IAC4 Agreement
ATTACHMENT III
PARTICIPANT AGREEMENT BY AND BETWEEN THE
COUNTY OF LOS ANGELES
AND PARTICIPATING ENTITIES FOR THE
LOS ANGELES REGION - IMAGERY ACQUISITION CONSORTIUM 4
("LAR-IAC4") PROJECT
This Participant Agreement (Agreement) is made and entered into by and between the
County of Los Angeles (County), a political subdivision of the State of California, and City of
Santa Clarita, a California city, special district, or agency. Each individual city, district, or
agency is referred to herein individually as a "Participating Entity" and collectively as the
"Participating Entities". The County and the Participating Entities are hereinafter referred to
collectively as the "Parties" and each individually as a 'Party".
A. WHEREAS, County has planned to acquire new digital orthogonal and oblique
aerial imagery in the winter of 2013-2014 Project;
B. WHEREAS, County has become aware that various Participating Entities have
similar projects currently underway or plans to undertake similar projects in the near future;
C. WHEREAS, in order to avoid the duplication of efforts and costs by the Parties,
the Parties desire to pool their resources to collectively undertake the Project; and
D. WHEREAS, the Parties intend to participate in the Project upon the terms and
conditions set forth herein below.
NOW, THEREFORE, in consideration of the mutual covenants herein set forth
and the mutual benefits to be derived therefrom, the Parties agree as follows:
1. Purpose
The purpose of this Agreement is to provide a vehicle for the collective
participation in the Project by the Parties. The Project shall focus on the acquisition of
certain aerial imagery digital data which may include, but are not limited to, products listed
in Attachment A ("Digital Data"). It is the intent of the Parties that Digital Data shall be
acquired under this Agreement for areas within the County of Los Angeles covered by the
jurisdictions of the Parties.
Page 12
LAR-IAC4 Participant Agreement
-f
2. Responsibilities of the County
A. Identify and provide specifications for Digital Data (or their derivatives) to
the contractors hired to complete the Project.
B. Develop all necessary procurement documents for necessary services to
be provided by one or more qualified contractors in connection with the
acquisition and administration of the Digital Data.
C. Select the most qualified contractor or contractors to provide the
necessary services in connection with the acquisition and administration of the
Digital Data and thereafter, manage the entire acquisition and administration of
the Project.
D. With the assistance of one or more selected contractors, provide Quality
Control (QC) for all Digital Data delivered under this Agreement.
E. Arrange for the delivery of the Digital Data (or portions thereof) to the
Participating Entity upon Project completion.
F. Provide monthly reports to the Participating Entities on the status of the
Project.
3. The Participating Entity Has the Right to
A. Participate in identifying and providing technical specifications for the
Digital Data (or their derivatives).
B. Provide currently available geodetic points (with necessary standards and
accuracy) for County's QC process.
D. Acquire additional digital aerial products from the contractors through this
agreement, provided that a Statement of Work is attached as Exhibit A.1. County
assumes no liability for the completion of these products.
4. Mutual Responsibilities; Maximum Contribution
The Parties shall be mutually responsible for the following:
A. Financing the acquisition and administration of the Digital Data including,
but not limited to, costs related to QC and the subsequent distribution thereof.
The total cost of such acquisition and administration (Total Cost) shall be
allocated among the Parties and the Participating Entities. The portion of the
Total Cost allocated to a Party hereunder shall be hereinafter referred to as the
Party's "Maximum Contribution." Each Participating Entity will transfer its
Maximum Contribution to a special trust account which has been established by
the County for this Project (Trust Account) and as further described in Paragraph
5 of this Agreement.
Page 13 LAR-IAC4 Participant Agreement
The Maximum Contribution of the Participating Entity shall be $83,201.66.
B. In the event the Project is terminated for any reason before the execution
of any contract with a contractor for the provision of goods and/or services in
connection with the Project, each Participating Entity shall be refunded its
Maximum Contribution (or such portion of the Maximum Contribution as shall
have been paid to the County by such Participating Entity) in its entirety.
5. Payment of Maximum Contribution; Administration of Trust Account
A. A Participating Entity shall have the following options in paying its
Maximum Contribution to the County hereunder:
The Participating Entity may elect to pay its Maximum Contribution
to County in its entirety upon execution of this Agreement.
i. The Participating Entity may elect to pay its Maximum Contribution
to County as follows: (a) fifty percent (50%) of the Maximum
Contribution upon its execution of this Agreement; and (b) fifty
percent (50%) upon delivery of the Digital Data to the Participating
Entity.
B. The Trust Account established by the County in connection with the
Project, shall be subject to the following:
All funds held in the Trust Account shall be used solely for the
payment of contractors selected by County to provide goods and
services in connection with the Project.
Any funds held in the Trust Account not expended upon the
completion of the Project or the termination of this Agreement shall
be held, administered, and returned to Parties based on their
prorated contribution to the total costs of the Project.
6. General Terms and Conditions
Page 14
A. This Agreement shall take effect upon execution and shall remain in effect
through final delivery of all Digital Data and through the duration of the license -
use term.
B. The term of this Agreement may be extended by an Amendment to this
Agreement.
