HomeMy WebLinkAbout2014-01-14 - AGENDA REPORTS - NEWHALL COMMUNITY CENTER PROJ (2)Agenda Item: 3
CITY OF SANTA CLARITA
AGENDA REPORT
CONSENT CALENDAR City Manager Approval:j44, —
Item to be presented by: Chris Price
DATE: January 14, 2014
SUBJECT: NEWHALL COMMUNITY CENTER ROOF REPLACEMENT
AND NEWHALL COMMUNITY CENTER ACOUSTIC SYSTEM
PROJECTS - AUTHORIZE COMBINING PROJECTS
DEPARTMENT: Parks, Recreation, and Community Services
RECOMMENDED ACTION
City Council
1. Authorize the combining of the Newhall Community Center Roof Replacement Project -
Project M3012 with the Newhall Community Center Acoustic System Project - Project P2010
2. Increase the expenditure authority on the construction contract for the combined project from
$174,275 to $196,037.
3. Authorize the following budget transfers: $53,992 from account P2010601-5161.001 to
account M3012601-5161.001; $12,000 from account F3019723-5161.001 to account
M3012723-5161.001; $5,390 from account M3013305-5161.001 to account
M3012305-5161.001.
BACKGROUND
The Newhall Community Center, a 17,000 square foot facility that has served the surrounding
community since January of 2006, contains a large multi-purpose room, boxing arena, meeting
rooms, classrooms, and staff offices. In recent years, the flat roofing system that covers a portion
of the building began to leak during even moderate rain events. The leaks were significant
enough that funds in the amount of $110,000 were appropriated during the Fiscal Year 2012-13
budget for the replacement of the roof.
With approval of the roofing project in the Fiscal Year 2012-13 budget, staff secured the
professional services of James Mickartz Architecture to develop a project scope. Using the
available as -built construction documents, the architect prepared plans for a new roof membrane
for the flat portion of the roof over the classroom areas. The plans and specifications were
completed in February of 2013 at a cost of $10,725.
The project was advertised for public bid in April of 2013 with a remaining construction budget
of $99,275. Bids were opened on May 16, 2013, and John Burgeson Contractors, Inc. was
deemed the lowest responsible bidder with a bid of $146,510. Staff evaluated several options to
bring the project in line with the available budget, including rebidding the project and selecting a
less expensive roofing material. Neither of these options would guarantee significant savings.
Staff determined the most prudent choice would be to review other related capital project budgets
to determine if any savings might be available to close the roofing budget shortfall.
The FY 2013-14 budget contained another project at the same facility, the Newhall Community
Center Acoustic System Project -Project P2010. This project was conceived to address the poor
acoustics in the large multipurpose room and had an approved budget of $75,000. After
consulting with an acoustical expert with experience on similar projects, a design was developed
that involved the strategic placement of acoustic panels on the four walls of the room at a cost of
approximately $23,000, significantly less than the project budget.
With John Burgeson Contractors ready to mobilize labor and equipment to the site for the roof
project, staff saw the opportunity to complete both projects under one contract while remaining
within the combined budget and under the City Manager's purchasing authority for an individual
project. Staff approached the City Manager to outline the funding issues and the timing
challenges inherent with rebuilding the roof prior to the coming winter and with minimal impact
to the use of the Center. The City Manager approved the concept of combining the projects and
staff mobilized immediately so that a contract could be awarded and work completed before the
rainy season. The newly combined construction contract was written for $174,275, which was
the remaining budget for the roof construction and the total budget for the acoustic panels.
The roofing portion of the project began in August, 2013. Upon removal of the old roofing
material, it became apparent that the insulation layer immediately underneath the roofing
membrane was of a different type and thickness than shown on the as -built plans which were
used in developing the replacement roofing design. These unforeseen conditions necessitated a
change order for removal of all of the existing flat roofing insulation and the installation of
replacement material. This was necessary to achieve the desired slope of the roof, provide the
needed thermal properties, and to ensure proper drainage. The amount of this change order was
$21,761.65. Staff authorized the work in order to assure the project would be completed
correctly, eliminate the potential for additional contractor costs due to delays, and to minimize
Community Center program disruptions. The work was completed in September before the
threat of winter rains.
The result of the change order together with the merging of the two previously separate projects
was that the combined contract exceeded the City Manager's purchasing authority. When staff
2
authorized the contractor to move forward with the change order, it was based on the belief that
doing so would be the most cost effective method to accomplish the project goals of improving
the Community Center and enhancing programming opportunities in a timely manner. While it is
always staffs intention to stay within project budget and spending authority, this unique
combination of factors created a situation that now requires City Council to ratify the expenditure
by approving these changes.
Since the completion of the roofing repair, the acoustic panel portion of the project was
completed successfully without any more change orders. In addition to the acoustic panels, staff
was able to re -use the gym wall padding from the Sports Complex that was being replaced in a
separate project. The padding greatly enhances the look, sound, and use possibilities of the
Newhall Community Center, and substantially reduced the amount of waste going to the overall
waste stream. The roof project is also complete, and has eliminated all of the previous water
issues that were present with the former roof.
ALTERNATIVE ACTIONS
As identified by the City Council.
FISCAL IMPACT
No additional funds need to be appropriated to this project, and there are no additional fiscal
impacts of this action. All funds for the projects have been appropriated. The budget shortfall
will be rectified by the requested budget transfers, which will also place the funds into the correct
project accounts.
3