C. It is the intention of the Parties that the Participating Entity shall receive,
with the delivery of the Digital Data, an unlimited irrevocable perpetual, royalty -
free license. The license may be used to, modify, edit, reuse, reproduce,
LAR-IAC4 Participant Agreement
Page 15
translate, create derivatives, compile, other works based upon the Digital Data,
and combine the data with other contents selected by the Participating Entity in
its own operation, with an unlimited number of seats, including, but not limited to
Internet and intranet applications, copying, and printing.
D. The Participating Entity shall have the right to transfer, sublicense, and
distribute any form of media either now known or hereinafter desired the Digital
Data to its subcontractors or consultants on projects which are outsourced from
its own operations. In this connection, the Participating Entity shall require each
subcontractor or consultant to whom the Digital Data is transferred to execute a
written acknowledgement and agreement to abide by such Participating Entity's
license to use the Digital Data. Such acknowledgement and agreement is
provided in Attachment B (Authorized User Confidentiality and Non -Disclosure
Agreement).
E. Notwithstanding any provision of this Agreement to the contrary, a
Participating Entity shall not have the right to sell, resell, or otherwise transfer its
license to use the Digital Data to any other person or entity.
F. This Agreement may be amended or modified by County only after
collaboration and consultation with the Participating Entities.
G. Nothing in this Agreement shall be construed to give any person or entity,
other than the Parties hereto, any legal or equitable right, remedy, or claim under
or in respect to this Agreement or any provision herein contained. This
Agreement and the provisions hereof are intended to be and are for the sole and
exclusive benefit of the Parties.
H. No Party may terminate its participation under this Agreement after the
execution of contract(s) for the acquisition of the Digital Data without the prior
written consent of County.
I. Any other California city, special district, or agency may become a
Participating Entity under this Agreement if
(i) Such entity executes this Agreement, and
(ii) Such entity makes its Maximum Contribution to County as provided
for under this Agreement. Any such contribution shall be deposited
into the Trust Account and administered in accordance with sub-
paragraph 5.6 of this Agreement.
J. This Agreement may be executed in counterparts and the signed
counterparts shall constitute a single instrument. The signatories to this
Agreement represent that they have the authority to bind their respective party to
this Agreement.
LAR-IAC4 Participant Agreement
r�
IN WITNESS WHEREOF, the parties have executed this Participant Agreement
for the Los Angeles Region — Imagery Acquisition Consortium 4 Program on the date
indicated below.
PARTICIPANT ENTITY
City of Santa Clarity
By:
Date:
Page 16
COUNTY OF LOS ANGELES
CHIEF INFORMATION OFFICE
By:
Richard Sanchez
Chief Information Officer
Date:
LAR-IAC4 Participant Agreement
N
ATTACHMENT IV
DIGITAL DATA
All data will be acquired in 2014 unless otherwise noted.
Digital Aerial Orthogonal Imagery
• 1 foot pixel resolution for Urban Areas from 2012
• 1 foot pixel resolution for Urban Areas from 2013
• 4 inch pixel resolution for Areas 1 and 3 (see Map 1 below) from 2014
• 1 foot pixel resolution for Area 2 (see Map 1 below) from 2014
Digital Aerial Oblique Imagery
• 4 inch pixel resolution (neighborhood and community shots) for Area 1 (see Map 2
below)
• 12 inch pixel resolution (community shots only) for Area 2 (see Map 2 below)
Building Outlines
• Building outlines for all of Los Angeles County over 400 square feet, including status
information (added, demolished, updated).
Digital Elevation Data
• Digital Elevation Model (DEM) with 2.5 foot spacing.
• Digital Terrain Model (DTM) with 2.5 foot spacing.
• Digital Surface Model (DSM) with 2.5 foot spacing.
• 1 -foot contours derived from LIDAR in the urban Areas.
• 2 -foot contours derived from LIDAR in the National Forest.
Derived Datasets
• Normalized Difference Vegetation Index (NDVI).
• Solar Model.
• Raster Tree Canopy Model.
• Raster Building data Model.
• Hillshade based upon the 2.5 foot DEM.
• Slope based upon the 2.5 foot DEM.
• Raster Height Model.
Map 1: Areas for Orthogonal Imagery Products
VENN
COUNT/
VEWUIU
COUNT!
Legend
Area t - a mph
- Area 2. f foot
Ortho Imagery Grid
OLas Angeles County Boundary
Page 18
Los Angeles Region -
Imagery Acquisition Consortium
Project Areas and Tile Grid
-t7r:,
ORANGE
COUNW
A
LARICIC
LOS ANON£S COUNTY
�,3lauenl ditA R.M
Mw Temples
Lw Arye CAW12
Maar 5 2
LAR-IAC4 Project Area Maps
VENTURA
COUNTY
Map 2: Areas for Oblique Imagery Products
NERN
COUNTY
n
ORANGE
COUNTY
COUNTY
t Capture Type
CommuMy 2 -Way. No NeghE , 040
CommuMy 2 -Way. NegNEo0 4My
CammuMy 2-Wey. NeighE rhoW 6V ft
COmmuMy 4 -My. W Nega[gTOotl
CommuMy 4 -Way, NegMareooE 4-WWYy
Page 19
LAR-IAC4 Project Area Maps
Los Angeles Region -
Imagery Acquisition Consortium
LAR�CIC
Oblique Imagery Grid
and Capture Types
LOSAWEf SCQUNI
(kpW .NRe9xxialgarvm'g '
(w Argabs, CA 90012
�A,
AWM 13, W19
LAR-IAC4 Project Area Maps